Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Chinyalisaur-Jogath Motor road Work Completed
Project: UDRP-RB UID: 3101 Sanction Cost: 1398.72  lakh Length: 20.000 KM.
District: Uttarkashi Block: Chinyalisaur Constituency: Yamunotri Circle: Tehri WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: ODR
Procurement:
Package No.: 8        Package Name:  UDRP/PWD/01/32/RD/008        Tender Date: 14-08-2014        Current Status: Agreement signed        Achieved on Date: 19-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/32/RD/008      Contractor Name: Bharat Construction
Start Date:  27-02-2015      Intended Completion Date:  10-12-2017      Original End Date:  26-05-2016
Total Bond Cost: 127545587.7 (1275.46 lakh)        Variation Cost: -12293693.86 (-122.94 lakh)    Hence Total Bond Cost is   115251893.84 (1152.52 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 13009692 for +204 days        LD Analysis for Milestone2: calculated LD is Rs 15305520 for 240 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.50 KM6.5315-12-201530-06-20160.50 KM0.50 KM0.526.53
2.R/Wall, B/ Wall Type Protection works1102.00 m136.0027-02-201515-04-20171102.00 m1102.00 m10.85136.00
3.GSB/RBI/G-10.45 KM1.5601-07-201531-07-20150.45 KM0.45 KM0.121.56
4.GSB/RBI/G-1 (Step 2)0.00 KM0.0015-08-201615-09-20160.00 KM0.00 KM00.00
5.G-20.25 KM1.1601-07-201531-07-20150.25 KM0.25 KM0.091.16
6.G-2 (Step 2)0.20 KM0.9216-08-201615-09-20160.20 KM0.20 KM0.070.92
7.G-31.00 KM3.0101-08-201509-11-20171.00 KM1.00 KM0.243.01
8.G-3 (Step 2)0.00 KM0.0010-11-201730-11-20170.00 KM0.00 KM00.00
9.BM i/c Prime Coat, Tack Coat5.00 KM100.0015-09-201530-11-20155.00 KM5.00 KM7.97100.00
10.BM i/c Prime Coat, Tack Coat (Step 2)5.00 KM100.0015-03-201615-06-20165.00 KM5.00 KM7.97100.00
11.BM i/c Prime Coat, Tack Coat (Step 3)5.00 KM100.0001-10-201630-11-20165.00 KM5.00 KM7.97100.00
12.BM i/c Prime Coat, Tack Coat (Step 4)6.40 KM123.0001-03-201730-11-20176.40 KM6.40 KM9.81123.00
13.SDBC i/c Tackcoat5.00 KM63.2215-09-201530-11-20155.00 KM5.00 KM5.0463.22
14.SDBC i/c Tackcoat (Step 2)5.00 KM63.2215-03-201615-06-20165.00 KM5.00 KM5.0463.22
15.SDBC i/c Tackcoat (Step 3)5.00 KM63.2201-10-201630-11-20165.00 KM5.00 KM5.0463.22
16.SDBC i/c Tackcoat (Step 4)6.40 KM75.0715-06-201730-11-20176.40 KM6.40 KM5.9975.07
17.Cause Way0.00 No0.0010-11-201705-12-20170.00 No0.00 No00.00
18.Culverts/Scupper 53.00 No115.7501-03-201515-12-201653.00 No53.00 No9.23115.75
19.longitudinal Drain20700.00 m109.8301-04-201510-12-201720700.00 m20700.00 m8.76109.83
20.Crash Barrier4000.00 m187.6601-06-201515-01-20184000.00 m4000.00 m14.97187.66
21.Road Furniture219.00 No3.8701-03-201510-12-2017219.00 No219.00 No0.313.87
Total Amount: 1254.02 100   1254.02
Remarks: No Remarks       Work Program Made On: 31-03-2015        Updation of work program on: 26-05-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-March-201535.53  lakh
2.18-May-201519.35  lakh
3.12-June-20158.51  lakh
4.25-July-201517.88  lakh
5.09-November-201540.30  lakh
6.19-January-201636.79  lakh
7.06-February-20160.03  lakh
8.30-March-201636.82  lakh
9.03-July-201640.87  lakh
10.31-July-2016278.91  lakh
11.26-October-201620.41  lakh
12.16-December-2016127.96  lakh
13.31-March-201797.28  lakh
14.19-May-201735.14  lakh
15.13-October-2017154.59  lakh
16.29-November-201756.12  lakh
17.08-December-201751.02  lakh
18.23-December-20172.56  lakh
19.26-December-201735.00  lakh
20.17-February-201813.67  lakh
21.27-February-201820.67  lakh
22.31-March-201823.09  lakh
23.28-October-20182.60  lakh
Total 1155.1  lakh
% Payment 100.22 %
Advance Amount:  420.93  lakh        Recovered Amount:  420.93  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1492   No. of Test Done : 1734    No. of Test Passed : 1695   No. of Test Failed : 39   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.70
Number of Notice(s) issued: 185

Mobile Pic Upload

Number of Pics Available on Web Repository: 683
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.09-03-20187/6CE sir, SE sir, EE sir visit at chinyali jogath MR pkg-008Ankit KuriyalJEUDRP R&B Uttarkashi See Pic
2.25-12-20171/30Visit by World bank missionChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
3.20-12-20171/30Chinyali jogath MR pkg 008 visit by world bank missionAnkit KuriyalJEUDRP R&B Uttarkashi See Pic
4.20-12-20171/24Chinyali jogath MR visit by world bank mission pkg 008Ankit KuriyalJEUDRP R&B Uttarkashi See Pic
5.14-12-20171/24Visit by S E sirChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
6.12-12-2017Chinyali jogat road ch 2/25Retaining wall made for protection in damaged portionRamesh ChandEEUDRP R&B Uttarkashi See Pic
7.07-12-2017Ch3/17WBM G3 layer rolling work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
8.02-12-2017Km5 hot mix plantSdbc mix production on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
9.02-12-2017Km5hmpBitumen tank temperatureNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
10.02-12-20171/750BM mix laying work on progress at chinyali jogath MRNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
11.25-11-201714/10SDBC LAYINGChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
12.18-11-2017Hot mix plant at km 5, chinyali jogath MRSDBC mix production on progress at chinyali jogath MRNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
13.18-11-2017Hot mix plant, km 5, chinyali jogath MRSDBC laying work on progress at chinyali jogath MR /pkg 008Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
14.16-11-2017Ch15/04SDBC work in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
15.13-11-201716/4SDBC Work start today .Chandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
16.10-11-201714/28B.M.. work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
17.09-11-201714/27B.M. work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
18.09-11-2017Km5HMPBM production on progress at chinyali jogath MR, pkg 008Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
19.09-11-2017Km5Hmp plant inspaction by SE SirNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
20.08-11-201714/38B.M. work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic