Bhadrasu Ramalgaon Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
3121 |
Sanction Cost: |
235.23 lakh |
Length:
|
2.770 KM. |
District: |
Uttarkashi |
Block: |
Mori |
Constituency: |
Purola |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 85
Package Name: 
UDRP/PWD/01/33/RD/074
Tender Date: 29-12-2014
Current Status: Agreement signed
Achieved on Date: 18-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/33/RD/074
Contractor Name: Devendra Construction
|
Start Date: 24-06-2015
Intended Completion Date: 07-01-2017
Original End Date: 23-09-2016 |
Total Bond Cost: 19635953.97 (196.36 lakh)
Variation Cost: 2714236.82 (27.14 lakh) Hence Total Bond Cost is 22350190.79 (223.5 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 765804 for 78 days
LD Analysis for Milestone2: calculated LD is Rs 1119252 for 114 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.80 KM | 14.68 | 01-07-2015 | 31-03-2016 | 2.80 KM | 2.80 KM | 7.85 | 14.68 | 2. | R/Wall, B/ Wall Type Protection works | 1693.00 m | 59.60 | 01-07-2015 | 31-03-2016 | 1693.00 m | 1693.00 m | 31.88 | 59.60 | 3. | GSB/RBI/G-1 | 0.00 KM | 0.00 | 01-08-2015 | 31-10-2015 | 0.00 KM | 0.00 KM | 0 | 0.00 | 4. | G-2 | 2.80 KM | 26.52 | 01-08-2015 | 15-08-2016 | 2.80 KM | 2.80 KM | 14.18 | 26.52 | 5. | G-3 | 2.80 KM | 16.54 | 01-11-2015 | 15-09-2016 | 2.80 KM | 2.80 KM | 8.85 | 16.54 | 6. | PC/CC i/c Prime Coat, Tack Coat | 2.80 KM | 33.36 | 01-04-2016 | 31-10-2016 | 2.80 KM | 2.80 KM | 17.84 | 33.36 | 7. | Cause Way | 1.00 No | 2.87 | 01-10-2015 | 31-08-2016 | 1.00 No | 1.00 No | 1.54 | 2.87 | 8. | Culverts/Scupper | 10.00 No | 23.64 | 01-09-2015 | 28-03-2016 | 11.00 No | 11.00 No | 12.64 | 23.64 | 9. | longitudinal Drain | 2700.00 m | 5.44 | 01-12-2015 | 31-08-2016 | 2700.00 m | 2700.00 m | 2.91 | 5.44 | 10. | Crash Barrier | 40.00 m | 0.77 | 01-05-2016 | 30-11-2016 | 40.00 m | 40.00 m | 0.41 | 0.77 | 11. | Parapet | 200.00 No | 2.63 | 01-01-2016 | 31-08-2016 | 200.00 No | 200.00 No | 1.41 | 2.63 | 12. | Road Furniture | 13.00 No | 0.92 | 01-03-2016 | 30-11-2016 | 13.00 No | 13.00 No | 0.49 | 0.92 |
Total Amount: |
186.97 |
|
100 |
186.97 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015 } ?>
Updation of work program on:
03-08-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2015 | 11.00 lakh | 2. | 30-September-2015 | 4.25 lakh | 3. | 26-October-2015 | 6.82 lakh | 4. | 21-January-2016 | 13.16 lakh | 5. | 06-February-2016 | 0.06 lakh | 6. | 19-February-2016 | 16.62 lakh | 7. | 30-March-2016 | 14.86 lakh | 8. | 11-May-2016 | 19.93 lakh | 9. | 10-August-2016 | 7.32 lakh | 10. | 29-September-2016 | 36.70 lakh | 11. | 27-October-2016 | 10.20 lakh | 12. | 15-December-2016 | 29.62 lakh | 13. | 25-February-2017 | 20.97 lakh | 14. | 31-July-2017 | 21.56 lakh | 15. | 28-August-2017 | 9.85 lakh |
Total |
222.92 lakh |
% Payment |
99.75 % |
|
Advance Amount: 95.72 lakh
Recovered Amount: 95.72 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 202 No. of Test Done : 247 No. of Test Passed : 222 No. of Test Failed : 25 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.46 |
Number of Notice(s) issued: 97 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 257 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 01-01-2017 | 0+300 | Protection work in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
2. | 01-01-2017 | 1+175 | Site visit regarding quality & progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
3. | 30-12-2016 | 2. 350 | Retaining wall work in progress | Ashish Anthwal | Environment Specialist | PIU UDRP R&B Dehradun | See Pic |
4. | 27-12-2016 | 0. 400 | Retaining wall dry in progress | Ashish Anthwal | Environment Specialist | PIU UDRP R&B Dehradun | See Pic |
5. | 20-12-2016 | 2400 | P .c work rollling on progresss | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
6. | 01-12-2016 | 0/0 | PC work completed patri dressing and proper compaction required contractor instructed to do | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
7. | 16-11-2016 | 2400 | P.c work | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
8. | 08-11-2016 | 0+100 | P .c work ....bhadrashu ramalgoun | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
9. | 08-11-2016 | 350 | H.p bend countune. slaiding | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
10. | 30-10-2016 | 1+650 | PC thickness found 25mm during inspection by SE sir | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
11. | 18-10-2016 | 2+000 | PC laying in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
12. | 18-10-2016 | 2+575 | WBM laying G2 in progress 2500 to 2700 | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
13. | 18-10-2016 | 2+600 | G2 layer work in progress from 2500 to 2700 | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
14. | 15-10-2016 | P.c work badrasu M/R | P.C work badrasu M/R | Prateek Talwar | JE | UDRP R&B Uttarkashi | See Pic |
15. | 14-10-2016 | P.c work badrasu M/R | P.C work badrasu M/R | Prateek Talwar | JE | UDRP R&B Uttarkashi | See Pic |
16. | 13-10-2016 | 2+400 | Cleaning for PC work in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
17. | 09-10-2016 | 2275 to 2300 | thikness checking | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
18. | 09-10-2016 | 2350 | compaction chacking ...thickness | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
19. | 09-10-2016 | 2400 | cleening suface for pc ..... | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
20. | 09-10-2016 | 2500 | k.c drain ....vertical portion | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
|
|