Bhaldiyana bend to Kamand MRoad
Work Completed
|
Project: |
UDRP-RB |
UID: |
2641 |
Sanction Cost: |
594.57 lakh |
Length:
|
7.430 KM. |
District: |
Tehri |
Block: |
Kouldhar |
Constituency: |
Pratapnagar |
Circle: |
Tehri WB Circle |
DEA: |
DEA Tehri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 17
Package Name: 
UDRP/PWD/04/48/RD/017
Tender Date: 14-08-2014
Current Status: Agreement signed
Achieved on Date: 27-03-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/04/48/RD/017
Contractor Name: Maa Bhagwati Construction company
|
Start Date: 03-04-2015
Intended Completion Date: 10-10-2016
Original End Date: 02-07-2016 |
Total Bond Cost: 59457484.12 (594.57 lakh)
Variation Cost: -3035955.59 (-30.36 lakh) Hence Total Bond Cost is 56421528.53 (564.22 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 2229675 for 75 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.21 KM | 5.03 | 20-05-2015 | 10-05-2016 | 0.21 KM | 0.21 KM | 0.89 | 5.03 | 2. | R/Wall, B/ Wall Type Protection works | 1526.00 m | 167.25 | 15-04-2015 | 20-08-2016 | 1526.00 m | 1526.00 m | 29.47 | 167.25 | 3. | GSB/RBI/G-1 | 0.28 KM | 2.68 | 15-08-2015 | 15-08-2016 | 0.28 KM | 0.28 KM | 0.47 | 2.68 | 4. | G-2 | 0.29 KM | 3.17 | 20-08-2015 | 15-08-2016 | 0.29 KM | 0.29 KM | 0.56 | 3.17 | 5. | G-3 | 0.45 KM | 3.09 | 25-08-2015 | 15-08-2016 | 0.45 KM | 0.45 KM | 0.55 | 3.09 | 6. | BM i/c Prime Coat, Tack Coat | 7.43 KM | 163.43 | 25-09-2015 | 25-10-2016 | 7.43 KM | 7.43 KM | 28.79 | 163.43 | 7. | SDBC i/c Tackcoat | 7.43 KM | 96.88 | 15-10-2015 | 30-10-2016 | 7.43 KM | 7.43 KM | 17.07 | 96.88 | 8. | Cause Way | 4.00 No | 16.17 | 20-10-2015 | 15-07-2016 | 4.00 No | 4.00 No | 2.85 | 16.17 | 9. | Culverts/Scupper | 19.00 No | 38.10 | 20-07-2015 | 10-05-2016 | 19.00 No | 19.00 No | 6.71 | 38.10 | 10. | longitudinal Drain | 7300.00 m | 27.39 | 15-08-2015 | 20-07-2016 | 7300.00 m | 7300.00 m | 4.83 | 27.39 | 11. | Crash Barrier | 200.00 m | 32.00 | 15-05-2016 | 25-06-2016 | 200.00 m | 200.00 m | 5.64 | 32.00 | 12. | Parapet | 300.00 No | 10.25 | 15-11-2015 | 30-07-2016 | 300.00 No | 300.00 No | 1.81 | 10.25 | 13. | Road Furniture | 84.00 No | 2.15 | 20-05-2016 | 30-10-2016 | 76.00 No | 76.00 No | 0.38 | 2.15 |
Total Amount: |
567.59 |
|
100 |
567.59 |
|
Remarks:
Sub Project Completed
Work Program Made On:
31-08-2015 } ?>
Updation of work program on:
25-09-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-August-2015 | 19.52 lakh | 2. | 07-November-2015 | 36.22 lakh | 3. | 15-December-2015 | 27.63 lakh | 4. | 31-December-2015 | 134.25 lakh | 5. | 25-January-2016 | 41.39 lakh | 6. | 05-March-2016 | 23.82 lakh | 7. | 29-March-2016 | 23.27 lakh | 8. | 19-May-2016 | 32.09 lakh | 9. | 22-July-2016 | 13.00 lakh | 10. | 31-August-2016 | 31.25 lakh | 11. | 28-November-2016 | 131.84 lakh | 12. | 21-June-2017 | 14.52 lakh | 13. | 28-November-2017 | 35.36 lakh |
Total |
564.16 lakh |
% Payment |
99.99 % |
|
Advance Amount: 180.93 lakh
Recovered Amount: 180.93 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 833 No. of Test Done : 905 No. of Test Passed : 874 No. of Test Failed : 31 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.22 |
Number of Notice(s) issued: 92 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 264 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-12-2017 | 7.300 | Site inspection by World Bank Mission pkg 017 | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
2. | 19-12-2017 | 7.425 | Site inspection by World Bank Mission | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
3. | 17-12-2017 | 0.660 | Work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
4. | 25-05-2017 | 4.100 | Site inspection by World Bank Team | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
5. | 25-05-2017 | 7.425 | World Bank mission Visit with PIU and DSC staff of Pkg 017 | Gaurav Pant | Site Supervisor | DSC2 WB R&B Tehri | See Pic |
6. | 24-05-2017 | 0.00 | Site inspection by World Bank Team | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
7. | 19-05-2017 | 7.425 | Site inspection by TL Sir, AE WB Tehri and Q C. DSC 2 Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
8. | 18-05-2017 | Ch 7.425 | Road end point | Kuldeep Kumar Karanwal | JE | UDRP R&B Tehri | See Pic |
9. | 18-05-2017 | Ch. 0.000 | Road start point | Kuldeep Kumar Karanwal | JE | UDRP R&B Tehri | See Pic |
10. | 08-02-2017 | 0.125 | Joint inspection by AE,JE WB Tehri, DSE 2 Tehri and AE, JE, PWD Chamba for Road Handover | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
11. | 17-10-2016 | Ch.0.800 | Wire crates complete | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
12. | 10-10-2016 | 3+100 | SDBC laying in Progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
13. | 10-10-2016 | Dobra plant | SDBC production in Progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
14. | 10-10-2016 | 2+100 | SDBC laying in Progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
15. | 10-10-2016 | Chamba Plant | SDBC production in Progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
16. | 10-10-2016 | Dobra plant | Bitumen Extraction Test for SDBC. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
17. | 09-10-2016 | 1.800 | SDBC work in pkg 017 Bhaldiyana bend to Kamand M/R | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
18. | 08-10-2016 | SDBC production in Progress. | SDBC production in Progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
19. | 07-10-2016 | 0+150 | SDBC final rolling. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
20. | 07-10-2016 | 0+050 | SDBC laying in Progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
|
|