Bhatwari-Barsu Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
3123 |
Sanction Cost: |
314.91 lakh |
Length:
|
2.250 KM. |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 82
Package Name: 
UDRP/PWD/01/31/RD/071
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 20-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/31/RD/071
Contractor Name: Parth Construction
|
Start Date: 27-02-2016
Intended Completion Date: 28-02-2018
Original End Date: 26-12-2016 |
Total Bond Cost: 35940985.37 (359.41 lakh)
Variation Cost: 29465244.98 (294.65 lakh) Hence Total Bond Cost is 65406230.35 (654.06 lakh)
|
Sub Project Cost: 201.89 lakh
Variation Cost of Sub Project: 10671411.76 (106.71 lakh)
Total Sub Project Cost:
308.6 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2282190 for 127 days
LD Analysis for Milestone2: calculated LD is Rs 3899490 for 217 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.25 KM | 18.04 | 27-02-2016 | 15-06-2017 | 2.25 KM | 2.25 KM | 6.51 | 18.04 | 2. | R/Wall, B/ Wall Type Protection works | 1201.00 m | 142.82 | 27-02-2016 | 15-06-2017 | 1201.00 m | 1201.00 m | 51.54 | 142.82 | 3. | G-2 | 0.65 KM | 16.25 | 15-05-2017 | 20-08-2017 | 0.65 KM | 0.65 KM | 5.86 | 16.25 | 4. | G-3 | 1.50 KM | 11.96 | 10-08-2017 | 20-09-2017 | 1.50 KM | 1.50 KM | 4.32 | 11.96 | 5. | PC/CC i/c Prime Coat, Tack Coat | 2.25 KM | 27.50 | 01-10-2017 | 30-11-2017 | 2.25 KM | 2.25 KM | 9.92 | 27.50 | 6. | Culverts/Scupper | 4.00 No | 15.47 | 15-11-2017 | 25-02-2018 | 4.00 No | 4.00 No | 5.58 | 15.47 | 7. | longitudinal Drain | 1850.00 m | 35.58 | 16-08-2017 | 15-01-2018 | 1850.00 m | 1850.00 m | 12.84 | 35.58 | 8. | Crash Barrier | 0.00 m | 0.00 | 15-01-2017 | 15-05-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 9. | Parapet | 300.00 No | 8.31 | 01-09-2017 | 30-09-2017 | 300.00 No | 300.00 No | 3 | 8.31 | 10. | Road Furniture | 30.00 No | 1.19 | 01-11-2016 | 28-02-2018 | 30.00 No | 30.00 No | 0.43 | 1.19 |
Total Amount: |
277.12 |
|
100 |
277.12 |
|
Remarks:
No Remarks
Work Program Made On:
18-05-2016 } ?>
Updation of work program on:
28-03-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-July-2016 | 25.71 lakh | 2. | 14-September-2016 | 5.13 lakh | 3. | 14-October-2016 | 15.00 lakh | 4. | 16-December-2016 | 0.67 lakh | 5. | 02-March-2017 | 23.75 lakh | 6. | 17-June-2017 | 39.59 lakh | 7. | 31-July-2017 | 6.92 lakh | 8. | 29-August-2017 | 1.08 lakh | 9. | 13-October-2017 | 20.64 lakh | 10. | 20-November-2017 | 7.69 lakh | 11. | 27-November-2017 | 10.00 lakh | 12. | 23-December-2017 | 1.13 lakh | 13. | 15-January-2018 | 56.51 lakh | 14. | 17-February-2018 | 3.34 lakh | 15. | 26-July-2018 | 36.39 lakh | 16. | 29-September-2018 | 55.99 lakh |
Total |
309.54 lakh |
% Payment | 100.3 % |
|
Advance Amount: 12.06 lakh
Recovered Amount: 12.06 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 315 No. of Test Done : 588 No. of Test Passed : 561 No. of Test Failed : 27 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.17 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 92 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-12-2017 | Ch 1725 | Debris disposal | Ramesh Chand | EE | UDRP R&B Uttarkashi | See Pic |
2. | 16-11-2017 | Ch 0/1 | P.C work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 05-11-2017 | Ch 0.200 | Checking of | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
4. | 30-10-2017 | 1/35 | Check road safety parapet specification | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
5. | 26-10-2017 | 0/25 | Measuring pc work | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
6. | 26-10-2017 | 0/27 | Measuring pc work | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
7. | 16-10-2017 | Ch 0.650 | Checking of P.C thickness by SE WB PWD Tehri | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
8. | 16-10-2017 | Ch1+200 | Checking of pri mix carpet width with EE sir | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
9. | 15-10-2017 | Ch0+425 | Checking of pri mix carpet width | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
10. | 04-10-2017 | Ch 1.300 | P.C work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
11. | 29-09-2017 | Ch 0.675 | Checking of grading of G2 | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
12. | 29-09-2017 | Ch 0.675 | Checking of WBM thickness by EE | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
13. | 29-09-2017 | Ch 2.100 | Checking of PC thickness by E.E | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
14. | 28-09-2017 | Ch 1.800 | P.C work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
15. | 19-06-2017 | 2/1 | Coolie walll ...in progresss | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
16. | 07-05-2017 | Ch0.550 | Hill side cutting and grade preparation | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
17. | 08-02-2017 | Ch 0.050 to 1.000 | Plum work for R/W | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
18. | 02-02-2017 | Plum block km 0/50 | Plum block work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
19. | 24-01-2017 | Plum block km 0/50 to 0/100 | Plum block work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
20. | 23-01-2017 | 0/2 | Plum block for protection in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
|
|