Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Syansu pul to Ratwari Nakot Kholi Motor road Work Completed
Project: UDRP-RB UID: 2852 Sanction Cost: 20.00  lakh Length: 4.000 KM.
District: Tehri Block: Kouldhar Constituency: Dhanaulti Circle: Tehri WB Circle
DEA: DEA Tehri DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 4        Package Name:  UDRP/PWD/04/46/RD/004        Tender Date: 22-02-2014        Current Status: Agreement signed        Achieved on Date: 12-06-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/04/46/RD/004      Contractor Name: Vijay Engineering Associates
Start Date:  19-06-2014      Intended Completion Date:  15-03-2016      Original End Date:  18-09-2015
Total Bond Cost: 37077339.47 (370.77 lakh)        Variation Cost: -2929148.67 (-29.29 lakh)    Hence Total Bond Cost is   34148190.8 (341.48 lakh) 
Sub Project Cost: 51.80  lakh        Variation Cost of Sub Project: 2618577.77  (26.19 lakh)       Total Sub Project Cost:   77.99 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works170.00 m15.5501-09-201431-12-2014170.72 m170.72 m32.9415.55
2.Culverts/Scupper 7.00 No31.6701-08-201431-01-20158.00 No8.00 No67.0731.67
Total Amount: 47.22 100   47.22
Remarks: No Remarks       Work Program Made On: 20-07-2014        Updation of work program on: 19-09-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-December-20145.84  lakh
2.24-February-20150.35  lakh
3.31-March-20157.75  lakh
4.28-August-20155.04  lakh
5.06-November-201513.37  lakh
6.28-March-201614.02  lakh
Total 46.37  lakh
% Payment59.46 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.25  lakh        Balance to be Recovered  -0.25  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 482   No. of Test Done : 537    No. of Test Passed : 510   No. of Test Failed : 27   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 28
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-02-2016Ch.3.700Slab Casting of 3m Span culvertNawal KishoreSite SupervisorDSC2 R&B WB Tehri See Pic
2.11-02-2016Ch.3.700Slab Reinforcement for 3m Span culvert completeNawal KishoreSite SupervisorDSC2 R&B WB Tehri See Pic
3.11-02-2016Ch 3.7003m span culvert reinforcementSaurab ChauhanAEUDRP R&B Tehri See Pic
4.04-02-2016Ch:-3/28Laying of bed blockSamiksha SharmaJEUDRP R&B Tehri See Pic
5.07-01-2016CH 3.225Catchpit construction 3 m culvertSaurab ChauhanAEUDRP R&B Tehri See Pic
6.28-10-20153.675Slab Casting of 3m Span culvertNawal KishoreSite SupervisorDSC2 R&B WB Tehri See Pic
7.28-10-2015CH 3.3003 m span culvertSaurab ChauhanAEUDRP R&B Tehri See Pic
8.30-09-2015Ch 3.300Plum blockSamiksha SharmaJEUDRP R&B Tehri See Pic
9.30-09-2015Ch 5.250Scupper with R wall drySamiksha SharmaJEUDRP R&B Tehri See Pic
10.18-09-2015Ch.5.250Slab castingSamiksha SharmaJEUDRP R&B Tehri See Pic
11.09-09-2015Ch 5.250Scupper under progressSamiksha SharmaJEUDRP R&B Tehri See Pic
12.09-09-2015Ch 5.175Scupper work in progressSamiksha SharmaJEUDRP R&B Tehri See Pic
13.20-08-2015Ch.5.100Scupper toe wallSamiksha SharmaJEUDRP R&B Tehri See Pic
14.20-08-2015Ch.5.200ScupperSamiksha SharmaJEUDRP R&B Tehri See Pic
15.23-07-2015Km 5.100 5.200Foundation of scupperSamiksha SharmaJEUDRP R&B Tehri See Pic
16.28-04-2015Km 2.400Rwall and coolie wallSamiksha SharmaJEUDRP R&B Tehri See Pic
17.28-04-2015Km 2.300Rwall drySamiksha SharmaJEUDRP R&B Tehri See Pic
18.26-03-2015Km 0/35WirecratesSamiksha SharmaJEUDRP R&B Tehri See Pic
19.25-02-2015Km2.200Scupper full lengthSamiksha SharmaJEUDRP R&B Tehri See Pic
20.07-01-2015Km 0/35Slip clearance required for laying of wirecratesSamiksha SharmaJEUDRP R&B Tehri See Pic