Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bhadrasu Ramalgaon Motor Road Work Completed
Project: UDRP-RB UID: 3121 Sanction Cost: 235.23  lakh Length: 2.770 KM.
District: Uttarkashi Block: Mori Constituency: Purola Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 85        Package Name:  UDRP/PWD/01/33/RD/074        Tender Date: 29-12-2014        Current Status: Agreement signed        Achieved on Date: 18-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/33/RD/074      Contractor Name: Devendra Construction
Start Date:  24-06-2015      Intended Completion Date:  07-01-2017      Original End Date:  23-09-2016
Total Bond Cost: 19635953.97 (196.36 lakh)        Variation Cost: 2714236.82 (27.14 lakh)    Hence Total Bond Cost is   22350190.79 (223.5 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 765804 for 78 days        LD Analysis for Milestone2: calculated LD is Rs 1119252 for 114 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.80 KM14.6801-07-201531-03-20162.80 KM2.80 KM7.8514.68
2.R/Wall, B/ Wall Type Protection works1693.00 m59.6001-07-201531-03-20161693.00 m1693.00 m31.8859.60
3.GSB/RBI/G-10.00 KM0.0001-08-201531-10-20150.00 KM0.00 KM00.00
4.G-22.80 KM26.5201-08-201515-08-20162.80 KM2.80 KM14.1826.52
5.G-32.80 KM16.5401-11-201515-09-20162.80 KM2.80 KM8.8516.54
6.PC/CC i/c Prime Coat, Tack Coat2.80 KM33.3601-04-201631-10-20162.80 KM2.80 KM17.8433.36
7.Cause Way1.00 No2.8701-10-201531-08-20161.00 No1.00 No1.542.87
8.Culverts/Scupper 10.00 No23.6401-09-201528-03-201611.00 No11.00 No12.6423.64
9.longitudinal Drain2700.00 m5.4401-12-201531-08-20162700.00 m2700.00 m2.915.44
10.Crash Barrier40.00 m0.7701-05-201630-11-201640.00 m40.00 m0.410.77
11.Parapet200.00 No2.6301-01-201631-08-2016200.00 No200.00 No1.412.63
12.Road Furniture13.00 No0.9201-03-201630-11-201613.00 No13.00 No0.490.92
Total Amount: 186.97 100   186.97
Remarks: No Remarks       Work Program Made On: 11-08-2015        Updation of work program on: 03-08-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-201511.00  lakh
2.30-September-20154.25  lakh
3.26-October-20156.82  lakh
4.21-January-201613.16  lakh
5.06-February-20160.06  lakh
6.19-February-201616.62  lakh
7.30-March-201614.86  lakh
8.11-May-201619.93  lakh
9.10-August-20167.32  lakh
10.29-September-201636.70  lakh
11.27-October-201610.20  lakh
12.15-December-201629.62  lakh
13.25-February-201720.97  lakh
14.31-July-201721.56  lakh
15.28-August-20179.85  lakh
Total 222.92  lakh
% Payment 99.75 %
Advance Amount:  95.72  lakh        Recovered Amount:  95.72  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 202   No. of Test Done : 247    No. of Test Passed : 222   No. of Test Failed : 25   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.46
Number of Notice(s) issued: 97

Mobile Pic Upload

Number of Pics Available on Web Repository: 257
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-01-20170+300Protection work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
2.01-01-20171+175Site visit regarding quality & progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
3.30-12-20162. 350Retaining wall work in progressAshish AnthwalEnvironment SpecialistPIU UDRP R&B Dehradun See Pic
4.27-12-20160. 400Retaining wall dry in progressAshish AnthwalEnvironment SpecialistPIU UDRP R&B Dehradun See Pic
5.20-12-20162400P .c work rollling on progresssPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
6.01-12-20160/0PC work completed patri dressing and proper compaction required contractor instructed to doPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
7.16-11-20162400P.c workPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
8.08-11-20160+100P .c work ....bhadrashu ramalgounPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
9.08-11-2016350H.p bend countune. slaidingPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
10.30-10-20161+650PC thickness found 25mm during inspection by SE sirPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
11.18-10-20162+000PC laying in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
12.18-10-20162+575WBM laying G2 in progress 2500 to 2700Praveen GuptaREDSC1 R&B WB Uttarkashi See Pic
13.18-10-20162+600G2 layer work in progress from 2500 to 2700Praveen GuptaREDSC1 R&B WB Uttarkashi See Pic
14.15-10-2016P.c work badrasu M/RP.C work badrasu M/RPrateek TalwarJEUDRP R&B Uttarkashi See Pic
15.14-10-2016P.c work badrasu M/RP.C work badrasu M/RPrateek TalwarJEUDRP R&B Uttarkashi See Pic
16.13-10-20162+400Cleaning for PC work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
17.09-10-20162275 to 2300thikness checkingPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
18.09-10-20162350compaction chacking ...thicknessPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
19.09-10-20162400cleening suface for pc .....Praveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
20.09-10-20162500k.c drain ....vertical portionPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic