Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Dabarkhal-Kunda-Mandwa- Ranichouri Motor road Work Completed
Project: UDRP-RB UID: 2662 Sanction Cost: 582.19  lakh Length: 7.000 KM.
District: Tehri Block: Narendra Nagar Constituency: Narendra Nagar Circle: Tehri WB Circle
DEA: DEA Tehri DSC: Egis International DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 123        Package Name:  UDRP/PWD/04/44/RD/112        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 13-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/04/44/RD/112      Contractor Name: Ramola Construction
Start Date:  20-10-2015      Intended Completion Date:  31-07-2017      Original End Date:  19-01-2017
Total Bond Cost: 38660077 (386.6 lakh)        Variation Cost: 15525827.27 (155.26 lakh)    Hence Total Bond Cost is   54185904.27 (541.86 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence6.69 KM57.6020-10-201515-07-20166.67 KM6.67 KM13.0557.60
2.R/Wall, B/ Wall Type Protection works2000.00 m173.1120-10-201520-09-20161800.00 m1800.00 m39.21173.11
3.GSB/RBI/G-15.75 KM36.0620-04-201620-08-20165.75 KM5.75 KM8.1736.06
4.G-26.61 KM34.8320-04-201620-08-20166.61 KM6.61 KM7.8934.83
5.G-36.61 KM3.9520-04-201615-09-20166.61 KM6.61 KM0.93.95
6.PC/CC i/c Prime Coat, Tack Coat6.51 KM42.8125-09-201615-12-20166.51 KM6.51 KM9.742.81
7.Culverts/Scupper 36.00 No67.1601-01-201610-08-201635.00 No35.00 No15.2167.16
8.longitudinal Drain6700.00 m16.4420-08-201620-10-20166500.00 m6500.00 m3.7216.44
9.Crash Barrier0.00 m0.0001-12-201601-12-20160.00 m0.00 m00.00
10.Parapet200.00 No6.9115-11-201620-01-2017235.00 No235.00 No1.576.91
11.Road Furniture128.00 No2.6101-01-201715-01-2017110.00 No110.00 No0.592.61
Total Amount: 441.48 100   441.48
Remarks: No Remarks       Work Program Made On: 10-12-2015        Updation of work program on: 14-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.13-January-201636.68  lakh
2.11-February-201641.86  lakh
3.28-March-201662.80  lakh
4.20-May-201621.48  lakh
5.11-July-201655.12  lakh
6.21-September-201660.16  lakh
7.26-October-201618.45  lakh
8.29-November-20167.96  lakh
9.28-December-201622.22  lakh
10.30-January-20178.55  lakh
11.28-February-201728.29  lakh
12.31-March-201731.25  lakh
13.27-April-201714.61  lakh
14.26-May-201724.56  lakh
15.21-June-201723.61  lakh
16.28-June-201717.39  lakh
17.07-October-201716.61  lakh
18.27-November-201725.72  lakh
19.26-February-201820.27  lakh
20.28-March-20183.22  lakh
21.30-November-20182.72  lakh
Total 543.53  lakh
% Payment 100.31 %
Advance Amount:  38.00  lakh        Recovered Amount:  38.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1302   No. of Test Done : 1451    No. of Test Passed : 1378   No. of Test Failed : 73   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.88
Number of Notice(s) issued: 73

Mobile Pic Upload

Number of Pics Available on Web Repository: 229
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-12-201716.600World Bank mission visitSudhir Kumar AEAEUDRP R&B Tehri See Pic
2.19-12-201716.600World Bank mission visitSudhir Kumar AEAEUDRP R&B Tehri See Pic
3.26-07-201715.890Tree plantation during harelaGaurav PantSite SupervisorDSC2 WB R&B Tehri See Pic
4.10-07-201710.400SRMD, Road blocked due to heavy boulderGaurav PantSite SupervisorDSC2 WB R&B Tehri See Pic
5.06-06-2017Ch 11.100Laying and rolling of PCSaurab ChauhanAEUDRP R&B Tehri See Pic
6.17-05-201715.305Compaction of PC with static RollerGaurav PantSite SupervisorDSC2 WB R&B Tehri See Pic
7.20-04-201713+875Laying of P.C compacted by static Rolar.Vikas BadoniSite SupervisorDSC2 R&B WB Tehri See Pic
8.20-04-201713+400Gradation test for Premix Carpet.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
9.15-04-201712+600 LabBitumen Extraction Test for PC.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
10.12-04-201713+550Laying of seal coat in P.C.Vikas BadoniSite SupervisorDSC2 R&B WB Tehri See Pic
11.11-04-201712+600Bitumen extraction test for P.C.Vikas BadoniSite SupervisorDSC2 R&B WB Tehri See Pic
12.01-04-201712+620AIV test for Premix Carpet.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
13.01-04-201712+620Flakiness test for Premix Carpet.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
14.25-03-201714+500Laying of PC compacted by static Rolar.Vikas BadoniSite SupervisorDSC2 R&B WB Tehri See Pic
15.20-03-201714+700Laying of P.C compacted by static Rolar.Vikas BadoniSite SupervisorDSC2 R&B WB Tehri See Pic
16.19-03-201714+825Laying of seal coat in P.C compacted by static Rolar.Vikas BadoniSite SupervisorDSC2 R&B WB Tehri See Pic
17.19-03-201714+800Laying of P.C compacted by static Rolar.Vikas BadoniSite SupervisorDSC2 R&B WB Tehri See Pic
18.18-03-201714+925PC laying/Rolling in progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
19.17-03-201714+925Laying of P.C compacted by static Rolar.Vikas BadoniSite SupervisorDSC2 R&B WB Tehri See Pic
20.16-03-201715+000Laying seal coat in P.C compacted by static Rolar.Vikas BadoniSite SupervisorDSC2 R&B WB Tehri See Pic