Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Jakhanidhar Garakot Paurikhal MR Work Completed
Project: UDRP-RB UID: 2727 Sanction Cost: 915.44  lakh Length: 24.500 KM.
District: Tehri Block: Jakhanidhar Constituency: Tehri Circle: Tehri WB Circle
DEA: DEA Tehri DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 39        Package Name:  UDRP/PWD/04/36/RD/039        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 12-06-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/04/36/RD/039      Contractor Name: Puran Chandra Ramola and Brothers
Start Date:  19-06-2014      Intended Completion Date:  18-12-2015      Original End Date:  18-09-2015
Total Bond Cost: 125298423.85 (1252.98 lakh)        Variation Cost: 15604981.66 (156.05 lakh)    Hence Total Bond Cost is   140903405.51 (1409.03 lakh) 
Sub Project Cost: 799.37  lakh        Variation Cost of Sub Project: 11900741.48  (119.01 lakh)       Total Sub Project Cost:   918.38 lakh
LD Analysis for Milestone1: calculated LD is Rs 2693907 for 43 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.29 KM6.3919-06-201430-03-20151.91 KM1.91 KM0.816.39
2.R/Wall, B/ Wall Type Protection works1089.00 m87.8301-07-201431-08-20151115.00 m1115.00 m11.0887.83
3.G-37.84 KM45.6901-01-201531-03-20157.84 KM7.84 KM5.7645.69
4.PC/CC i/c Prime Coat, Tack Coat24.50 KM255.6901-04-201517-09-201524.50 KM24.50 KM32.26255.69
5.Cause Way9.00 No69.8901-09-201430-08-201511.00 No11.00 No8.8269.89
6.Culverts/Scupper 22.00 No44.8401-09-201430-08-201522.00 No22.00 No5.6644.84
7.longitudinal Drain17150.00 m239.3401-09-201430-08-201523500.00 m23500.00 m30.2239.34
8.Crash Barrier1838.00 m40.2201-07-201518-09-20151853.00 m1853.00 m5.0740.22
9.Road Furniture25.00 No2.7201-07-201518-09-2015177.00 No177.00 No0.342.72
Total Amount: 792.61 100   792.61
Remarks: Sub project completed        Work Program Made On: 12-08-2014        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-201450.00  lakh
2.30-November-20143.53  lakh
3.31-December-201432.00  lakh
4.24-February-201582.56  lakh
5.31-March-2015138.28  lakh
6.19-May-2015145.29  lakh
7.09-June-201562.50  lakh
8.03-July-201567.13  lakh
9.05-August-2015135.55  lakh
10.18-August-201519.33  lakh
11.26-September-201588.66  lakh
12.07-November-201558.99  lakh
13.08-December-201516.47  lakh
14.31-March-201712.10  lakh
Total 912.39  lakh
% Payment99.35 %
Advance Amount:  193.58  lakh        Recovered Amount:  193.58  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 682   No. of Test Done : 735    No. of Test Passed : 682   No. of Test Failed : 53   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.44
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 90
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.22-08-201615.200Skip clearance n road openingSudhir Kumar AEAEUDRP R&B Tehri See Pic
2.10-08-20160.00Plantation by AESudhir Kumar AEAEUDRP R&B Tehri See Pic
3.24-12-2015Km3.500Village path yet to be repairVirendra Singh PundirEEUDRP R&B Tehri See Pic
4.24-12-2015Km4.025Old suppers yet to be cleanVirendra Singh PundirEEUDRP R&B Tehri See Pic
5.24-12-2015Km3.675Suppers yet to be clean on pkg 039Virendra Singh PundirEEUDRP R&B Tehri See Pic
6.24-12-2015Km3.250Suppers yet to be clean on pkg 039Virendra Singh PundirEEUDRP R&B Tehri See Pic
7.24-12-2015Km0.00Pkg 039Jakhanidhar Garakot Motor Road had been completedVirendra Singh PundirEEUDRP R&B Tehri See Pic
8.24-07-2015Km15.200_15.400Road closed due to chronic slipVirendra Singh PundirEEDEA WB Tehri See Pic
9.24-07-2015Km22.200_22.400Chronic slide zoneVirendra Singh PundirEEDEA WB Tehri See Pic
10.16-07-2015Km22.200_22.300Chronic slide zoneVirendra Singh PundirEEDEA WB Tehri See Pic
11.16-07-2015Km15.200_15.300Chronic slip zone, Road closed for trafficVirendra Singh PundirEEDEA WB Tehri See Pic
12.16-07-2015Km3.400_3.500CausewayVirendra Singh PundirEEDEA WB Tehri See Pic
13.16-07-2015Km 0.100Drain closed due to slipVirendra Singh PundirEEDEA WB Tehri See Pic
14.04-06-2015Km 4.800 4.900Laying of G3Samiksha SharmaJEUDRP R&B Tehri See Pic
15.04-06-2015Km 5.400Laying of P.CSamiksha SharmaJEUDRP R&B Tehri See Pic
16.04-06-2015Km 5.300 5.400Laying of plum concreteSamiksha SharmaJEUDRP R&B Tehri See Pic
17.07-05-2015Km7.500Testing of A Impact ValueVirendra Singh PundirEEDEA WB Tehri See Pic
18.07-05-2015Km 19.900Bitumen content testVirendra Singh PundirEEDEA WB Tehri See Pic
19.07-05-2015Km 19.900Bitumen content test(centrifugal extractor method)Virendra Singh PundirEEDEA WB Tehri See Pic
20.23-04-2015Km 7.000Laying of G3Samiksha SharmaJEUDRP R&B Tehri See Pic