Syuri-Taithi-Pata Motor Road Work Completed
Project: UDRP-RB UID: 2544 Sanction Cost: 400.74  lakh Length: 5.250 KM.
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 63        Package Name:  UDRP/PWD/03/39/RD/027(a)        Tender Date: 20-11-2014        Current Status: Agreement signed        Achieved on Date: 08-03-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/39/RD/027(a)      Contractor Name: Shivom Construction
Start Date:  15-03-2016      Intended Completion Date:  31-10-2018      Original End Date:  14-12-2016
Total Bond Cost: 30771037.95 (307.71 lakh)        Variation Cost: 6661072.91 (66.61 lakh)    Hence Total Bond Cost is   37432110.86 (374.32 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 1477056 for 96 days        LD Analysis for Milestone2: calculated LD is Rs 4231150 for 275 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence5.25 KM33.5821-03-201625-10-20175.25 KM5.25 KM10.6433.58
2.R/Wall, B/ Wall Type Protection works1310.00 m58.0925-03-201610-09-20181526.00 m1526.00 m18.4158.09
3.G-210.50 KM52.1215-02-201710-12-201710.50 KM10.50 KM16.5252.12
4.G-35.25 KM36.2015-04-201718-12-20175.25 KM5.25 KM11.4736.20
5.PC/CC i/c Prime Coat, Tack Coat5.25 KM52.5301-10-201725-06-20185.25 KM5.25 KM16.6552.53
6.Cause Way3.00 No20.7126-10-201625-12-20173.00 No3.00 No6.5620.71
7.Culverts/Scupper 17.00 No30.2615-05-201605-01-201817.00 No17.00 No9.5930.26
8.longitudinal Drain5200.00 m20.9201-02-201725-06-20185200.00 m5200.00 m6.6320.92
9.Crash Barrier0.00 m0.0016-10-201725-02-20180.00 m0.00 m00.00
10.Parapet340.00 No9.7715-07-201830-10-2018340.00 No340.00 No3.19.77
11.Road Furniture68.00 No1.3825-08-201830-10-201868.00 No68.00 No0.441.38
Total Amount: 315.56 100   315.56
Remarks: No Remarks       Work Program Made On: 18-05-2016        Updation of work program on: 12-11-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.20-May-201624.52  lakh
2.30-August-201624.20  lakh
3.21-September-201614.54  lakh
4.15-November-201618.80  lakh
5.28-February-201725.79  lakh
6.18-May-201734.92  lakh
7.03-August-201729.16  lakh
8.21-September-201731.01  lakh
9.15-October-201722.23  lakh
10.28-November-201719.08  lakh
11.24-January-201823.87  lakh
12.13-March-201819.26  lakh
13.24-April-201811.77  lakh
14.16-May-201817.31  lakh
15.06-July-20183.53  lakh
16.19-July-201813.75  lakh
17.30-July-201940.76  lakh
Total 374.5  lakh
% Payment 100.04 %
Advance Amount:  204.23  lakh        Recovered Amount:  204.23  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 350   No. of Test Done : 378    No. of Test Passed : 357   No. of Test Failed : 21   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 91.76
Number of Notice(s) issued: 102

Mobile Pic Upload

Number of Pics Available on Web Repository: 103
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-03-2018S. E. Sir site visitPrashant KumarQCDSC WB SPW Rudraprayag See Pic
2.21-03-20183+300S. E. SIR site visitPrashant KumarQCDSC WB SPW Rudraprayag See Pic
3.24-02-20181+300Site visit EE sir and RE sirVineet KumarJEUDRP R&B Guptkashi See Pic
4.20-11-2017Ch 2.200G3 laying in progressRahul PanwarSurvey EngineerNH Srinagar See Pic
5.17-11-20171+900B/wall work in progressPrashant KumarQCDSC WB SPW Rudraprayag See Pic
6.14-11-2017Ch 1.450C.E. sir site visitRahul PanwarSurvey EngineerNH Srinagar See Pic
7.13-11-20172+900Pc rollingPrashant KumarQCDSC WB SPW Rudraprayag See Pic
8.03-11-20173+650Pc layingPrashant KumarQCDSC WB SPW Rudraprayag See Pic
9.05-07-20172+775Subgrade work progressPrashant KumarQCDSC WB SPW Rudraprayag See Pic
10.08-06-20170+7753m span culvert Slab casting work in progress.Vineet KumarJEUDRP R&B Guptkashi See Pic
11.12-05-20171+100Stone blast collection work.Vineet KumarJEUDRP R&B Guptkashi See Pic
12.03-05-20174+240Thickness checking by chief sir PauriNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
13.17-03-20172+850CE Sir, SE Sir and EE sir site visit.Vineet KumarJEUDRP R&B Guptkashi See Pic
14.17-03-20172+9003.0 m span culvert masonary work in progressVineet KumarJEUDRP R&B Guptkashi See Pic
15.02-03-20172+850Visit of CE sir,SE sir,and EE sir ,CE sir instructions for box culvert.Naresh Kumar RathorAEUDRP R&B Guptkashi See Pic
16.27-02-20171+700Defect cutting in progressVineet KumarJEUDRP R&B Guptkashi See Pic
17.27-02-20170+810Sub grade making.Vineet KumarJEUDRP R&B Guptkashi See Pic
18.09-02-20172+175G2 1st layer material stacking workVineet KumarJEUDRP R&B Guptkashi See Pic
19.09-02-20171+260Hill side cuttingVineet KumarJEUDRP R&B Guptkashi See Pic
20.01-02-20171+250Hp bend devlopement cutting workVineet KumarJEUDRP R&B Guptkashi See Pic