Kempti Byepass Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2749 |
Sanction Cost: |
348.81 lakh |
Length:
|
5.750 KM. |
District: |
Tehri |
Block: |
Jaunpur |
Constituency: |
Dhanaulti |
Circle: |
Tehri WB Circle |
DEA: |
DEA Tehri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 18
Package Name: 
UDRP/PWD/04/49/RD/018
Tender Date: 03-05-2014
Current Status: Agreement signed
Achieved on Date: 03-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/04/49/RD/018
Contractor Name: Shiv Shankar Construction Company
|
Start Date: 10-11-2014
Intended Completion Date: 30-04-2016
Original End Date: 09-02-2016 |
Total Bond Cost: 30322641.85 (303.23 lakh)
Variation Cost: 3735039.50 (37.35 lakh) Hence Total Bond Cost is 34057681.35 (340.58 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 379025 for 25 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 500.00 m | 35.00 | 15-11-2014 | 15-04-2015 | 350.00 m | 350.00 m | 11.56 | 35.00 | 2. | GSB/RBI/G-1 | 0.25 KM | 0.20 | 01-03-2015 | 31-03-2015 | 0.34 KM | 0.34 KM | 0.07 | 0.20 | 3. | G-2 | 0.25 KM | 0.15 | 10-03-2015 | 15-04-2015 | 0.34 KM | 0.34 KM | 0.05 | 0.15 | 4. | G-3 | 0.25 KM | 0.21 | 01-04-2015 | 30-04-2015 | 0.76 KM | 0.76 KM | 0.07 | 0.21 | 5. | BM i/c Prime Coat, Tack Coat | 5.75 KM | 145.00 | 15-04-2015 | 10-06-2015 | 5.75 KM | 5.75 KM | 47.87 | 145.00 | 6. | SDBC i/c Tackcoat | 5.75 KM | 80.00 | 01-05-2015 | 15-06-2015 | 5.75 KM | 5.75 KM | 26.41 | 80.00 | 7. | Cause Way | 1.00 No | 7.80 | 01-03-2015 | 31-03-2015 | 2.00 No | 2.00 No | 2.58 | 7.80 | 8. | Culverts/Scupper | 11.00 No | 2.05 | 01-12-2014 | 31-03-2015 | 11.00 No | 11.00 No | 0.68 | 2.05 | 9. | longitudinal Drain | 2.26 m | 21.00 | 01-02-2015 | 15-04-2015 | 5260.00 m | 5260.00 m | 6.93 | 21.00 | 10. | Parapet | 250.00 No | 6.00 | 01-03-2015 | 15-04-2015 | 292.00 No | 292.00 No | 1.98 | 6.00 | 11. | Road Furniture | 180.00 No | 5.50 | 01-03-2015 | 14-04-2015 | 180.00 No | 180.00 No | 1.82 | 5.50 |
Total Amount: |
302.91 |
|
100 |
302.91 |
|
Remarks:
Sub project completed
Work Program Made On:
02-02-2015 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-January-2015 | 9.79 lakh | 2. | 30-March-2015 | 15.13 lakh | 3. | 02-May-2015 | 20.66 lakh | 4. | 03-June-2015 | 111.13 lakh | 5. | 17-June-2015 | 47.24 lakh | 6. | 16-July-2015 | 75.07 lakh | 7. | 30-September-2015 | 14.80 lakh | 8. | 05-November-2015 | 12.16 lakh | 9. | 06-January-2016 | 11.34 lakh | 10. | 21-March-2016 | 11.37 lakh | 11. | 23-February-2017 | 11.71 lakh |
Total |
340.4 lakh |
% Payment |
99.95 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 310 No. of Test Done : 325 No. of Test Passed : 310 No. of Test Failed : 15 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 93.71 |
Number of Notice(s) issued: 84 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 43 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-06-2016 | 1.625 | Mts checking | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
2. | 29-03-2016 | 4.800 | Sign boards | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
3. | 02-06-2015 | Km5.625 | BM work had been compleated | Virendra Singh Pundir | EE | DEA WB Tehri | See Pic |
4. | 14-05-2015 | Km 0.100 | Laying with paver | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
5. | 14-05-2015 | Km 0.00 | Laying of B.M | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
6. | 07-04-2015 | Km 2.500 | Scupper | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
7. | 07-04-2015 | Km 2.150 | Bended wall | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
8. | 06-04-2015 | Km3.900 | Kempty Fall No 3 | Virendra Singh Pundir | EE | DEA WB Tehri | See Pic |
9. | 06-04-2015 | Km3.925 | Kempty Lake No 2 | Virendra Singh Pundir | EE | DEA WB Tehri | See Pic |
10. | 06-04-2015 | Km3.950 | KEMPTY LAKE | Virendra Singh Pundir | EE | DEA WB Tehri | See Pic |
11. | 06-04-2015 | Km5.075 | C/O Scupper | Virendra Singh Pundir | EE | DEA WB Tehri | See Pic |
12. | 06-04-2015 | Km4.350 | C/O Scupper | Virendra Singh Pundir | EE | DEA WB Tehri | See Pic |
13. | 06-04-2015 | Km2.525 | C/O Scupper | Virendra Singh Pundir | EE | DEA WB Tehri | See Pic |
14. | 06-04-2015 | Km2.150 | C/O R/Wall for opening irrigation Canal | Virendra Singh Pundir | EE | DEA WB Tehri | See Pic |
15. | 19-03-2015 | Km 2.175 | Clearance of slip for opening the canal | Virendra Singh Pundir | EE | DEA WB Tehri | See Pic |
16. | 18-03-2015 | Km 7.500.7.600 | Bwall at bend | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
17. | 18-03-2015 | Km 8.000 | Scupper | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
18. | 18-03-2015 | Km 8.500 8.600 | Laying of causeway | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
19. | 18-03-2015 | Km 8.400 8.500 | Causeway | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
20. | 18-03-2015 | Km 6.600 6.700 | Bwall | Samiksha Sharma | JE | UDRP R&B Tehri | See Pic |
|
|