Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Rudraprayag- gandhar- Garhidhar-dasjula MR Work Completed
Project: UDRP-RB UID: 2540 Sanction Cost: 612.37  lakh Length: 19.500 KM.
District: Rudraprayag Block: August Muni Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 42        Package Name:  UDRP/PWD/03/39/RD/042        Tender Date: 21-10-2014        Current Status: Agreement signed        Achieved on Date: 21-04-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/39/RD/042      Contractor Name: Crystal Infrastructure
Start Date:  28-04-2015      Intended Completion Date:  30-11-2018      Original End Date:  27-07-2016
Total Bond Cost: 44954521.83 (449.55 lakh)        Variation Cost: 11761912.88 (117.62 lakh)    Hence Total Bond Cost is   56716434.71 (567.16 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 1910545 for 85 days        LD Analysis for Milestone2: calculated LD is Rs 2719717 for 121 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence4.23 KM71.8020-09-201515-06-20164.23 KM4.23 KM12.6671.80
2.R/Wall, B/ Wall Type Protection works5850.00 m80.2801-08-201515-08-20165850.00 m5850.00 m14.1680.28
3.GSB/RBI/G-17.00 KM42.9801-08-201528-02-20177.00 KM7.00 KM7.5842.98
4.G-27.00 KM39.5701-09-201530-09-20177.00 KM7.00 KM6.9839.57
5.G-37.50 KM58.2715-09-201523-11-20177.00 KM7.00 KM10.2758.27
6.PC/CC i/c Prime Coat, Tack Coat12.50 KM147.2815-03-201630-11-201712.50 KM12.50 KM25.97147.28
7.Cause Way7.00 No14.8215-11-201630-11-20185.00 No5.00 No2.6114.82
8.Culverts/Scupper 8.00 No19.1501-10-201510-10-20178.00 No8.00 No3.3819.15
9.longitudinal Drain12500.00 m32.5301-10-201505-10-201812500.00 m12500.00 m5.7432.53
10.Crash Barrier910.00 m23.7705-09-201805-11-2018910.00 m910.00 m4.1923.77
11.Parapet568.00 No16.4901-01-201715-09-2018568.00 No568.00 No2.9116.49
12.Road Furniture62.00 No4.0501-10-201826-11-201862.00 No62.00 No0.724.05
13.Other Allied Works & Finishing Work 1.00 Job16.1615-11-201730-11-20181.00 Job1.00 Job2.8516.16
Total Amount: 567.15 100   567.15
Remarks: no remark       Work Program Made On: 06-10-2015        Updation of work program on: 12-11-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.13-June-201519.25  lakh
2.13-August-201511.40  lakh
3.10-September-201513.84  lakh
4.10-October-201512.84  lakh
5.07-November-201516.35  lakh
6.11-December-201510.62  lakh
7.30-December-20158.73  lakh
8.28-January-201611.31  lakh
9.17-March-201617.51  lakh
10.20-May-201639.98  lakh
11.06-June-201620.79  lakh
12.28-June-201644.28  lakh
13.11-September-20169.49  lakh
14.07-October-201614.20  lakh
15.28-February-201729.16  lakh
16.18-April-201723.92  lakh
17.24-June-201721.98  lakh
18.04-August-201714.45  lakh
19.23-September-201718.89  lakh
20.18-October-201718.14  lakh
21.09-November-201721.47  lakh
22.15-December-201720.13  lakh
23.06-April-201814.90  lakh
24.30-August-201820.78  lakh
25.24-December-201827.21  lakh
26.31-May-201937.87  lakh
Total 519.49  lakh
% Payment 91.6 %
Advance Amount:  85.69  lakh        Recovered Amount:  85.69  lakh        Balance to be Recovered  -0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 643   No. of Test Done : 693    No. of Test Passed : 628   No. of Test Failed : 65   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.45
Number of Notice(s) issued: 136

Mobile Pic Upload

Number of Pics Available on Web Repository: 174
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-02-2019Starting pointJoint inspection with AE GuptkashiLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
2.16-03-201828+000Se sir visitPrashant KumarQCDSC WB SPW Rudraprayag See Pic
3.13-03-201825+700Se. Sir and A. e. Mam site visitPrashant KumarQCDSC WB SPW Rudraprayag See Pic
4.04-02-201827+900Gram sabha held for grievance discussion at gadhidhar dated 04/02/2018Prashant KumarQCDSC WB SPW Rudraprayag See Pic
5.21-11-2017Wbm g3 water sprinklingPrashant KumarQCDSC WB SPW Rudraprayag See Pic
6.16-11-201727+200Wbm g3 gradation test, results found by okPrashant KumarQCDSC WB SPW Rudraprayag See Pic
7.04-11-201727+800Pc layingPrashant KumarQCDSC WB SPW Rudraprayag See Pic
8.26-10-201723+750Pc workPrashant KumarQCDSC WB SPW Rudraprayag See Pic
9.06-10-201727+900R. E. Sir instructions to contractor for subgrade preparation, rectification of undulation and subgrade preparations, road wirth rectificationPrashant KumarQCDSC WB SPW Rudraprayag See Pic
10.20-09-20170+000S. E. Sir visitPrashant KumarQCDSC WB SPW Rudraprayag See Pic
11.22-08-201714+300Aam sabha along with R.E. pradhan, chopda, J. E.Prashant KumarQCDSC WB SPW Rudraprayag See Pic
12.01-08-201723+500SrmdPrashant KumarQCDSC WB SPW Rudraprayag See Pic
13.11-05-201724+400Stone collect for WBMNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
14.14-03-201725+900Hill side cuttingParvindar SinghJEUDRP R&B Guptkashi See Pic
15.14-03-201713+350Construction of parapetParvindar SinghJEUDRP R&B Guptkashi See Pic
16.16-02-2017Chainage 24+300Hill side cuttingParvindar SinghJEUDRP R&B Guptkashi See Pic
17.13-02-201717+800 site lab AIV testAIV test of G1,G2Naresh Kumar RathorAEUDRP R&B Guptkashi See Pic
18.13-02-201716+800Construction of parapetParvindar SinghJEUDRP R&B Guptkashi See Pic
19.13-02-2017At site labAIV testParvindar SinghJEUDRP R&B Guptkashi See Pic
20.09-02-201724+060Hill side cuttingParvindar SinghJEUDRP R&B Guptkashi See Pic