Chinyalisaur-Jogath Motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
3101 |
Sanction Cost: |
1398.72 lakh |
Length:
|
20.000 KM. |
District: |
Uttarkashi |
Block: |
Chinyalisaur |
Constituency: |
Yamunotri |
Circle: |
Tehri WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 8
Package Name: 
UDRP/PWD/01/32/RD/008
Tender Date: 14-08-2014
Current Status: Agreement signed
Achieved on Date: 19-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/32/RD/008
Contractor Name: Bharat Construction
|
Start Date: 27-02-2015
Intended Completion Date: 10-12-2017
Original End Date: 26-05-2016 |
Total Bond Cost: 127545587.7 (1275.46 lakh)
Variation Cost: -12293693.86 (-122.94 lakh) Hence Total Bond Cost is 115251893.84 (1152.52 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 13009692 for +204 days
LD Analysis for Milestone2: calculated LD is Rs 15305520 for 240 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.50 KM | 6.53 | 15-12-2015 | 30-06-2016 | 0.50 KM | 0.50 KM | 0.52 | 6.53 | 2. | R/Wall, B/ Wall Type Protection works | 1102.00 m | 136.00 | 27-02-2015 | 15-04-2017 | 1102.00 m | 1102.00 m | 10.85 | 136.00 | 3. | GSB/RBI/G-1 | 0.45 KM | 1.56 | 01-07-2015 | 31-07-2015 | 0.45 KM | 0.45 KM | 0.12 | 1.56 | 4. | GSB/RBI/G-1 (Step 2) | 0.00 KM | 0.00 | 15-08-2016 | 15-09-2016 | 0.00 KM | 0.00 KM | 0 | 0.00 | 5. | G-2 | 0.25 KM | 1.16 | 01-07-2015 | 31-07-2015 | 0.25 KM | 0.25 KM | 0.09 | 1.16 | 6. | G-2 (Step 2) | 0.20 KM | 0.92 | 16-08-2016 | 15-09-2016 | 0.20 KM | 0.20 KM | 0.07 | 0.92 | 7. | G-3 | 1.00 KM | 3.01 | 01-08-2015 | 09-11-2017 | 1.00 KM | 1.00 KM | 0.24 | 3.01 | 8. | G-3 (Step 2) | 0.00 KM | 0.00 | 10-11-2017 | 30-11-2017 | 0.00 KM | 0.00 KM | 0 | 0.00 | 9. | BM i/c Prime Coat, Tack Coat | 5.00 KM | 100.00 | 15-09-2015 | 30-11-2015 | 5.00 KM | 5.00 KM | 7.97 | 100.00 | 10. | BM i/c Prime Coat, Tack Coat (Step 2) | 5.00 KM | 100.00 | 15-03-2016 | 15-06-2016 | 5.00 KM | 5.00 KM | 7.97 | 100.00 | 11. | BM i/c Prime Coat, Tack Coat (Step 3) | 5.00 KM | 100.00 | 01-10-2016 | 30-11-2016 | 5.00 KM | 5.00 KM | 7.97 | 100.00 | 12. | BM i/c Prime Coat, Tack Coat (Step 4) | 6.40 KM | 123.00 | 01-03-2017 | 30-11-2017 | 6.40 KM | 6.40 KM | 9.81 | 123.00 | 13. | SDBC i/c Tackcoat | 5.00 KM | 63.22 | 15-09-2015 | 30-11-2015 | 5.00 KM | 5.00 KM | 5.04 | 63.22 | 14. | SDBC i/c Tackcoat (Step 2) | 5.00 KM | 63.22 | 15-03-2016 | 15-06-2016 | 5.00 KM | 5.00 KM | 5.04 | 63.22 | 15. | SDBC i/c Tackcoat (Step 3) | 5.00 KM | 63.22 | 01-10-2016 | 30-11-2016 | 5.00 KM | 5.00 KM | 5.04 | 63.22 | 16. | SDBC i/c Tackcoat (Step 4) | 6.40 KM | 75.07 | 15-06-2017 | 30-11-2017 | 6.40 KM | 6.40 KM | 5.99 | 75.07 | 17. | Cause Way | 0.00 No | 0.00 | 10-11-2017 | 05-12-2017 | 0.00 No | 0.00 No | 0 | 0.00 | 18. | Culverts/Scupper | 53.00 No | 115.75 | 01-03-2015 | 15-12-2016 | 53.00 No | 53.00 No | 9.23 | 115.75 | 19. | longitudinal Drain | 20700.00 m | 109.83 | 01-04-2015 | 10-12-2017 | 20700.00 m | 20700.00 m | 8.76 | 109.83 | 20. | Crash Barrier | 4000.00 m | 187.66 | 01-06-2015 | 15-01-2018 | 4000.00 m | 4000.00 m | 14.97 | 187.66 | 21. | Road Furniture | 219.00 No | 3.87 | 01-03-2015 | 10-12-2017 | 219.00 No | 219.00 No | 0.31 | 3.87 |
Total Amount: |
1254.02 |
|
100 |
1254.02 |
|
Remarks:
No Remarks
Work Program Made On:
31-03-2015 } ?>
Updation of work program on:
26-05-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2015 | 35.53 lakh | 2. | 18-May-2015 | 19.35 lakh | 3. | 12-June-2015 | 8.51 lakh | 4. | 25-July-2015 | 17.88 lakh | 5. | 09-November-2015 | 40.30 lakh | 6. | 19-January-2016 | 36.79 lakh | 7. | 06-February-2016 | 0.03 lakh | 8. | 30-March-2016 | 36.82 lakh | 9. | 03-July-2016 | 40.87 lakh | 10. | 31-July-2016 | 278.91 lakh | 11. | 26-October-2016 | 20.41 lakh | 12. | 16-December-2016 | 127.96 lakh | 13. | 31-March-2017 | 97.28 lakh | 14. | 19-May-2017 | 35.14 lakh | 15. | 13-October-2017 | 154.59 lakh | 16. | 29-November-2017 | 56.12 lakh | 17. | 08-December-2017 | 51.02 lakh | 18. | 23-December-2017 | 2.56 lakh | 19. | 26-December-2017 | 35.00 lakh | 20. | 17-February-2018 | 13.67 lakh | 21. | 27-February-2018 | 20.67 lakh | 22. | 31-March-2018 | 23.09 lakh | 23. | 28-October-2018 | 2.60 lakh |
Total |
1155.1 lakh |
% Payment |
100.22 % |
|
Advance Amount: 420.93 lakh
Recovered Amount: 420.93 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1492 No. of Test Done : 1734 No. of Test Passed : 1695 No. of Test Failed : 39 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.70 |
Number of Notice(s) issued: 185 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 683 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 09-03-2018 | 7/6 | CE sir, SE sir, EE sir visit at chinyali jogath MR pkg-008 | Ankit Kuriyal | JE | UDRP R&B Uttarkashi | See Pic |
2. | 25-12-2017 | 1/30 | Visit by World bank mission | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
3. | 20-12-2017 | 1/30 | Chinyali jogath MR pkg 008 visit by world bank mission | Ankit Kuriyal | JE | UDRP R&B Uttarkashi | See Pic |
4. | 20-12-2017 | 1/24 | Chinyali jogath MR visit by world bank mission pkg 008 | Ankit Kuriyal | JE | UDRP R&B Uttarkashi | See Pic |
5. | 14-12-2017 | 1/24 | Visit by S E sir | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
6. | 12-12-2017 | Chinyali jogat road ch 2/25 | Retaining wall made for protection in damaged portion | Ramesh Chand | EE | UDRP R&B Uttarkashi | See Pic |
7. | 07-12-2017 | Ch3/17 | WBM G3 layer rolling work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
8. | 02-12-2017 | Km5 hot mix plant | Sdbc mix production on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
9. | 02-12-2017 | Km5hmp | Bitumen tank temperature | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
10. | 02-12-2017 | 1/750 | BM mix laying work on progress at chinyali jogath MR | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
11. | 25-11-2017 | 14/10 | SDBC LAYING | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
12. | 18-11-2017 | Hot mix plant at km 5, chinyali jogath MR | SDBC mix production on progress at chinyali jogath MR | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
13. | 18-11-2017 | Hot mix plant, km 5, chinyali jogath MR | SDBC laying work on progress at chinyali jogath MR /pkg 008 | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
14. | 16-11-2017 | Ch15/04 | SDBC work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
15. | 13-11-2017 | 16/4 | SDBC Work start today . | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
16. | 10-11-2017 | 14/28 | B.M.. work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
17. | 09-11-2017 | 14/27 | B.M. work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
18. | 09-11-2017 | Km5HMP | BM production on progress at chinyali jogath MR, pkg 008 | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
19. | 09-11-2017 | Km5 | Hmp plant inspaction by SE Sir | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
20. | 08-11-2017 | 14/38 | B.M. work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
|
|