Silla-Bamangaon MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2541 |
Sanction Cost: |
61.63 lakh |
Length:
|
1.350 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 64
Package Name: 
UDRP/PWD/03/40/RD/054
Tender Date: 24-12-2014
Current Status: Agreement signed
Achieved on Date: 31-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/RD/054
Contractor Name: Digambar Singh Gusain
|
Start Date: 07-08-2015
Intended Completion Date: 10-05-2017
Original End Date: 06-11-2016 |
Total Bond Cost: 28342025.25 (283.42 lakh)
Variation Cost: 496275.16 (4.96 lakh) Hence Total Bond Cost is 28838300.41 (288.38 lakh)
|
Sub Project Cost: 60.89 lakh
Variation Cost of Sub Project: -1016897.83 (-10.17 lakh)
Total Sub Project Cost:
50.72 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 368446 for 26 days
LD Analysis for Milestone2: calculated LD is Rs 2309873 for 163 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.35 KM | 2.14 | 05-10-2015 | 30-03-2016 | 1.35 KM | 1.35 KM | 3.84 | 2.14 | 2. | R/Wall, B/ Wall Type Protection works | 230.00 m | 13.73 | 07-08-2015 | 30-04-2016 | 230.00 m | 230.00 m | 24.61 | 13.73 | 3. | G-2 | 0.20 KM | 0.59 | 07-08-2015 | 30-05-2016 | 0.20 KM | 0.20 KM | 1.06 | 0.59 | 4. | G-3 | 0.10 KM | 0.59 | 15-05-2016 | 30-05-2016 | 0.10 KM | 0.10 KM | 1.06 | 0.59 | 5. | PC/CC i/c Prime Coat, Tack Coat | 1.35 KM | 16.62 | 01-05-2016 | 20-06-2016 | 1.35 KM | 1.35 KM | 29.79 | 16.62 | 6. | Cause Way | 1.00 No | 3.19 | 15-10-2015 | 20-04-2016 | 1.00 No | 1.00 No | 5.71 | 3.19 | 7. | Culverts/Scupper | 2.00 No | 8.53 | 15-10-2015 | 20-04-2016 | 2.00 No | 2.00 No | 15.29 | 8.53 | 8. | longitudinal Drain | 1125.00 m | 3.47 | 15-11-2015 | 11-05-2016 | 1125.00 m | 1125.00 m | 6.22 | 3.47 | 9. | Crash Barrier | 30.00 m | 0.69 | 01-05-2016 | 31-08-2016 | 30.00 m | 30.00 m | 1.24 | 0.69 | 10. | Parapet | 22.00 No | 0.86 | 01-11-2015 | 30-08-2016 | 22.00 No | 22.00 No | 1.54 | 0.86 | 11. | Road Furniture | 13.00 No | 0.22 | 01-05-2016 | 31-08-2016 | 13.00 No | 13.00 No | 0.39 | 0.22 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 5.16 | 20-11-2016 | 20-12-2016 | 1.00 Job | 1.00 Job | 9.25 | 5.16 |
Total Amount: |
55.79 |
|
100 |
55.79 |
|
Remarks:
No Remarks
Work Program Made On:
06-10-2015 } ?>
Updation of work program on:
19-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 24-September-2015 | 2.42 lakh | 2. | 22-December-2015 | 5.78 lakh | 3. | 02-May-2016 | 6.56 lakh | 4. | 15-July-2016 | 15.44 lakh | 5. | 23-August-2016 | 9.91 lakh | 6. | 22-September-2016 | 0.40 lakh | 7. | 04-March-2017 | 1.67 lakh | 8. | 16-June-2017 | 0.91 lakh | 9. | 28-November-2017 | 7.64 lakh |
Total |
50.73 lakh |
% Payment | 100.02 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 3.00 lakh
Balance to be Recovered -3.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 162 No. of Test Done : 173 No. of Test Passed : 161 No. of Test Failed : 12 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 27 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-12-2016 | 3/150 | Collie wall | Suresh Chandra Sharma | JE | UDRP R&B Guptkashi | See Pic |
2. | 19-12-2016 | In leb | A.I.v.test | Suresh Chandra Sharma | JE | UDRP R&B Guptkashi | See Pic |
3. | 19-12-2016 | In leb | A.I.v.test | Suresh Chandra Sharma | JE | UDRP R&B Guptkashi | See Pic |
4. | 17-06-2016 | Ch. 0+350 | Seal Coat Rolling | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
5. | 15-06-2016 | CH. 0+325 | PC Rolling | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
6. | 29-05-2016 | CH. 0+975 | Scupper abutment in progress | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
7. | 09-04-2016 | 0+110 | checking slope of bended r/wall | Jagat Chand Ramola | JE | UDRP R&B Guptkashi | See Pic |
8. | 05-04-2016 | CH. 0.615 | Cause way M30 | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
9. | 03-04-2016 | Ch. 0+110 | R/wall Bended | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
10. | 03-04-2016 | CH.0+610 | Causeway M-30 | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
11. | 07-11-2015 | End Point | Sampling for Water Test | Saroj Kumar | QC | DSC1 R&B WB Rudraprayag | See Pic |
12. | 07-11-2015 | End Point | Ambient noise level monitoring | Saroj Kumar | QC | DSC1 R&B WB Rudraprayag | See Pic |
13. | 07-11-2015 | End Point | Sampling for Soil | Saroj Kumar | QC | DSC1 R&B WB Rudraprayag | See Pic |
14. | 07-11-2015 | End Point | Sampling & Testing for Air | Saroj Kumar | QC | DSC1 R&B WB Rudraprayag | See Pic |
15. | 07-11-2015 | CH-0.400 | Ambient air Quality monitoring | Saroj Kumar | QC | DSC1 R&B WB Rudraprayag | See Pic |
16. | 03-11-2015 | 0+950 | B/w bended | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
17. | 03-11-2015 | CH. 0.010 | B/w bended | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
18. | 03-11-2015 | 1+025 | B/w bended | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
19. | 01-10-2015 | Ch. 0.610 | B/w work in progress | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
20. | 23-09-2015 | CH-1.250 | B/W Bended | Saroj Kumar | QC | DSC1 R&B WB Rudraprayag | See Pic |
|
|