Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kempti Byepass Motor Road Work Completed
Project: UDRP-RB UID: 2749 Sanction Cost: 348.81  lakh Length: 5.750 KM.
District: Tehri Block: Jaunpur Constituency: Dhanaulti Circle: Tehri WB Circle
DEA: DEA Tehri DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 18        Package Name:  UDRP/PWD/04/49/RD/018        Tender Date: 03-05-2014        Current Status: Agreement signed        Achieved on Date: 03-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/04/49/RD/018      Contractor Name: Shiv Shankar Construction Company
Start Date:  10-11-2014      Intended Completion Date:  30-04-2016      Original End Date:  09-02-2016
Total Bond Cost: 30322641.85 (303.23 lakh)        Variation Cost: 3735039.50 (37.35 lakh)    Hence Total Bond Cost is   34057681.35 (340.58 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 379025 for 25 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works500.00 m35.0015-11-201415-04-2015350.00 m350.00 m11.5635.00
2.GSB/RBI/G-10.25 KM0.2001-03-201531-03-20150.34 KM0.34 KM0.070.20
3.G-20.25 KM0.1510-03-201515-04-20150.34 KM0.34 KM0.050.15
4.G-30.25 KM0.2101-04-201530-04-20150.76 KM0.76 KM0.070.21
5.BM i/c Prime Coat, Tack Coat5.75 KM145.0015-04-201510-06-20155.75 KM5.75 KM47.87145.00
6.SDBC i/c Tackcoat5.75 KM80.0001-05-201515-06-20155.75 KM5.75 KM26.4180.00
7.Cause Way1.00 No7.8001-03-201531-03-20152.00 No2.00 No2.587.80
8.Culverts/Scupper 11.00 No2.0501-12-201431-03-201511.00 No11.00 No0.682.05
9.longitudinal Drain2.26 m21.0001-02-201515-04-20155260.00 m5260.00 m6.9321.00
10.Parapet250.00 No6.0001-03-201515-04-2015292.00 No292.00 No1.986.00
11.Road Furniture180.00 No5.5001-03-201514-04-2015180.00 No180.00 No1.825.50
Total Amount: 302.91 100   302.91
Remarks: Sub project completed       Work Program Made On: 02-02-2015        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-January-20159.79  lakh
2.30-March-201515.13  lakh
3.02-May-201520.66  lakh
4.03-June-2015111.13  lakh
5.17-June-201547.24  lakh
6.16-July-201575.07  lakh
7.30-September-201514.80  lakh
8.05-November-201512.16  lakh
9.06-January-201611.34  lakh
10.21-March-201611.37  lakh
11.23-February-201711.71  lakh
Total 340.4  lakh
% Payment 99.95 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 310   No. of Test Done : 325    No. of Test Passed : 310   No. of Test Failed : 15   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.71
Number of Notice(s) issued: 84

Mobile Pic Upload

Number of Pics Available on Web Repository: 43
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-06-20161.625Mts checkingSudhir Kumar AEAEUDRP R&B Tehri See Pic
2.29-03-20164.800Sign boardsSudhir Kumar AEAEUDRP R&B Tehri See Pic
3.02-06-2015Km5.625BM work had been compleatedVirendra Singh PundirEEDEA WB Tehri See Pic
4.14-05-2015Km 0.100Laying with paverSamiksha SharmaJEUDRP R&B Tehri See Pic
5.14-05-2015Km 0.00Laying of B.MSamiksha SharmaJEUDRP R&B Tehri See Pic
6.07-04-2015Km 2.500ScupperSamiksha SharmaJEUDRP R&B Tehri See Pic
7.07-04-2015Km 2.150Bended wallSamiksha SharmaJEUDRP R&B Tehri See Pic
8.06-04-2015Km3.900Kempty Fall No 3Virendra Singh PundirEEDEA WB Tehri See Pic
9.06-04-2015Km3.925Kempty Lake No 2Virendra Singh PundirEEDEA WB Tehri See Pic
10.06-04-2015Km3.950KEMPTY LAKEVirendra Singh PundirEEDEA WB Tehri See Pic
11.06-04-2015Km5.075C/O ScupperVirendra Singh PundirEEDEA WB Tehri See Pic
12.06-04-2015Km4.350C/O ScupperVirendra Singh PundirEEDEA WB Tehri See Pic
13.06-04-2015Km2.525C/O ScupperVirendra Singh PundirEEDEA WB Tehri See Pic
14.06-04-2015Km2.150C/O R/Wall for opening irrigation CanalVirendra Singh PundirEEDEA WB Tehri See Pic
15.19-03-2015Km 2.175Clearance of slip for opening the canalVirendra Singh PundirEEDEA WB Tehri See Pic
16.18-03-2015Km 7.500.7.600Bwall at bendSamiksha SharmaJEUDRP R&B Tehri See Pic
17.18-03-2015Km 8.000ScupperSamiksha SharmaJEUDRP R&B Tehri See Pic
18.18-03-2015Km 8.500 8.600Laying of causewaySamiksha SharmaJEUDRP R&B Tehri See Pic
19.18-03-2015Km 8.400 8.500CausewaySamiksha SharmaJEUDRP R&B Tehri See Pic
20.18-03-2015Km 6.600 6.700BwallSamiksha SharmaJEUDRP R&B Tehri See Pic