Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Barnali Jhotari Motor Road Work Completed
Project: UDRP-RB UID: 3118 Sanction Cost: 669.46  lakh Length: 9.050 KM.
District: Uttarkashi Block: Mori Constituency: Purola Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 84        Package Name:  UDRP/PWD/01/33/RD/073        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 03-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/33/RD/073      Contractor Name: Dinesh Prasad Dangwal
Start Date:  10-10-2015      Intended Completion Date:  23-03-2017      Original End Date:  09-01-2017
Total Bond Cost: 61277047.15 (612.77 lakh)        Variation Cost: 4931535.87 (49.32 lakh)    Hence Total Bond Cost is   66208583.02 (662.09 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 337029 for 11 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence9.00 KM27.0011-10-201530-09-20169.00 KM9.00 KM4.7127.00
2.R/Wall, B/ Wall Type Protection works2616.00 m256.8101-11-201531-10-20162616.00 m2616.00 m44.76256.81
3.G-23.30 KM12.5001-01-201631-10-20163.30 KM3.30 KM2.1812.50
4.G-33.30 KM27.8701-03-201631-10-20163.30 KM3.30 KM4.8627.87
5.PC/CC i/c Prime Coat, Tack Coat9.00 KM92.9415-04-201630-11-20169.00 KM9.00 KM16.292.94
6.Culverts/Scupper 24.00 No72.2301-11-201531-07-201624.00 No24.00 No12.5972.23
7.longitudinal Drain9000.00 m82.8201-12-201526-10-20169000.00 m9000.00 m14.4382.82
8.Crash Barrier0.00 m0.0001-04-201631-12-20160.00 m0.00 m00.00
9.Road Furniture77.00 No1.6201-03-201631-12-201677.00 No77.00 No0.281.62
Total Amount: 573.79 100   573.79
Remarks: No Remarks       Work Program Made On: 29-10-2015        Updation of work program on: 16-03-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-January-201645.74  lakh
2.19-February-201629.06  lakh
3.17-March-201633.95  lakh
4.30-March-201642.15  lakh
5.09-June-201676.08  lakh
6.29-June-201631.89  lakh
7.09-August-201672.58  lakh
8.24-September-201663.87  lakh
9.26-October-201640.82  lakh
10.15-December-2016128.29  lakh
11.31-January-201716.64  lakh
12.30-March-201773.69  lakh
13.31-May-20187.53  lakh
Total 662.29  lakh
% Payment 100.05 %
Advance Amount:  75.82  lakh        Recovered Amount:  75.82  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 310   No. of Test Done : 378    No. of Test Passed : 369   No. of Test Failed : 9   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 86.32
Number of Notice(s) issued: 86

Mobile Pic Upload

Number of Pics Available on Web Repository: 107
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-01-20174+200Parapet work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
2.01-01-20179+000Site visit regarding quality & progress reviewPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
3.01-12-20160/1PC work completed patri dressing and proper compaction required instructed to doPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
4.06-11-20161800P.c surface ..seal coat is not properPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
5.06-11-2016600P.c work ..barnali jhotari motor roadPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
6.19-10-20166+800PC work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
7.19-10-20167200seal coat laying in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
8.18-10-20166+625PC compaction in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
9.18-10-20166+675tack coat laying for PC workPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
10.18-10-20166900thickness check p.cPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
11.18-10-20167200temprature ..checking .....p.c workPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
12.18-10-20167900Emulsion use for pkg 73 p.c works ......Praveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
13.18-10-20167900todays ready for p.c at pkg 73 .....pure ....Praveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
14.13-10-20163+700WBM laying in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
15.13-10-20167+800paver for PC work arrived at sitePraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
16.13-10-20168+800G3 layer completedPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
17.13-10-20169kmrollling ..painting .....surface ...Praveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
18.09-10-2016jhotari road last point 9kmdressing surface for last point jhotari motor road .....station pointPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
19.09-10-2016g2 laying worklaying workPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
20.22-09-20163875wbm g2 thicknessPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic