Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Sirain-Chaura- Bhatwari Motor Road Work Completed
Project: UDRP-RB UID: 2542 Sanction Cost: 250.13  lakh Length: 3.000 KM.
District: Rudraprayag Block: Jakholi Constituency: Rudraprayag Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 69        Package Name:  UDRP/PWD/03/29/RD/059        Tender Date: 24-12-2014        Current Status: Agreement signed        Achieved on Date: 21-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/29/RD/059      Contractor Name: Tushar Builders
Start Date:  28-07-2015      Intended Completion Date:  27-12-2016      Original End Date:  27-10-2016
Total Bond Cost: 20737723.9 (207.38 lakh)        Variation Cost: 4275136.46 (42.75 lakh)    Hence Total Bond Cost is   25012860.36 (250.13 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 207380 for 20 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence3.00 KM9.6010-08-201530-03-20163.00 KM3.00 KM4.639.60
2.R/Wall, B/ Wall Type Protection works830.00 m47.5113-08-201510-04-2016830.00 m830.00 m22.9147.51
3.G-26.60 KM33.4510-09-201530-06-20166.60 KM6.60 KM16.1333.45
4.G-33.30 KM21.8315-05-201630-06-20163.30 KM3.30 KM10.5321.83
5.PC/CC i/c Prime Coat, Tack Coat3.30 KM35.6816-09-201631-10-20163.30 KM3.30 KM17.2135.68
6.Cause Way4.00 No2.7915-05-201603-06-20164.00 No4.00 No1.352.79
7.Culverts/Scupper 11.00 No27.9525-08-201530-06-201611.00 No11.00 No13.4827.95
8.Crash Barrier100.00 m2.2030-05-201630-06-2016100.00 m100.00 m1.062.20
9.Parapet300.00 No8.9830-05-201627-12-2016300.00 No300.00 No4.338.98
10.Road Furniture82.00 No0.5220-09-201627-12-201682.00 No82.00 No0.250.52
11.Other Allied Works & Finishing Work 1.00 Job16.8620-09-201627-12-20161.00 Job1.00 Job8.1316.86
Total Amount: 207.37 100   207.37
Remarks: No Remarks       Work Program Made On: 29-09-2015        Updation of work program on: 19-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.24-September-201532.21  lakh
2.22-December-201513.04  lakh
3.29-February-201626.14  lakh
4.29-June-201635.76  lakh
5.23-August-201635.15  lakh
6.13-September-201627.96  lakh
7.26-October-201626.41  lakh
8.21-January-201720.61  lakh
9.30-June-201721.95  lakh
Total 239.23  lakh
% Payment 95.65 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 246   No. of Test Done : 265    No. of Test Passed : 252   No. of Test Failed : 13   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.82
Number of Notice(s) issued: 62

Mobile Pic Upload

Number of Pics Available on Web Repository: 89
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-01-20171+00Giving instructions about retaining wall by EE sirAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
2.21-12-20160+900Gradation of g2 materials checked by SE sir 7th circleAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
3.21-12-20160+900Wbm g1 ,g2,,g3 and PC thickness checking by SE sir 7th circleAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
4.21-12-20160/180Inspection of cause way by 7th circle S.E. sir & A.e. sir & checking thicknessSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
5.04-12-20163/300Cooliwall in perogreshSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
6.22-10-2016Ch. 1500PC laying & rollingRahul PanwarSurvey EngineerNH Srinagar See Pic
7.22-10-2016Ch. 1590PC Laying and RollingRahul PanwarSurvey EngineerNH Srinagar See Pic
8.20-10-2016Ch. 2200PC rollingRahul PanwarSurvey EngineerNH Srinagar See Pic
9.19-10-2016Ch. 0+850Screening material laying over G3Rahul PanwarSurvey EngineerNH Srinagar See Pic
10.18-10-2016Ch. 0.850Prime coat surfaceRahul PanwarSurvey EngineerNH Srinagar See Pic
11.18-10-2016Ch. 2200Tack coat layingRahul PanwarSurvey EngineerNH Srinagar See Pic
12.14-10-2016Ch. 2250Thickness checkingAmod Kumar ThakurREDSC1 R&B WB Rudraprayag See Pic
13.14-10-2016CH. 2300PC + seal coat surfaceAmod Kumar ThakurREDSC1 R&B WB Rudraprayag See Pic
14.14-10-20162+300Seal coat Temperature checking at layingAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
15.14-10-20162+300Laying of seal coatAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
16.27-08-20161050demage road due to land slideJagat Chand RamolaJEUDRP R&B Guptkashi See Pic
17.17-08-20161180slipJagat Chand RamolaJEUDRP R&B Guptkashi See Pic
18.17-08-20161+00Settlement due to land slideAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
19.20-07-2016980r/wall demage due to heavy slipJagat Chand RamolaJEUDRP R&B Guptkashi See Pic
20.20-07-2016950slip clearance work on progressJagat Chand RamolaJEUDRP R&B Guptkashi See Pic