Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Suryaprayag- Mussadung Motor Road Work Completed
Project: UDRP-RB UID: 2543 Sanction Cost: 277.63  lakh Length: 5.500 KM.
District: Rudraprayag Block: Jakholi Constituency: Rudraprayag Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 106        Package Name:  UDRP/PWD/03/RD/095        Tender Date: 04-07-2015        Current Status: Agreement signed        Achieved on Date: 03-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/RD/095      Contractor Name: Vinod Kumar Chauhan
Start Date:  10-10-2015      Intended Completion Date:  06-06-2017      Original End Date:  09-01-2017
Total Bond Cost: 55718387.81 (557.18 lakh)        Variation Cost: 9792705.36 (97.93 lakh)    Hence Total Bond Cost is   65511093.17 (655.11 lakh) 
Sub Project Cost: 216.71  lakh        Variation Cost of Sub Project: 5440958.78  (54.41 lakh)       Total Sub Project Cost:   271.12 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence5.50 KM12.8401-11-201530-04-20165.50 KM5.50 KM5.1312.84
2.R/Wall, B/ Wall Type Protection works304.00 m35.1408-11-201530-04-2016304.00 m304.00 m14.0435.14
3.G-23.00 KM17.1223-01-201615-04-20163.00 KM3.00 KM6.8417.12
4.G-31.50 KM11.0701-02-201625-05-20171.50 KM1.50 KM4.4211.07
5.PC/CC i/c Prime Coat, Tack Coat5.50 KM66.4716-04-201601-06-20175.50 KM5.50 KM26.5666.47
6.Cause Way3.00 No54.5008-12-201515-05-20163.00 No3.00 No21.7854.50
7.Culverts/Scupper 11.00 No29.9418-12-201530-04-201611.00 No11.00 No11.9629.94
8.longitudinal Drain5400.00 m12.2801-03-201630-05-20175400.00 m5400.00 m4.9112.28
9.Crash Barrier400.00 m10.6115-05-201631-05-2016400.00 m400.00 m4.2410.61
10.Road Furniture62.00 No0.2801-06-201630-06-201762.00 No62.00 No0.110.28
Total Amount: 250.25 100   250.25
Remarks: No Remarks       Work Program Made On: 17-11-2015        Updation of work program on: 02-06-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-November-201512.68  lakh
2.26-December-201521.87  lakh
3.28-January-20169.63  lakh
4.26-February-201642.79  lakh
5.28-March-20168.59  lakh
6.02-May-201653.96  lakh
7.18-May-201636.37  lakh
8.07-June-201613.54  lakh
9.28-June-20167.75  lakh
10.18-May-201716.89  lakh
11.22-June-201716.18  lakh
12.27-July-201713.00  lakh
Total 253.25  lakh
% Payment93.41 %
Advance Amount:  4.54  lakh        Recovered Amount:  4.54  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 316   No. of Test Done : 349    No. of Test Passed : 334   No. of Test Failed : 15   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.11
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 212
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-06-20175+235R/W damage and heavy land slide due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
2.08-06-20175+275Parapet base wash-out due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
3.08-06-20175+300Land slide and chauked scupper due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
4.08-06-20175+375Land slides and full patri damage due to heavy run off water heavy rainfal. 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
5.08-06-20175+420R/W damage due to heavy run off water heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
6.08-06-20175+420Road and R/W damage due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
7.08-06-20175+275Land slides and road damage due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
8.08-06-20175+150Land slide due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
9.08-06-20175+000Slip cleaning work due to land slide heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
10.08-06-20174+975Old R/W damage due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
11.08-06-20173+025Slip cleaning work in progressVineet KumarJEUDRP R&B Guptkashi See Pic
12.08-06-20173+025Old r/w demage bottom of causeway due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
13.08-06-20172+100Road opening work in progress due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
14.08-06-20172+100R/W demage old due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
15.08-06-20175+175Land slides road block in rainfall 27-05-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
16.08-06-20175+275Land slides due to rainfall on date 27-05-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
17.17-05-20175+300II layer wire crate fixing work in progressVineet KumarJEUDRP R&B Guptkashi See Pic
18.12-05-20175+175Wire crate fixing work in progress.Vineet KumarJEUDRP R&B Guptkashi See Pic
19.06-05-20175+230Road cleaning workVineet KumarJEUDRP R&B Guptkashi See Pic
20.05-05-20175+140R/W damage dye to heavy rainfall before two days.Vineet KumarJEUDRP R&B Guptkashi See Pic