Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kandai Kamoldi Molkakhal MR Phase2 (Ch-0 to 10 Km) Agreement signed
Project: UDRP-RB UID: 2568 Sanction Cost: 918.72  lakh Length: 10.000 KM.
District: Rudraprayag Block: 0017 Constituency: 7 Circle:
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 145        Package Name:  UDRP/PWD/03/RD/129        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/RD/129      Contractor Name: Tomar Construction Company
Start Date:  21-11-2017      Intended Completion Date:  20-02-2019     
Total Bond Cost: 73800626.64 (738.01 lakh)        Variation Cost: 8592916.48 (85.93 lakh)    Hence Total Bond Cost is   82393543.12 (823.94 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 13505400 for 366 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence10.00 KM91.3523-11-201715-12-201810.00 KM9.00 KM9.9882.21
2.R/Wall, B/ Wall Type Protection works1384.00 m169.4615-12-201720-12-20181384.00 m800.00 m11.8997.96
3.G-214.25 KM89.0105-01-201815-12-201814.25 KM9.00 KM6.8256.22
4.G-38.41 KM50.2615-07-201820-09-20188.41 KM1.00 KM0.735.98
5.PC/CC i/c Prime Coat, Tack Coat10.00 KM115.9811-09-201820-02-201910.00 KM0.00 KM00.00
6.Cause Way4.00 No25.5415-06-201830-12-20184.00 No1.00 No0.776.38
7.Culverts/Scupper 28.00 No95.6401-12-201730-12-201828.00 No18.00 No7.4661.48
8.longitudinal Drain9955.00 m45.7705-06-201815-12-20189955.00 m5000.00 m2.7922.99
9.Crash Barrier1450.00 m41.4010-01-201920-02-20191450.00 m0.00 m00.00
10.Parapet950.00 No34.3025-10-201831-01-2019950.00 No0.00 No00.00
11.Road Furniture594.00 No21.7801-11-201831-12-2018594.00 No0.00 No00.00
12.Other Allied Works & Finishing Work 1.00 Job43.4515-10-201820-02-20191.00 Job0.00 Job00.00
Total Amount: 823.94 40.44   333.22
Remarks: No Remarks       Work Program Made On: 29-12-2017        Updation of work program on: 12-11-2018       
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.17-February-201848.18  lakh
2.28-March-201855.24  lakh
3.16-May-201826.32  lakh
4.05-July-201835.17  lakh
5.21-August-201839.20  lakh
6.30-September-201843.85  lakh
7.31-October-201836.83  lakh
Total 284.79  lakh
% Payment 34.56 %
Advance Amount:  5.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  5.00  lakh        * Advances are at package level not sub project level
Analysis:Bill should be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 395   No. of Test Done : 414    No. of Test Passed : 409   No. of Test Failed : 5   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.68
Number of Notice(s) issued: 32

Mobile Pic Upload

Number of Pics Available on Web Repository: 77
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-10-2018Bitumen batching plantTesting of bitumen contentRavi BishtJEUDRP R&B Guptkashi See Pic
2.30-10-201810/000Pc WorkSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
3.28-10-2018Bitumen batching plantBatching plant inspection by SE sirRavi BishtJEUDRP R&B Guptkashi See Pic
4.16-10-2018Km 7/00Cause way curingRavi BishtJEUDRP R&B Guptkashi See Pic
5.15-10-2018Km 2.600Slip removalRavi BishtJEUDRP R&B Guptkashi See Pic
6.29-09-2018Km 0/800Slip removalRavi BishtJEUDRP R&B Guptkashi See Pic
7.26-09-2018Km 2.7RR dry R/w.Ravi BishtJEUDRP R&B Guptkashi See Pic
8.18-09-20189/900W.b.m g2 seive analysisSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
9.18-09-20187/4003 m span culvert abutment mesoneriSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
10.13-09-20189/300Scupper slab reinforcementSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
11.11-09-2018Km 4.7Scupper slab castingRavi BishtJEUDRP R&B Guptkashi See Pic
12.05-09-2018QC labSite visit and lab inspection by SE sir.Ravi BishtJEUDRP R&B Guptkashi See Pic
13.30-08-20187/4003m span Culvert abutment mesoneriSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
14.29-08-2018Km 3.975Excavation for scupperRavi BishtJEUDRP R&B Guptkashi See Pic
15.24-08-2018Km 4.7seive analysis of sandRavi BishtJEUDRP R&B Guptkashi See Pic
16.21-08-20189/275Drain workSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
17.19-08-20187/000Scupper bed block castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
18.17-08-20181/000R/wall drySuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
19.17-08-20188/250E.e sir sait vigitSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
20.16-08-2018Km 4.7Scupper abutment work in progressRavi BishtJEUDRP R&B Guptkashi See Pic