Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Tachla-Naour motor road Work Completed
Project: UDRP-RB UID: 2854 Sanction Cost: 849.91  lakh Length: 9.000 KM.
District: Tehri Block: Narendra Nagar Constituency: Narendra Nagar Circle: Tehri WB Circle
DEA: DEA Tehri DSC: Egis International DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 122        Package Name:  UDRP/PWD/04/44/RD/111        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 18-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/04/44/RD/111      Contractor Name: VAR Associates
Start Date:  25-12-2015      Intended Completion Date:  28-02-2018      Original End Date:  24-03-2017
Total Bond Cost: 66309758.97 (663.1 lakh)        Variation Cost: 7508282.72 (75.08 lakh)    Hence Total Bond Cost is   73818041.69 (738.18 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 2387160 for 72 days        LD Analysis for Milestone2: calculated LD is Rs 4310150 for 130 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence8.63 KM61.2725-12-201530-10-20167.75 KM7.75 KM10.7761.27
2.R/Wall, B/ Wall Type Protection works2930.00 m201.4724-01-201609-12-20162930.00 m2930.00 m35.4201.47
3.GSB/RBI/G-16.66 KM67.9010-06-201612-11-20166.66 KM6.66 KM11.9367.90
4.G-26.66 KM45.9203-09-201602-12-20166.66 KM6.66 KM8.0745.92
5.G-37.97 KM67.4318-09-201627-12-20167.69 KM7.69 KM11.8567.43
6.PC/CC i/c Prime Coat, Tack Coat7.69 KM14.3401-02-201718-03-20177.69 KM7.69 KM2.5214.34
7.Culverts/Scupper 50.00 No42.7728-09-201607-12-201623.00 No23.00 No7.5242.77
8.longitudinal Drain7100.00 m25.8913-05-201615-10-20167679.00 m7679.00 m4.5525.89
9.Crash Barrier1200.00 m31.0910-01-201728-02-2017500.00 m500.00 m5.4631.09
10.Parapet300.00 No8.2231-12-201628-02-2017300.00 No300.00 No1.458.22
11.Road Furniture127.00 No2.8418-02-201724-03-2017127.00 No127.00 No0.52.84
Total Amount: 569.14 100   569.14
Remarks: No Remarks       Work Program Made On: 02-04-2016        Updation of work program on: 22-10-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.01-March-201629.64  lakh
2.22-March-20169.97  lakh
3.05-May-201631.64  lakh
4.08-June-201625.01  lakh
5.22-July-201623.98  lakh
6.29-August-201633.95  lakh
7.30-September-201631.70  lakh
8.26-October-201643.80  lakh
9.29-November-201638.28  lakh
10.28-December-201611.32  lakh
11.30-January-201711.51  lakh
12.28-February-201736.59  lakh
13.17-March-201733.96  lakh
14.31-March-201716.09  lakh
15.27-April-201713.70  lakh
16.29-May-201713.93  lakh
17.17-June-201766.01  lakh
18.28-June-201729.71  lakh
19.19-July-201713.09  lakh
20.31-August-20173.90  lakh
21.07-October-201716.87  lakh
22.28-November-201749.13  lakh
23.30-December-201744.62  lakh
24.31-January-201818.37  lakh
25.28-March-201820.29  lakh
26.30-May-201849.87  lakh
27.31-October-201818.04  lakh
28.30-November-20188.01  lakh
Total 742.98  lakh
% Payment 100.67 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 991   No. of Test Done : 1107    No. of Test Passed : 1058   No. of Test Failed : 49   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.50
Number of Notice(s) issued: 87

Mobile Pic Upload

Number of Pics Available on Web Repository: 339
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.26-04-20181.500Site inspection by EE Mam WB PWD Tehri, TL Sir DSC 2,Sudhir Kumar AEAEUDRP R&B Tehri See Pic
2.26-04-20182.900Site inspection by SE Sir n EE Mam WB PWD TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
3.09-02-20182.400Cons. Of Kutcha drainSudhir Kumar AEAEUDRP R&B Tehri See Pic
4.24-01-20180.350Pucca drainSudhir Kumar AEAEUDRP R&B Tehri See Pic
5.24-01-20185.875Naur village pathSudhir Kumar AEAEUDRP R&B Tehri See Pic
6.09-01-20180.00Site inspection /Sudhir Kumar AEAEUDRP R&B Tehri See Pic
7.09-01-20180.000Site inspection by Environment n social expert PIU DehradunSudhir Kumar AEAEUDRP R&B Tehri See Pic
8.28-12-20170.050Site inspection by CE Sir ,SE sir n EE MamSudhir Kumar AEAEUDRP R&B Tehri See Pic
9.27-12-20175.875Site inspection by EE MamSudhir Kumar AEAEUDRP R&B Tehri See Pic
10.27-12-20170.525C/O Kutcha drainSudhir Kumar AEAEUDRP R&B Tehri See Pic
11.27-12-20173.100Foot trackSudhir Kumar AEAEUDRP R&B Tehri See Pic
12.21-12-20173.300Village path (Foot Track )Sudhir Kumar AEAEUDRP R&B Tehri See Pic
13.19-12-20170.025Collection of stone for kharanjaSudhir Kumar AEAEUDRP R&B Tehri See Pic
14.17-12-20170.525PC work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
15.14-12-20170.050G3 completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
16.14-12-20170.625Rolling of PC surfaceSudhir Kumar AEAEUDRP R&B Tehri See Pic
17.14-12-20175.100Meeting with Naur villagersSudhir Kumar AEAEUDRP R&B Tehri See Pic
18.14-12-20175.100Meeting with villagers NaurSudhir Kumar AEAEUDRP R&B Tehri See Pic
19.14-12-20171.400Medical check up of labourSudhir Kumar AEAEUDRP R&B Tehri See Pic
20.14-12-20172.675Rolling of PC surfaceSudhir Kumar AEAEUDRP R&B Tehri See Pic