Syansu pul to Ratwari Nakot Kholi Motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2852 |
Sanction Cost: |
20.00 lakh |
Length:
|
4.000 KM. |
District: |
Tehri |
Block: |
Kouldhar |
Constituency: |
Dhanaulti |
Circle: |
Tehri WB Circle |
DEA: |
DEA Tehri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 4
Package Name: 
UDRP/PWD/04/46/RD/004
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 12-06-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/04/46/RD/004
Contractor Name: Vijay Engineering Associates
|
Start Date: 19-06-2014
Intended Completion Date: 15-03-2016
Original End Date: 18-09-2015 |
Total Bond Cost: 37077339.47 (370.77 lakh)
Variation Cost: -2929148.67 (-29.29 lakh) Hence Total Bond Cost is 34148190.8 (341.48 lakh)
|
Sub Project Cost: 51.80 lakh
Variation Cost of Sub Project: 2618577.77 (26.19 lakh)
Total Sub Project Cost:
77.99 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 170.00 m | 15.55 | 01-09-2014 | 31-12-2014 | 170.72 m | 170.72 m | 32.94 | 15.55 | 2. | Culverts/Scupper | 7.00 No | 31.67 | 01-08-2014 | 31-01-2015 | 8.00 No | 8.00 No | 67.07 | 31.67 |
Total Amount: |
47.22 |
|
100 |
47.22 |
|
Remarks:
No Remarks
Work Program Made On:
20-07-2014 } ?>
Updation of work program on:
19-09-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-December-2014 | 5.84 lakh | 2. | 24-February-2015 | 0.35 lakh | 3. | 31-March-2015 | 7.75 lakh | 4. | 28-August-2015 | 5.04 lakh | 5. | 06-November-2015 | 13.37 lakh | 6. | 28-March-2016 | 14.02 lakh |
Total |
46.37 lakh |
% Payment | 59.46 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.25 lakh
Balance to be Recovered -0.25 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 482 No. of Test Done : 537 No. of Test Passed : 510 No. of Test Failed : 27 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 28 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-02-2016 | Ch.3.700 | Slab Casting of 3m Span culvert | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
2. | 11-02-2016 | Ch.3.700 | Slab Reinforcement for 3m Span culvert complete | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
3. | 11-02-2016 | Ch 3.700 | 3m span culvert reinforcement | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
4. | 04-02-2016 | Ch:-3/28 | Laying of bed block | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
5. | 07-01-2016 | CH 3.225 | Catchpit construction 3 m culvert | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
6. | 28-10-2015 | 3.675 | Slab Casting of 3m Span culvert | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
7. | 28-10-2015 | CH 3.300 | 3 m span culvert | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
8. | 30-09-2015 | Ch 3.300 | Plum block | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
9. | 30-09-2015 | Ch 5.250 | Scupper with R wall dry | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
10. | 18-09-2015 | Ch.5.250 | Slab casting | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
11. | 09-09-2015 | Ch 5.250 | Scupper under progress | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
12. | 09-09-2015 | Ch 5.175 | Scupper work in progress | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
13. | 20-08-2015 | Ch.5.100 | Scupper toe wall | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
14. | 20-08-2015 | Ch.5.200 | Scupper | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
15. | 23-07-2015 | Km 5.100 5.200 | Foundation of scupper | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
16. | 28-04-2015 | Km 2.400 | Rwall and coolie wall | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
17. | 28-04-2015 | Km 2.300 | Rwall dry | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
18. | 26-03-2015 | Km 0/35 | Wirecrates | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
19. | 25-02-2015 | Km2.200 | Scupper full length | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
20. | 07-01-2015 | Km 0/35 | Slip clearance required for laying of wirecrates | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
|
|