Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kandai Kamoldi Molkakhal MR Phase2 (Ch-0 to 10 Km) Agreement signed
Project: UDRP-RB UID: 2568 Sanction Cost: 918.72  lakh Length: 10.000 KM.
District: Rudraprayag Block: 0017 Constituency: 7 Circle:
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 145        Package Name:  UDRP/PWD/03/RD/129        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/RD/129      Contractor Name: Tomar Construction Company
Start Date:  21-11-2017      Intended Completion Date:  20-02-2019     
Total Bond Cost: 73800626.64 (738.01 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 6937200 for 188 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence10.00 KM82.6823-11-201725-05-201810.00 KM7.00 KM7.8457.87
2.R/Wall, B/ Wall Type Protection works1384.00 m148.6615-12-201725-09-20181384.00 m450.00 m6.5548.34
3.G-214.25 KM89.0105-01-201820-09-201814.25 KM1.50 KM1.279.37
4.G-37.65 KM45.6510-04-201815-10-20187.65 KM0.00 KM00.00
5.PC/CC i/c Prime Coat, Tack Coat10.00 KM115.9829-04-201831-10-201810.00 KM0.00 KM00.00
6.Cause Way3.00 No15.9925-05-201831-07-20183.00 No0.00 No00.00
7.Culverts/Scupper 28.00 No66.4101-12-201715-06-201828.00 No8.00 No2.5718.98
8.longitudinal Drain9955.00 m40.6815-04-201815-10-20189955.00 m0.00 m00.00
9.Crash Barrier1450.00 m36.2525-09-201815-12-20181450.00 m0.00 m00.00
10.Parapet950.00 No34.3015-06-201830-10-2018950.00 No0.00 No00.00
11.Road Furniture594.00 No18.1815-11-201820-02-2019594.00 No0.00 No00.00
12.Other Allied Works & Finishing Work 1.00 Job44.3315-10-201820-02-20191.00 Job0.00 Job00.00
Total Amount: 738.12 18.23   134.56
Remarks: No Remarks       Work Program Made On: 29-12-2017        Updation of work program on: 24-04-2018       
Work Program Status:Program Failed
Financial Progress
SNo. Date Payment
1.17-February-201848.18  lakh
2.28-March-201855.24  lakh
Total 103.42  lakh
% Payment 14.01 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill should be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 288   No. of Test Done : 305    No. of Test Passed : 300   No. of Test Failed : 5   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.00
Number of Notice(s) issued: 31

Mobile Pic Upload

Number of Pics Available on Web Repository: 36
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.16-05-2018Site labA.I.v. testSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
2.20-04-2018At labWbm g2 aiv test and result found satisfactoryPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
3.20-04-2018At labWbm g2 gradation test, material found oversize and instructions given to contractor urgently rebroken stone.Prashant KumarQCDSC4 R&B WB Rudraprayag See Pic
4.10-04-20185+225Checkup of labours by CMS and physician, District hospital, Rudraprayag during health camp at Kandai-Kamoldi MRPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
5.10-04-20185+225On the occasion of world health week, health camp settup on site of kandai kamoldi molkhakhalPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
6.29-03-20185+100Water sprinklingPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
7.20-03-20184+900Slab castingPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
8.17-03-20187+000Social expert neha mam site visitPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
9.13-03-20183/050Slab reinforcementSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
10.12-03-2018at ch. 4+000Public grievance discussion Dpm sir, so. e. Sir and ee sirPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
11.12-03-20180+000Dpm sir visit with s.e.sir and ee sirPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
12.04-03-20182+800Hill side cuttingPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
13.14-02-20184/700Hill side cuttingSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
14.08-02-20184+000Gram sabha held for grievance discussion at shipuriPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
15.01-02-20182/300Dumping zoneSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
16.01-02-20181/350Damping zoneSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
17.28-01-2018At labFire safetyPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
18.25-01-20181+450Scupper slab castingPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
19.23-01-2018SE sir and EE sir site visitPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
20.22-01-20182/050Hill side cuttingSuresh Chandra SharmaJEUDRP R&B Tehri See Pic