Barnali Jhotari Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
3118 |
Sanction Cost: |
669.46 lakh |
Length:
|
9.050 KM. |
District: |
Uttarkashi |
Block: |
Mori |
Constituency: |
Purola |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 84
Package Name: 
UDRP/PWD/01/33/RD/073
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 03-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/33/RD/073
Contractor Name: Dinesh Prasad Dangwal
|
Start Date: 10-10-2015
Intended Completion Date: 23-03-2017
Original End Date: 09-01-2017 |
Total Bond Cost: 61277047.15 (612.77 lakh)
Variation Cost: 4931535.87 (49.32 lakh) Hence Total Bond Cost is 66208583.02 (662.09 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 337029 for 11 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 9.00 KM | 27.00 | 11-10-2015 | 30-09-2016 | 9.00 KM | 9.00 KM | 4.71 | 27.00 | 2. | R/Wall, B/ Wall Type Protection works | 2616.00 m | 256.81 | 01-11-2015 | 31-10-2016 | 2616.00 m | 2616.00 m | 44.76 | 256.81 | 3. | G-2 | 3.30 KM | 12.50 | 01-01-2016 | 31-10-2016 | 3.30 KM | 3.30 KM | 2.18 | 12.50 | 4. | G-3 | 3.30 KM | 27.87 | 01-03-2016 | 31-10-2016 | 3.30 KM | 3.30 KM | 4.86 | 27.87 | 5. | PC/CC i/c Prime Coat, Tack Coat | 9.00 KM | 92.94 | 15-04-2016 | 30-11-2016 | 9.00 KM | 9.00 KM | 16.2 | 92.94 | 6. | Culverts/Scupper | 24.00 No | 72.23 | 01-11-2015 | 31-07-2016 | 24.00 No | 24.00 No | 12.59 | 72.23 | 7. | longitudinal Drain | 9000.00 m | 82.82 | 01-12-2015 | 26-10-2016 | 9000.00 m | 9000.00 m | 14.43 | 82.82 | 8. | Crash Barrier | 0.00 m | 0.00 | 01-04-2016 | 31-12-2016 | 0.00 m | 0.00 m | 0 | 0.00 | 9. | Road Furniture | 77.00 No | 1.62 | 01-03-2016 | 31-12-2016 | 77.00 No | 77.00 No | 0.28 | 1.62 |
Total Amount: |
573.79 |
|
100 |
573.79 |
|
Remarks:
No Remarks
Work Program Made On:
29-10-2015 } ?>
Updation of work program on:
16-03-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-January-2016 | 45.74 lakh | 2. | 19-February-2016 | 29.06 lakh | 3. | 17-March-2016 | 33.95 lakh | 4. | 30-March-2016 | 42.15 lakh | 5. | 09-June-2016 | 76.08 lakh | 6. | 29-June-2016 | 31.89 lakh | 7. | 09-August-2016 | 72.58 lakh | 8. | 24-September-2016 | 63.87 lakh | 9. | 26-October-2016 | 40.82 lakh | 10. | 15-December-2016 | 128.29 lakh | 11. | 31-January-2017 | 16.64 lakh | 12. | 30-March-2017 | 73.69 lakh | 13. | 31-May-2018 | 7.53 lakh |
Total |
662.29 lakh |
% Payment |
100.05 % |
|
Advance Amount: 75.82 lakh
Recovered Amount: 75.82 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 310 No. of Test Done : 378 No. of Test Passed : 369 No. of Test Failed : 9 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.32 |
Number of Notice(s) issued: 86 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 107 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 01-01-2017 | 4+200 | Parapet work in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
2. | 01-01-2017 | 9+000 | Site visit regarding quality & progress review | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
3. | 01-12-2016 | 0/1 | PC work completed patri dressing and proper compaction required instructed to do | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
4. | 06-11-2016 | 1800 | P.c surface ..seal coat is not proper | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
5. | 06-11-2016 | 600 | P.c work ..barnali jhotari motor road | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
6. | 19-10-2016 | 6+800 | PC work in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
7. | 19-10-2016 | 7200 | seal coat laying in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
8. | 18-10-2016 | 6+625 | PC compaction in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
9. | 18-10-2016 | 6+675 | tack coat laying for PC work | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
10. | 18-10-2016 | 6900 | thickness check p.c | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
11. | 18-10-2016 | 7200 | temprature ..checking .....p.c work | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
12. | 18-10-2016 | 7900 | Emulsion use for pkg 73 p.c works ...... | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
13. | 18-10-2016 | 7900 | todays ready for p.c at pkg 73 .....pure .... | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
14. | 13-10-2016 | 3+700 | WBM laying in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
15. | 13-10-2016 | 7+800 | paver for PC work arrived at site | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
16. | 13-10-2016 | 8+800 | G3 layer completed | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
17. | 13-10-2016 | 9km | rollling ..painting .....surface ... | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
18. | 09-10-2016 | jhotari road last point 9km | dressing surface for last point jhotari motor road .....station point | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
19. | 09-10-2016 | g2 laying work | laying work | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
20. | 22-09-2016 | 3875 | wbm g2 thickness | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
|
|