Barethi Kanwa Motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
3114 |
Sanction Cost: |
49.63 lakh |
Length:
|
2.000 KM. |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 2
Package Name: 
UDRP/PWD/01/30/RD/002
Tender Date: 20-11-2014
Current Status: Agreement signed
Achieved on Date: 03-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/30/RD/002
Contractor Name: Vinod Kumar Chauhan
|
Start Date: 10-06-2015
Intended Completion Date: 09-09-2016
|
Total Bond Cost: 18394419.74 (183.94 lakh)
Variation Cost: 1403503.13 (14.04 lakh) Hence Total Bond Cost is 19797922.87 (197.98 lakh)
|
Sub Project Cost: 43.00 lakh
Variation Cost of Sub Project: 215082.35 (2.15 lakh)
Total Sub Project Cost:
45.15 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.50 KM | 0.31 | 16-09-2015 | 16-10-2015 | 1.50 KM | 1.50 KM | 0.59 | 0.31 | 2. | R/Wall, B/ Wall Type Protection works | 83.00 m | 17.13 | 15-07-2015 | 15-08-2015 | 83.00 m | 83.00 m | 32.78 | 17.13 | 3. | G-3 | 1.50 KM | 2.98 | 01-09-2015 | 15-10-2015 | 1.50 KM | 1.50 KM | 5.71 | 2.98 | 4. | PC/CC i/c Prime Coat, Tack Coat | 1.50 KM | 17.78 | 15-10-2015 | 15-11-2015 | 1.50 KM | 1.50 KM | 34.01 | 17.78 | 5. | longitudinal Drain | 875.00 m | 13.32 | 01-08-2015 | 15-09-2015 | 875.00 m | 875.00 m | 25.48 | 13.32 | 6. | Road Furniture | 2.00 No | 0.27 | 10-06-2015 | 09-07-2015 | 2.00 No | 2.00 No | 0.51 | 0.27 | 7. | Env. Man & Moni Plan | 1.00 Job | 0.48 | 01-08-2015 | 09-09-2016 | 1.00 Job | 1.00 Job | 0.93 | 0.48 |
Total Amount: |
52.27 |
|
100 |
52.27 |
|
Remarks:
No Remarks
Work Program Made On:
02-09-2015 } ?>
Updation of work program on:
14-10-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2015 | 12.00 lakh | 2. | 30-September-2015 | 3.60 lakh | 3. | 13-October-2015 | 26.57 lakh | 4. | 09-November-2015 | 7.05 lakh | 5. | 22-June-2016 | 3.00 lakh |
Total |
52.22 lakh |
% Payment | 115.66 % |
|
Advance Amount: 10.20 lakh
Recovered Amount: 10.20 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 321 No. of Test Done : 321 No. of Test Passed : 319 No. of Test Failed : 2 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 72 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 11-07-2016 | 1/11 | inspection of completed road by T.L Sheladia associates | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
2. | 10-07-2016 | Ch0/4 | Site visit with TL sir | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
3. | 17-06-2016 | Culliwall work in progress km 1/21 | Culliwall | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
4. | 14-06-2016 | 1/20 | Colli wall | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
5. | 01-06-2016 | Culliwall work in progress km 1/11 | Culliwall work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
6. | 21-05-2016 | Excavation in foundation | Culliwall | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
7. | 27-10-2015 | @1000m | Seal coat | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
8. | 22-10-2015 | Ch 1/15 | P.C work in progress | Naveen Kumar Sharma | AE | UDRP R&B WB Karanprayag | See Pic |
9. | 19-10-2015 | 1/28 | PC work complete | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
10. | 16-10-2015 | Ch0/13 | Pc work on progress | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
11. | 16-10-2015 | Km1 | Pc work on progress | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
12. | 15-10-2015 | 1/30 | P C work | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
13. | 15-10-2015 | 1/29 | P C work complete | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
14. | 14-10-2015 | 0/11 | preparation for PC work | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
15. | 14-10-2015 | 1/15 | KC drain work completed | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
16. | 13-10-2015 | Ch0/31 | Tack coat test | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
17. | 12-10-2015 | Ch0/31 | Tack coat test | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
18. | 12-10-2015 | Km1 | Tack coat test | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
19. | 09-10-2015 | 0/39 | Seal coat work | Deepak Kumar 2 | JE | UDRP R&B Uttarkashi | See Pic |
20. | 09-10-2015 | 0/39 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
|
|