Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Chaka-Pendarsh Motor raod Work Completed
Project: UDRP-RB UID: 2652 Sanction Cost: 417.14  lakh Length: 8.850 KM.
District: Tehri Block: Narendra Nagar Constituency: Narendra Nagar Circle: Tehri WB Circle
DEA: DEA Tehri DSC: Egis International DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 74        Package Name:  UDRP/PWD/04/44/RD/064        Tender Date: 15-12-2015        Current Status: Agreement signed        Achieved on Date: 06-04-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/04/44/RD/064      Contractor Name: O. P. Builders
Start Date:  13-04-2016      Intended Completion Date:  31-12-2017      Original End Date:  12-07-2017
Total Bond Cost: 41156128.5 (411.56 lakh)        Variation Cost: 3803382.19 (38.03 lakh)    Hence Total Bond Cost is   44959510.69 (449.6 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 61734 for 3 days        LD Analysis for Milestone2: calculated LD is Rs 2345892 for 114 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works1313.00 m30.2701-06-201615-09-20161090.00 m1090.00 m7.9930.27
2.GSB/RBI/G-10.00 KM0.0001-06-201630-11-20160.00 KM0.00 KM00.00
3.G-22.85 KM19.0901-06-201630-11-20162.49 KM2.49 KM5.0419.09
4.G-32.85 KM19.2201-06-201630-11-20162.93 KM2.93 KM5.0719.22
5.PC/CC i/c Prime Coat, Tack Coat8.85 KM8.6201-10-201631-03-20178.85 KM8.85 KM2.288.62
6.BM i/c Prime Coat, Tack Coat8.85 KM161.1901-10-201631-03-20178.79 KM8.79 KM42.53161.19
7.SDBC i/c Tackcoat8.85 KM100.2501-10-201631-03-20178.79 KM8.79 KM26.45100.25
8.Cause Way3.00 No3.0501-05-201630-04-20172.00 No2.00 No0.813.05
9.Culverts/Scupper 13.00 No26.4701-06-201620-10-201614.00 No14.00 No6.9926.47
10.longitudinal Drain584.00 m10.1501-05-201631-08-20168550.00 m8550.00 m2.6810.15
11.Crash Barrier0.00 m0.0001-03-201730-06-20170.00 m0.00 m00.00
12.Road Furniture36.00 No0.6701-03-201730-06-201736.00 No36.00 No0.180.67
Total Amount: 378.98 100   378.98
Remarks: No Remarks       Work Program Made On: 03-07-2016        Updation of work program on: 15-11-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-July-201635.02  lakh
2.08-September-201631.50  lakh
3.30-September-201648.56  lakh
4.26-December-201610.25  lakh
5.29-May-201731.91  lakh
6.30-June-2017264.05  lakh
7.12-October-20174.45  lakh
8.28-November-201710.46  lakh
9.30-May-201812.63  lakh
10.30-November-20182.91  lakh
Total 451.74  lakh
% Payment 100.49 %
Advance Amount:  222.41  lakh        Recovered Amount:  222.41  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1110   No. of Test Done : 1151    No. of Test Passed : 1110   No. of Test Failed : 41   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 82.59
Number of Notice(s) issued: 69

Mobile Pic Upload

Number of Pics Available on Web Repository: 194
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-03-2018Ch 8.000JointKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
2.24-01-20181.800Site inspection by EE Mam WB PWD TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
3.06-12-2017Ch 0.400Parapets with white wasKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
4.29-06-20170.200Core cuttingSudhir Kumar AEAEUDRP R&B Tehri See Pic
5.08-06-20178.700SDBC work in progressSudhir Kumar AEAEUDRP R&B Tehri See Pic
6.08-06-20177.435Site inspection by SE Sir TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
7.06-06-20177.887Bm rollingKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
8.06-06-20177.900Laying of BMSudhir Kumar AEAEUDRP R&B Tehri See Pic
9.02-06-20177+875BM laying in Progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
10.01-06-2017Ch 8.200Bm rollingKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
11.31-05-20178.700Rolling of BMSudhir Kumar AEAEUDRP R&B Tehri See Pic
12.31-05-20171.250Checking thickness of BM / SDBC by QC DSC 2 Tehri . AE.JE WB Tehri .n Contractor,s Engineer . It found 75 mm (BM +SDBC)Sudhir Kumar AEAEUDRP R&B Tehri See Pic
13.16-05-20176.250Sieve test for G3Sudhir Kumar AEAEUDRP R&B Tehri See Pic
14.16-05-2017Laying of G35.400Sudhir Kumar AEAEUDRP R&B Tehri See Pic
15.16-05-20178.500G3 testingSudhir Kumar AEAEUDRP R&B Tehri See Pic
16.09-05-2017Ch7.300Parti filling under constructionKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
17.27-04-20177+840Site visit by Team Leader.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
18.24-04-20177+450Gradation test for WBM G3.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
19.13-04-20173.975Meeting/ Discuss about problems with Jakholi villagers by AE WB TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
20.11-04-2017Ch. 3.980Site visit AE sir for villagers village pathKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic