Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bhaldiyana bend to Kamand MRoad Work Completed
Project: UDRP-RB UID: 2641 Sanction Cost: 594.57  lakh Length: 7.430 KM.
District: Tehri Block: Kouldhar Constituency: Pratapnagar Circle: Tehri WB Circle
DEA: DEA Tehri DSC: Egis International DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 17        Package Name:  UDRP/PWD/04/48/RD/017        Tender Date: 14-08-2014        Current Status: Agreement signed        Achieved on Date: 27-03-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/04/48/RD/017      Contractor Name: Maa Bhagwati Construction company
Start Date:  03-04-2015      Intended Completion Date:  10-10-2016      Original End Date:  02-07-2016
Total Bond Cost: 59457484.12 (594.57 lakh)        Variation Cost: -3035955.59 (-30.36 lakh)    Hence Total Bond Cost is   56421528.53 (564.22 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 2229675 for 75 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.21 KM5.0320-05-201510-05-20160.21 KM0.21 KM0.895.03
2.R/Wall, B/ Wall Type Protection works1526.00 m167.2515-04-201520-08-20161526.00 m1526.00 m29.47167.25
3.GSB/RBI/G-10.28 KM2.6815-08-201515-08-20160.28 KM0.28 KM0.472.68
4.G-20.29 KM3.1720-08-201515-08-20160.29 KM0.29 KM0.563.17
5.G-30.45 KM3.0925-08-201515-08-20160.45 KM0.45 KM0.553.09
6.BM i/c Prime Coat, Tack Coat7.43 KM163.4325-09-201525-10-20167.43 KM7.43 KM28.79163.43
7.SDBC i/c Tackcoat7.43 KM96.8815-10-201530-10-20167.43 KM7.43 KM17.0796.88
8.Cause Way4.00 No16.1720-10-201515-07-20164.00 No4.00 No2.8516.17
9.Culverts/Scupper 19.00 No38.1020-07-201510-05-201619.00 No19.00 No6.7138.10
10.longitudinal Drain7300.00 m27.3915-08-201520-07-20167300.00 m7300.00 m4.8327.39
11.Crash Barrier200.00 m32.0015-05-201625-06-2016200.00 m200.00 m5.6432.00
12.Parapet300.00 No10.2515-11-201530-07-2016300.00 No300.00 No1.8110.25
13.Road Furniture84.00 No2.1520-05-201630-10-201676.00 No76.00 No0.382.15
Total Amount: 567.59 100   567.59
Remarks: Sub Project Completed       Work Program Made On: 31-08-2015        Updation of work program on: 25-09-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.13-August-201519.52  lakh
2.07-November-201536.22  lakh
3.15-December-201527.63  lakh
4.31-December-2015134.25  lakh
5.25-January-201641.39  lakh
6.05-March-201623.82  lakh
7.29-March-201623.27  lakh
8.19-May-201632.09  lakh
9.22-July-201613.00  lakh
10.31-August-201631.25  lakh
11.28-November-2016131.84  lakh
12.21-June-201714.52  lakh
13.28-November-201735.36  lakh
Total 564.16  lakh
% Payment 99.99 %
Advance Amount:  180.93  lakh        Recovered Amount:  180.93  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 833   No. of Test Done : 905    No. of Test Passed : 874   No. of Test Failed : 31   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.22
Number of Notice(s) issued: 92

Mobile Pic Upload

Number of Pics Available on Web Repository: 264
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-12-20177.300Site inspection by World Bank Mission pkg 017Sudhir Kumar AEAEUDRP R&B Tehri See Pic
2.19-12-20177.425Site inspection by World Bank MissionSudhir Kumar AEAEUDRP R&B Tehri See Pic
3.17-12-20170.660Work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
4.25-05-20174.100Site inspection by World Bank TeamSudhir Kumar AEAEUDRP R&B Tehri See Pic
5.25-05-20177.425World Bank mission Visit with PIU and DSC staff of Pkg 017Gaurav PantSite SupervisorDSC2 WB R&B Tehri See Pic
6.24-05-20170.00Site inspection by World Bank TeamSudhir Kumar AEAEUDRP R&B Tehri See Pic
7.19-05-20177.425Site inspection by TL Sir, AE WB Tehri and Q C. DSC 2 TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
8.18-05-2017Ch 7.425Road end pointKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
9.18-05-2017Ch. 0.000Road start pointKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
10.08-02-20170.125Joint inspection by AE,JE WB Tehri, DSE 2 Tehri and AE, JE, PWD Chamba for Road HandoverSudhir Kumar AEAEUDRP R&B Tehri See Pic
11.17-10-2016Ch.0.800Wire crates completeNawal KishoreSite SupervisorDSC2 R&B WB Tehri See Pic
12.10-10-20163+100SDBC laying in Progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
13.10-10-2016Dobra plantSDBC production in Progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
14.10-10-20162+100SDBC laying in Progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
15.10-10-2016Chamba PlantSDBC production in Progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
16.10-10-2016Dobra plantBitumen Extraction Test for SDBC.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
17.09-10-20161.800SDBC work in pkg 017 Bhaldiyana bend to Kamand M/RSudhir Kumar AEAEUDRP R&B Tehri See Pic
18.08-10-2016SDBC production in Progress.SDBC production in Progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
19.07-10-20160+150SDBC final rolling.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
20.07-10-20160+050SDBC laying in Progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic