Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kandai Kamoldi Molkakhal MR Phase2 (Ch-0 to 10 Km) Agreement signed
Project: UDRP-RB UID: 2568 Sanction Cost: 918.72  lakh Length: 10.000 KM.
District: Rudraprayag Block: 0017 Constituency: 7 Circle:
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 145        Package Name:  UDRP/PWD/03/RD/129        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/RD/129      Contractor Name: Tomar Construction Company
Start Date:  21-11-2017      Intended Completion Date:  20-02-2019     
Total Bond Cost: 73800626.64 (738.01 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 10258200 for 278 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence10.00 KM82.6823-11-201730-07-201810.00 KM9.00 KM10.0874.41
2.R/Wall, B/ Wall Type Protection works1384.00 m148.6615-12-201730-10-20181384.00 m600.00 m8.7364.45
3.G-214.25 KM89.0105-01-201815-09-201814.25 KM7.25 KM6.1445.29
4.G-37.65 KM45.6515-07-201820-09-20187.65 KM0.00 KM00.00
5.PC/CC i/c Prime Coat, Tack Coat10.00 KM115.9811-09-201831-10-201810.00 KM0.00 KM00.00
6.Cause Way3.00 No15.9915-06-201820-09-20183.00 No0.00 No00.00
7.Culverts/Scupper 28.00 No66.4101-12-201715-09-201828.00 No12.00 No3.8628.46
8.longitudinal Drain9955.00 m40.6805-06-201815-12-20189955.00 m2000.00 m1.118.17
9.Crash Barrier1450.00 m36.2510-10-201831-12-20181450.00 m0.00 m00.00
10.Parapet950.00 No34.3015-07-201831-12-2018950.00 No0.00 No00.00
11.Road Furniture594.00 No18.1801-11-201831-12-2018594.00 No0.00 No00.00
12.Other Allied Works & Finishing Work 1.00 Job44.3315-10-201820-02-20191.00 Job0.00 Job00.00
Total Amount: 738.12 29.91   220.78
Remarks: No Remarks       Work Program Made On: 29-12-2017        Updation of work program on: 22-05-2018       
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.17-February-201848.18  lakh
2.28-March-201855.24  lakh
3.16-May-201826.32  lakh
4.05-July-201835.17  lakh
Total 164.91  lakh
% Payment 22.35 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill should be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 347   No. of Test Done : 366    No. of Test Passed : 361   No. of Test Failed : 5   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.96
Number of Notice(s) issued: 32

Mobile Pic Upload

Number of Pics Available on Web Repository: 61
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-08-20187/000Scupper bed block castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
2.17-08-20181/000R/wall drySuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
3.17-08-20188/250E.e sir sait vigitSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
4.16-08-2018Km 4.7Scupper abutment work in progressRavi BishtJEUDRP R&B Guptkashi See Pic
5.13-08-2018Km 0.9Casting of Scupper slabRavi BishtJEUDRP R&B Guptkashi See Pic
6.11-08-2018Km 2.800Casting of Scupper bed blockRavi BishtJEUDRP R&B Guptkashi See Pic
7.11-08-2018Km 1.060SRMD, Kandai kamoldi road excavation for R/WRavi BishtJEUDRP R&B Guptkashi See Pic
8.08-08-20182/800Road clearing in progressSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
9.30-07-20181/150thickness checking of wbm, 2 layer g2, totel thickness 17 cm.Suresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
10.25-07-20185/200Wire create workSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
11.23-07-20184/900Scupper slab castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
12.23-07-20183/975Scupper slab reinforcementSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
13.18-07-20183/195Scupper slab castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
14.14-07-20185/500E.E. sir sait visitSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
15.14-07-20181/135Hill side cuttingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
16.10-07-20181/350Scupper slab castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
17.05-07-20181/450Scupper slab castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
18.05-07-20181/135Scupper slab castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
19.30-06-20180/470Slip ClearanceSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
20.30-06-20186/575Hill side cuttingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic