Suryaprayag- Mussadung Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2543 |
Sanction Cost: |
277.63 lakh |
Length:
|
5.500 KM. |
District: |
Rudraprayag |
Block: |
Jakholi |
Constituency: |
Rudraprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 106
Package Name: 
UDRP/PWD/03/RD/095
Tender Date: 04-07-2015
Current Status: Agreement signed
Achieved on Date: 03-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/RD/095
Contractor Name: Vinod Kumar Chauhan
|
Start Date: 10-10-2015
Intended Completion Date: 06-06-2017
Original End Date: 09-01-2017 |
Total Bond Cost: 55718387.81 (557.18 lakh)
Variation Cost: 9792705.36 (97.93 lakh) Hence Total Bond Cost is 65511093.17 (655.11 lakh)
|
Sub Project Cost: 216.71 lakh
Variation Cost of Sub Project: 5440958.78 (54.41 lakh)
Total Sub Project Cost:
271.12 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 5.50 KM | 12.84 | 01-11-2015 | 30-04-2016 | 5.50 KM | 5.50 KM | 5.13 | 12.84 | 2. | R/Wall, B/ Wall Type Protection works | 304.00 m | 35.14 | 08-11-2015 | 30-04-2016 | 304.00 m | 304.00 m | 14.04 | 35.14 | 3. | G-2 | 3.00 KM | 17.12 | 23-01-2016 | 15-04-2016 | 3.00 KM | 3.00 KM | 6.84 | 17.12 | 4. | G-3 | 1.50 KM | 11.07 | 01-02-2016 | 25-05-2017 | 1.50 KM | 1.50 KM | 4.42 | 11.07 | 5. | PC/CC i/c Prime Coat, Tack Coat | 5.50 KM | 66.47 | 16-04-2016 | 01-06-2017 | 5.50 KM | 5.50 KM | 26.56 | 66.47 | 6. | Cause Way | 3.00 No | 54.50 | 08-12-2015 | 15-05-2016 | 3.00 No | 3.00 No | 21.78 | 54.50 | 7. | Culverts/Scupper | 11.00 No | 29.94 | 18-12-2015 | 30-04-2016 | 11.00 No | 11.00 No | 11.96 | 29.94 | 8. | longitudinal Drain | 5400.00 m | 12.28 | 01-03-2016 | 30-05-2017 | 5400.00 m | 5400.00 m | 4.91 | 12.28 | 9. | Crash Barrier | 400.00 m | 10.61 | 15-05-2016 | 31-05-2016 | 400.00 m | 400.00 m | 4.24 | 10.61 | 10. | Road Furniture | 62.00 No | 0.28 | 01-06-2016 | 30-06-2017 | 62.00 No | 62.00 No | 0.11 | 0.28 |
Total Amount: |
250.25 |
|
100 |
250.25 |
|
Remarks:
No Remarks
Work Program Made On:
17-11-2015 } ?>
Updation of work program on:
02-06-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-November-2015 | 12.68 lakh | 2. | 26-December-2015 | 21.87 lakh | 3. | 28-January-2016 | 9.63 lakh | 4. | 26-February-2016 | 42.79 lakh | 5. | 28-March-2016 | 8.59 lakh | 6. | 02-May-2016 | 53.96 lakh | 7. | 18-May-2016 | 36.37 lakh | 8. | 07-June-2016 | 13.54 lakh | 9. | 28-June-2016 | 7.75 lakh | 10. | 18-May-2017 | 16.89 lakh | 11. | 22-June-2017 | 16.18 lakh | 12. | 27-July-2017 | 13.00 lakh |
Total |
253.25 lakh |
% Payment | 93.41 % |
|
Advance Amount: 4.54 lakh
Recovered Amount: 4.54 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 316 No. of Test Done : 349 No. of Test Passed : 334 No. of Test Failed : 15 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.11 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 212 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-06-2017 | 5+235 | R/W damage and heavy land slide due to heavy rainfall 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
2. | 08-06-2017 | 5+275 | Parapet base wash-out due to heavy rainfall 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
3. | 08-06-2017 | 5+300 | Land slide and chauked scupper due to heavy rainfall 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
4. | 08-06-2017 | 5+375 | Land slides and full patri damage due to heavy run off water heavy rainfal. 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
5. | 08-06-2017 | 5+420 | R/W damage due to heavy run off water heavy rainfall 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
6. | 08-06-2017 | 5+420 | Road and R/W damage due to heavy rainfall 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
7. | 08-06-2017 | 5+275 | Land slides and road damage due to heavy rainfall 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
8. | 08-06-2017 | 5+150 | Land slide due to heavy rainfall 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
9. | 08-06-2017 | 5+000 | Slip cleaning work due to land slide heavy rainfall 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
10. | 08-06-2017 | 4+975 | Old R/W damage due to heavy rainfall 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
11. | 08-06-2017 | 3+025 | Slip cleaning work in progress | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
12. | 08-06-2017 | 3+025 | Old r/w demage bottom of causeway due to heavy rainfall 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
13. | 08-06-2017 | 2+100 | Road opening work in progress due to heavy rainfall 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
14. | 08-06-2017 | 2+100 | R/W demage old due to heavy rainfall 05-06-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
15. | 08-06-2017 | 5+175 | Land slides road block in rainfall 27-05-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
16. | 08-06-2017 | 5+275 | Land slides due to rainfall on date 27-05-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
17. | 17-05-2017 | 5+300 | II layer wire crate fixing work in progress | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
18. | 12-05-2017 | 5+175 | Wire crate fixing work in progress. | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
19. | 06-05-2017 | 5+230 | Road cleaning work | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
20. | 05-05-2017 | 5+140 | R/W damage dye to heavy rainfall before two days. | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
|
|