Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ukhimath Mansoona MR (Uben area) Work Completed
Project: UDRP-RB UID: 2548 Sanction Cost: 200.57  lakh Length: 3.000 KM.
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 21        Package Name:  UDRP/PWD/03/40/RD/021        Tender Date: 01-02-2014        Current Status: Agreement signed        Achieved on Date: 22-05-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/40/RD/021      Contractor Name: Vijay Builders
Start Date:  29-05-2014      Intended Completion Date:  10-02-2016      Original End Date:  28-08-2015
Total Bond Cost: 69242751.29 (692.43 lakh)        Variation Cost: -3935394.25 (-39.35 lakh)    Hence Total Bond Cost is   65307357.04 (653.07 lakh) 
Sub Project Cost: 177.07  lakh        Variation Cost of Sub Project: 838866.40  (8.39 lakh)       Total Sub Project Cost:   185.46 lakh
LD Analysis for Milestone1: calculated LD is Rs 4466109 for 129 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works250.00 m18.2615-06-201430-09-2014250.00 m250.00 m10.6618.26
2.G-20.80 KM4.7201-08-201431-10-20140.80 KM0.80 KM2.764.72
3.G-30.50 KM2.1801-08-201431-10-20140.50 KM0.50 KM1.282.18
4.BM i/c Prime Coat, Tack Coat2.91 KM70.0801-02-201531-03-20152.91 KM2.91 KM40.9270.08
5.SDBC i/c Tackcoat2.91 KM33.9001-02-201531-03-20152.91 KM2.91 KM19.833.90
6.Cause Way1.00 No2.2001-07-201431-08-20141.00 No1.00 No1.292.20
7.Culverts/Scupper 3.00 No5.1301-07-201430-11-20143.00 No3.00 No35.13
8.longitudinal Drain1210.00 m20.0101-07-201430-11-20141210.00 m1210.00 m11.6820.01
9.Crash Barrier624.00 m13.7601-04-201515-12-2015624.00 m624.00 m8.0413.76
10.Road Furniture3.00 No1.0001-05-201520-12-20153.00 No3.00 No0.591.00
Total Amount: 171.24 100   171.24
Remarks: No Remarks       Work Program Made On: 01-08-2014        Updation of work program on: 20-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-September-201419.66  lakh
2.31-December-201410.41  lakh
3.30-March-20158.38  lakh
4.31-March-201533.44  lakh
5.08-May-201570.32  lakh
6.18-May-201534.75  lakh
7.30-May-20150.90  lakh
8.09-June-2015-10.09  lakh
9.13-August-20153.68  lakh
10.28-January-201611.91  lakh
11.03-July-20161.27  lakh
Total 184.63  lakh
% Payment99.55 %
Advance Amount:  50.00  lakh        Recovered Amount:  50.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 149   No. of Test Done : 162    No. of Test Passed : 118   No. of Test Failed : 44   Test report of this package      * Tests Information is at package level not sub project level
Quality ranking not done.
Number of Notice(s) issued: 1

Mobile Pic Upload

Number of Pics Available on Web Repository: 23
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-12-20162+00Slope checking by SE sir 7 the circleAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
2.21-12-20161+300Slope checking of dry wall by SE sir 7th circleAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
3.14-12-20152+075Crash barriarAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
4.13-12-20152.075Road Marking Thermoplastic paint CompletedR S RajputREDSC1 R&B WB Rudraprayag See Pic
5.17-08-20152+300Complete R/W top section bandedNaveen YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
6.03-08-201532.300R/wAnurag DevJEUDRP R&B Guptkashi See Pic
7.31-07-20152.300Construction of R/W..Anurag DevJEUDRP R&B Guptkashi See Pic
8.29-07-20152.300Construction of r/w in ukhimath manusuna m/RAnurag DevJEUDRP R&B Guptkashi See Pic
9.27-07-20152.300R/W Inspection by CER S RajputREDSC1 R&B WB Rudraprayag See Pic
10.25-07-20151+250Complete work of R.R. stone masonary (dry)of B/W with Karb and channel drainNaveen YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
11.25-07-20151+400Complete work of R.R. stone masonry (1:5) of R/WNaveen YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
12.25-07-20152+850Completed work of surface coarseNaveen YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
13.25-07-20152+275R.R.stone masonry (1:5) work in progress of R/W (slope stabilization)Naveen YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
14.25-07-20152+275R.R. stone masonary physical work in progress of R/W(slope stabilization)Naveen YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
15.25-07-20151+850Completed work of surface coarsesNaveen YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
16.22-07-20152(0-2)Construction of r/w at km 3 in ukhimath masuna motor road.Anurag DevJEUDRP R&B Guptkashi See Pic
17.03-05-20150.375SdbcworkS C TyagiEEDEA WB Guptkashi See Pic
18.02-05-20152.025SdbcworkS C TyagiEEDEA WB Guptkashi See Pic
19.12-04-20152.300BMR S RajputREDSC1 R&B WB Rudraprayag See Pic
20.01-11-2014Ch 1.125Retaining Wall completeManoj BishtMEEPIU UDRP R&B See Pic