Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Tala Sari motor road Work Completed
Project: UDRP-RB UID: 2545 Sanction Cost: 143.25  lakh Length: 4.000 KM.
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 66        Package Name:  UDRP/PWD/03/40/RD/056        Tender Date: 24-12-2014        Current Status: Agreement signed        Achieved on Date: 02-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/40/RD/056      Contractor Name: R. B. Group Developers & Builders
Start Date:  09-09-2015      Intended Completion Date:  28-02-2017      Original End Date:  08-12-2016
Total Bond Cost: 32989287.78 (329.89 lakh)        Variation Cost: 1571927.14 (15.72 lakh)    Hence Total Bond Cost is   34561214.92 (345.61 lakh) 
Sub Project Cost: 181.97  lakh        Variation Cost of Sub Project: 5266163.55  (52.66 lakh)       Total Sub Project Cost:   234.63 lakh
LD Analysis for Milestone1: calculated LD is Rs 758770 for 46 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence4.60 KM13.9201-11-201530-04-20164.60 KM4.60 KM9.9413.92
2.R/Wall, B/ Wall Type Protection works430.00 m20.6601-11-201531-03-2016430.00 m430.00 m14.7620.66
3.G-21.20 KM6.3701-03-201631-03-20161.20 KM1.20 KM4.556.37
4.PC/CC i/c Prime Coat, Tack Coat4.60 KM48.0015-04-201615-06-20164.60 KM4.60 KM34.2848.00
5.Cause Way2.00 No2.8201-03-201630-04-20162.00 No2.00 No2.012.82
6.Culverts/Scupper 5.00 No16.9501-03-201630-06-20165.00 No5.00 No12.1116.95
7.longitudinal Drain4500.00 m7.9601-03-201630-05-20164500.00 m4500.00 m5.697.96
8.Crash Barrier1200.00 m11.3801-07-201631-08-20161200.00 m1200.00 m8.1311.38
9.Parapet209.00 No2.7001-08-201630-09-2016209.00 No209.00 No1.932.70
10.Road Furniture41.00 No9.2501-12-201631-12-201641.00 No41.00 No6.619.25
Total Amount: 140.01 100   140.01
Remarks: No Remarks       Work Program Made On: 30-10-2015        Updation of work program on: 28-04-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-January-20167.21  lakh
2.29-February-201614.72  lakh
3.02-May-20169.03  lakh
4.18-May-201625.64  lakh
5.09-June-201646.21  lakh
6.29-June-20169.28  lakh
7.02-August-201613.61  lakh
8.14-September-201622.40  lakh
9.26-October-20164.96  lakh
10.16-February-20176.72  lakh
11.24-May-201733.18  lakh
Total 192.96  lakh
% Payment82.24 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 309   No. of Test Done : 324    No. of Test Passed : 312   No. of Test Failed : 12   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 42
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-12-20164+580E.E. sir and A.E. sir visitAnurag DevJEUDRP R&B Guptkashi See Pic
2.13-12-20161/21R/wall completedAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
3.13-12-20163+625Clearance or earthen boulder from road.Anurag Rawat AEAEUDRP R&B Guptkashi See Pic
4.13-12-20164+200Slip clearnce from road surfaceAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
5.13-12-20161+150Earthen boulder clear from road surfaceAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
6.25-11-20160+550World Bank visitAnurag DevJEUDRP R&B Guptkashi See Pic
7.23-11-20160+300Pc Thickness checking by world bank teamAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
8.04-11-2016KM.2 CH 425PC WORK IS RUNNING ON PATHALI PALDWARI ROADShankar RamEEUDRP R&B Guptkashi See Pic
9.22-10-20161+525Removing undulation instructed by S.E. sir during visitAnurag DevJEUDRP R&B Guptkashi See Pic
10.22-10-20161+425Clearance of surface before p. C.Anurag DevJEUDRP R&B Guptkashi See Pic
11.22-10-20161+425Thickness checked by S. E. SirAnurag DevJEUDRP R&B Guptkashi See Pic
12.22-10-20161+500P. C. + seal coatAnurag DevJEUDRP R&B Guptkashi See Pic
13.22-10-20161+470Prime coatAnurag DevJEUDRP R&B Guptkashi See Pic
14.22-10-20160.025Retaining wall and edge stoneAnurag DevJEUDRP R&B Guptkashi See Pic
15.24-09-20160+100CausewayAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
16.24-09-20160+025Edge stone& R/wAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
17.09-08-20163.000Slip fall on roadAjay YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
18.18-07-20164+200Slip in roadAnurag DevJEUDRP R&B Guptkashi See Pic
19.18-07-20161/21Damaged retaining wallAnurag DevJEUDRP R&B Guptkashi See Pic
20.18-07-20163+625Earthen boulderAnurag Rawat AEAEUDRP R&B Guptkashi See Pic