Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Barethi Kanwa Motor road Work Completed
Project: UDRP-RB UID: 3114 Sanction Cost: 49.63  lakh Length: 2.000 KM.
District: Uttarkashi Block: Dunda Constituency: Gangotri Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 2        Package Name:  UDRP/PWD/01/30/RD/002        Tender Date: 20-11-2014        Current Status: Agreement signed        Achieved on Date: 03-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/30/RD/002      Contractor Name: Vinod Kumar Chauhan
Start Date:  10-06-2015      Intended Completion Date:  09-09-2016     
Total Bond Cost: 18394419.74 (183.94 lakh)        Variation Cost: 1403503.13 (14.04 lakh)    Hence Total Bond Cost is   19797922.87 (197.98 lakh) 
Sub Project Cost: 43.00  lakh        Variation Cost of Sub Project: 215082.35  (2.15 lakh)       Total Sub Project Cost:   45.15 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.50 KM0.3116-09-201516-10-20151.50 KM1.50 KM0.590.31
2.R/Wall, B/ Wall Type Protection works83.00 m17.1315-07-201515-08-201583.00 m83.00 m32.7817.13
3.G-31.50 KM2.9801-09-201515-10-20151.50 KM1.50 KM5.712.98
4.PC/CC i/c Prime Coat, Tack Coat1.50 KM17.7815-10-201515-11-20151.50 KM1.50 KM34.0117.78
5.longitudinal Drain875.00 m13.3201-08-201515-09-2015875.00 m875.00 m25.4813.32
6.Road Furniture2.00 No0.2710-06-201509-07-20152.00 No2.00 No0.510.27
7.Env. Man & Moni Plan1.00 Job0.4801-08-201509-09-20161.00 Job1.00 Job0.930.48
Total Amount: 52.27 100   52.27
Remarks: No Remarks       Work Program Made On: 02-09-2015        Updation of work program on: 14-10-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-201512.00  lakh
2.30-September-20153.60  lakh
3.13-October-201526.57  lakh
4.09-November-20157.05  lakh
5.22-June-20163.00  lakh
Total 52.22  lakh
% Payment115.66 %
Advance Amount:  10.20  lakh        Recovered Amount:  10.20  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 321   No. of Test Done : 321    No. of Test Passed : 319   No. of Test Failed : 2   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 72
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.11-07-20161/11inspection of completed road by T.L Sheladia associatesPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
2.10-07-2016Ch0/4Site visit with TL sirNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
3.17-06-2016Culliwall work in progress km 1/21CulliwallSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
4.14-06-20161/20Colli wallChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
5.01-06-2016Culliwall work in progress km 1/11Culliwall work in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
6.21-05-2016Excavation in foundationCulliwallSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
7.27-10-2015@1000mSeal coatManish RanaJEUDRP R&B Gopeshwar See Pic
8.22-10-2015Ch 1/15P.C work in progressNaveen Kumar SharmaAEUDRP R&B WB Karanprayag See Pic
9.19-10-20151/28PC work completeChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
10.16-10-2015Ch0/13Pc work on progressNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
11.16-10-2015Km1Pc work on progressNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
12.15-10-20151/30P C workChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
13.15-10-20151/29P C work completeChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
14.14-10-20150/11preparation for PC workPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
15.14-10-20151/15KC drain work completedPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
16.13-10-2015Ch0/31Tack coat testNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
17.12-10-2015Ch0/31Tack coat testNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
18.12-10-2015Km1Tack coat testNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
19.09-10-20150/39Seal coat workDeepak Kumar 2JEUDRP R&B Uttarkashi See Pic
20.09-10-20150/39PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic