Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Silla-Bamangaon MR Work Completed
Project: UDRP-RB UID: 2541 Sanction Cost: 61.63  lakh Length: 1.350 KM.
District: Rudraprayag Block: August Muni Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 64        Package Name:  UDRP/PWD/03/40/RD/054        Tender Date: 24-12-2014        Current Status: Agreement signed        Achieved on Date: 31-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/40/RD/054      Contractor Name: Digambar Singh Gusain
Start Date:  07-08-2015      Intended Completion Date:  10-05-2017      Original End Date:  06-11-2016
Total Bond Cost: 28342025.25 (283.42 lakh)        Variation Cost: 496275.16 (4.96 lakh)    Hence Total Bond Cost is   28838300.41 (288.38 lakh) 
Sub Project Cost: 60.89  lakh        Variation Cost of Sub Project: -1016897.83  (-10.17 lakh)       Total Sub Project Cost:   50.72 lakh
LD Analysis for Milestone1: calculated LD is Rs 368446 for 26 days        LD Analysis for Milestone2: calculated LD is Rs 2309873 for 163 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.35 KM2.1405-10-201530-03-20161.35 KM1.35 KM3.842.14
2.R/Wall, B/ Wall Type Protection works230.00 m13.7307-08-201530-04-2016230.00 m230.00 m24.6113.73
3.G-20.20 KM0.5907-08-201530-05-20160.20 KM0.20 KM1.060.59
4.G-30.10 KM0.5915-05-201630-05-20160.10 KM0.10 KM1.060.59
5.PC/CC i/c Prime Coat, Tack Coat1.35 KM16.6201-05-201620-06-20161.35 KM1.35 KM29.7916.62
6.Cause Way1.00 No3.1915-10-201520-04-20161.00 No1.00 No5.713.19
7.Culverts/Scupper 2.00 No8.5315-10-201520-04-20162.00 No2.00 No15.298.53
8.longitudinal Drain1125.00 m3.4715-11-201511-05-20161125.00 m1125.00 m6.223.47
9.Crash Barrier30.00 m0.6901-05-201631-08-201630.00 m30.00 m1.240.69
10.Parapet22.00 No0.8601-11-201530-08-201622.00 No22.00 No1.540.86
11.Road Furniture13.00 No0.2201-05-201631-08-201613.00 No13.00 No0.390.22
12.Other Allied Works & Finishing Work 1.00 Job5.1620-11-201620-12-20161.00 Job1.00 Job9.255.16
Total Amount: 55.79 100   55.79
Remarks: No Remarks       Work Program Made On: 06-10-2015        Updation of work program on: 19-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.24-September-20152.42  lakh
2.22-December-20155.78  lakh
3.02-May-20166.56  lakh
4.15-July-201615.44  lakh
5.23-August-20169.91  lakh
6.22-September-20160.40  lakh
7.04-March-20171.67  lakh
8.16-June-20170.91  lakh
9.28-November-20177.64  lakh
Total 50.73  lakh
% Payment100.02 %
Advance Amount:  0.00  lakh        Recovered Amount:  3.00  lakh        Balance to be Recovered  -3.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 162   No. of Test Done : 173    No. of Test Passed : 161   No. of Test Failed : 12   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 27
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.24-12-20163/150Collie wallSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
2.19-12-2016In lebA.I.v.testSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
3.19-12-2016In lebA.I.v.testSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
4.17-06-2016Ch. 0+350Seal Coat RollingRahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
5.15-06-2016CH. 0+325PC RollingRahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
6.29-05-2016CH. 0+975Scupper abutment in progressRahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
7.09-04-20160+110checking slope of bended r/wallJagat Chand RamolaJEUDRP R&B Guptkashi See Pic
8.05-04-2016CH. 0.615Cause way M30Rahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
9.03-04-2016Ch. 0+110R/wall BendedRahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
10.03-04-2016CH.0+610Causeway M-30Rahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
11.07-11-2015End PointSampling for Water TestSaroj KumarQCDSC1 R&B WB Rudraprayag See Pic
12.07-11-2015End PointAmbient noise level monitoringSaroj KumarQCDSC1 R&B WB Rudraprayag See Pic
13.07-11-2015End PointSampling for SoilSaroj KumarQCDSC1 R&B WB Rudraprayag See Pic
14.07-11-2015End PointSampling & Testing for AirSaroj KumarQCDSC1 R&B WB Rudraprayag See Pic
15.07-11-2015CH-0.400Ambient air Quality monitoringSaroj KumarQCDSC1 R&B WB Rudraprayag See Pic
16.03-11-20150+950B/w bendedAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
17.03-11-2015CH. 0.010B/w bendedRahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
18.03-11-20151+025B/w bendedRahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
19.01-10-2015Ch. 0.610B/w work in progressRahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
20.23-09-2015CH-1.250B/W BendedSaroj KumarQCDSC1 R&B WB Rudraprayag See Pic