Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kandai Kamoldi Molkakhal MR Phase2 (Ch-0 to 10 Km) Agreement signed
Project: UDRP-RB UID: 2568 Sanction Cost: 918.72  lakh Length: 10.000 KM.
District: Rudraprayag Block: 0017 Constituency: 7 Circle:
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 145        Package Name:  UDRP/PWD/03/RD/129        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/RD/129      Contractor Name: Tomar Construction Company
Start Date:  21-11-2017      Intended Completion Date:  20-02-2019     
Total Bond Cost: 73800626.64 (738.01 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 3616200 for 98 days        LD Analysis for Milestone2: calculated LD is Rs 3616200 for 98 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence10.00 KM82.6823-11-201705-04-201810.00 KM1.00 KM1.128.27
2.R/Wall, B/ Wall Type Protection works1384.00 m148.6615-12-201725-09-20181384.00 m0.00 m00.00
3.G-214.25 KM89.0105-01-201820-09-201814.25 KM0.00 KM00.00
4.G-37.65 KM45.6515-03-201815-10-20187.65 KM0.00 KM00.00
5.PC/CC i/c Prime Coat, Tack Coat10.00 KM115.9825-03-201831-10-201810.00 KM0.00 KM00.00
6.Cause Way3.00 No15.9910-02-201831-05-20183.00 No0.00 No00.00
7.Culverts/Scupper 28.00 No66.4101-12-201721-05-201828.00 No2.00 No0.644.74
8.longitudinal Drain9955.00 m40.6815-04-201815-10-20189955.00 m0.00 m00.00
9.Crash Barrier1450.00 m36.2525-09-201815-12-20181450.00 m0.00 m00.00
10.Parapet950.00 No34.3015-04-201830-10-2018950.00 No0.00 No00.00
11.Road Furniture594.00 No18.1815-11-201820-02-2019594.00 No0.00 No00.00
12.Other Allied Works & Finishing Work 1.00 Job44.3315-10-201820-02-20191.00 Job0.00 Job00.00
Total Amount: 738.12 1.76   13.01
Remarks: No Remarks       Work Program Made On: 29-12-2017        Updation of work program on: 04-01-2018       
Work Program Status:Program Failed
Financial Progress
No Financial Progress.
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles, labour licence
Environment & Social Compliances(Sub Project level): water sprinkling, Query
Detailed report of this subproject
Quality
No. of Test Required : 78   No. of Test Done : 86    No. of Test Passed : 85   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 79.59
Number of Notice(s) issued: 29

Mobile Pic Upload

Number of Pics Available on Web Repository: 24
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.14-02-20184/700Hill side cuttingSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
2.08-02-20184+000Gram sabha held for grievance discussion at shipuriPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
3.01-02-20182/300Dumping zoneSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
4.01-02-20181/350Damping zoneSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
5.28-01-2018At labFire safetyPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
6.25-01-20181+450Scupper slab castingPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
7.23-01-2018SE sir and EE sir site visitPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
8.22-01-20182/050Hill side cuttingSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
9.19-01-20187/300Scupper slab castingSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
10.11-01-20187/100Scupper slab castingSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
11.11-01-20181/700Hill side cuttingSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
12.10-01-20188/275Hill side cuttingSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
13.10-01-20187/175Scupper slabe castingSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
14.10-01-20187+175Slump testPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
15.21-12-20171+110Hill side cutting work in progressPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
16.19-12-20171+000Hill side cutting work in progressPrashant KumarQCDSC4 R&B WB Rudraprayag See Pic
17.17-12-20170/975Hill side cuttingSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
18.14-12-20171/025Hill side cuttingSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
19.14-12-20177/300Scupper work in progressSuresh Chandra SharmaJEUDRP R&B Tehri See Pic
20.14-12-20177/900R.R stone mesoneri in 1:5Suresh Chandra SharmaJEUDRP R&B Tehri See Pic