Tala Sari motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2545 |
Sanction Cost: |
143.25 lakh |
Length:
|
4.000 KM. |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 66
Package Name: 
UDRP/PWD/03/40/RD/056
Tender Date: 24-12-2014
Current Status: Agreement signed
Achieved on Date: 02-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/RD/056
Contractor Name: R. B. Group Developers & Builders
|
Start Date: 09-09-2015
Intended Completion Date: 28-02-2017
Original End Date: 08-12-2016 |
Total Bond Cost: 32989287.78 (329.89 lakh)
Variation Cost: 1571927.14 (15.72 lakh) Hence Total Bond Cost is 34561214.92 (345.61 lakh)
|
Sub Project Cost: 181.97 lakh
Variation Cost of Sub Project: 5266163.55 (52.66 lakh)
Total Sub Project Cost:
234.63 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 758770 for 46 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 4.60 KM | 13.92 | 01-11-2015 | 30-04-2016 | 4.60 KM | 4.60 KM | 9.94 | 13.92 | 2. | R/Wall, B/ Wall Type Protection works | 430.00 m | 20.66 | 01-11-2015 | 31-03-2016 | 430.00 m | 430.00 m | 14.76 | 20.66 | 3. | G-2 | 1.20 KM | 6.37 | 01-03-2016 | 31-03-2016 | 1.20 KM | 1.20 KM | 4.55 | 6.37 | 4. | PC/CC i/c Prime Coat, Tack Coat | 4.60 KM | 48.00 | 15-04-2016 | 15-06-2016 | 4.60 KM | 4.60 KM | 34.28 | 48.00 | 5. | Cause Way | 2.00 No | 2.82 | 01-03-2016 | 30-04-2016 | 2.00 No | 2.00 No | 2.01 | 2.82 | 6. | Culverts/Scupper | 5.00 No | 16.95 | 01-03-2016 | 30-06-2016 | 5.00 No | 5.00 No | 12.11 | 16.95 | 7. | longitudinal Drain | 4500.00 m | 7.96 | 01-03-2016 | 30-05-2016 | 4500.00 m | 4500.00 m | 5.69 | 7.96 | 8. | Crash Barrier | 1200.00 m | 11.38 | 01-07-2016 | 31-08-2016 | 1200.00 m | 1200.00 m | 8.13 | 11.38 | 9. | Parapet | 209.00 No | 2.70 | 01-08-2016 | 30-09-2016 | 209.00 No | 209.00 No | 1.93 | 2.70 | 10. | Road Furniture | 41.00 No | 9.25 | 01-12-2016 | 31-12-2016 | 41.00 No | 41.00 No | 6.61 | 9.25 |
Total Amount: |
140.01 |
|
100 |
140.01 |
|
Remarks:
No Remarks
Work Program Made On:
30-10-2015 } ?>
Updation of work program on:
28-04-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-January-2016 | 7.21 lakh | 2. | 29-February-2016 | 14.72 lakh | 3. | 02-May-2016 | 9.03 lakh | 4. | 18-May-2016 | 25.64 lakh | 5. | 09-June-2016 | 46.21 lakh | 6. | 29-June-2016 | 9.28 lakh | 7. | 02-August-2016 | 13.61 lakh | 8. | 14-September-2016 | 22.40 lakh | 9. | 26-October-2016 | 4.96 lakh | 10. | 16-February-2017 | 6.72 lakh | 11. | 24-May-2017 | 33.18 lakh |
Total |
192.96 lakh |
% Payment | 82.24 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 309 No. of Test Done : 324 No. of Test Passed : 312 No. of Test Failed : 12 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 42 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-12-2016 | 4+580 | E.E. sir and A.E. sir visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
2. | 13-12-2016 | 1/21 | R/wall completed | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
3. | 13-12-2016 | 3+625 | Clearance or earthen boulder from road. | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
4. | 13-12-2016 | 4+200 | Slip clearnce from road surface | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
5. | 13-12-2016 | 1+150 | Earthen boulder clear from road surface | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
6. | 25-11-2016 | 0+550 | World Bank visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
7. | 23-11-2016 | 0+300 | Pc Thickness checking by world bank team | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
8. | 04-11-2016 | KM.2 CH 425 | PC WORK IS RUNNING ON PATHALI PALDWARI ROAD | Shankar Ram | EE | UDRP R&B Guptkashi | See Pic |
9. | 22-10-2016 | 1+525 | Removing undulation instructed by S.E. sir during visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
10. | 22-10-2016 | 1+425 | Clearance of surface before p. C. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
11. | 22-10-2016 | 1+425 | Thickness checked by S. E. Sir | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
12. | 22-10-2016 | 1+500 | P. C. + seal coat | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
13. | 22-10-2016 | 1+470 | Prime coat | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
14. | 22-10-2016 | 0.025 | Retaining wall and edge stone | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
15. | 24-09-2016 | 0+100 | Causeway | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
16. | 24-09-2016 | 0+025 | Edge stone& R/w | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
17. | 09-08-2016 | 3.000 | Slip fall on road | Ajay Yadav | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
18. | 18-07-2016 | 4+200 | Slip in road | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
19. | 18-07-2016 | 1/21 | Damaged retaining wall | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
20. | 18-07-2016 | 3+625 | Earthen boulder | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
|
|