Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Pathali-Paldwari motor road Work Completed
Project: UDRP-RB UID: 2537 Sanction Cost: 210.78  lakh Length: 2.600 KM.
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 66        Package Name:  UDRP/PWD/03/40/RD/056        Tender Date: 24-12-2014        Current Status: Agreement signed        Achieved on Date: 02-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/40/RD/056      Contractor Name: R. B. Group Developers & Builders
Start Date:  09-09-2015      Intended Completion Date:  28-02-2017      Original End Date:  08-12-2016
Total Bond Cost: 32989287.78 (329.89 lakh)        Variation Cost: 1571927.14 (15.72 lakh)    Hence Total Bond Cost is   34561214.92 (345.61 lakh) 
Sub Project Cost: 188.97  lakh        Variation Cost of Sub Project: -3694236.41  (-36.94 lakh)       Total Sub Project Cost:   152.03 lakh
LD Analysis for Milestone1: calculated LD is Rs 758770 for 46 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.60 KM17.3005-10-201530-05-20161.60 KM1.60 KM10.217.30
2.R/Wall, B/ Wall Type Protection works710.00 m47.7501-10-201515-09-2016710.00 m710.00 m28.1547.75
3.G-23.20 KM17.0101-12-201515-09-20163.20 KM3.20 KM10.0317.01
4.G-31.60 KM8.5015-05-201610-10-20161.60 KM1.60 KM5.018.50
5.PC/CC i/c Prime Coat, Tack Coat1.60 KM31.1410-10-201625-10-20161.60 KM1.60 KM18.3631.14
6.Cause Way2.00 No2.8301-03-201615-04-20162.00 No2.00 No1.672.83
7.Culverts/Scupper 4.00 No21.9201-12-201531-10-20164.00 No4.00 No12.9321.92
8.longitudinal Drain1600.00 m7.9615-05-201631-10-20161600.00 m1600.00 m4.697.96
9.Crash Barrier300.00 m1.3701-07-201630-09-2016300.00 m300.00 m0.811.37
10.Parapet205.00 No12.4520-09-201630-10-2016205.00 No205.00 No7.3412.45
11.Road Furniture27.00 No1.3715-11-201608-12-201627.00 No27.00 No0.811.37
Total Amount: 169.6 100   169.6
Remarks: No Remarks       Work Program Made On: 30-10-2015        Updation of work program on: 19-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-20158.46  lakh
2.28-January-201613.69  lakh
3.29-February-201616.72  lakh
4.02-May-20164.04  lakh
5.18-May-20160.24  lakh
6.09-June-20160.05  lakh
7.29-June-201625.06  lakh
8.02-August-201611.27  lakh
9.14-September-201629.25  lakh
10.26-October-201628.37  lakh
11.16-February-201710.17  lakh
12.24-May-20173.53  lakh
Total 150.85  lakh
% Payment99.22 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 309   No. of Test Done : 324    No. of Test Passed : 312   No. of Test Failed : 12   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 64
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-12-20161+475R/wall completedAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
2.13-12-20161+550Completed r/wallAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
3.13-12-20162+525Slip clearnce from roadAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
4.13-12-20162+120Old r/wall damaged in rainy season constructed new r/wallAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
5.25-11-20160+00World Bank visitAnurag DevJEUDRP R&B Guptkashi See Pic
6.25-11-20160+00World Bank visitAnurag DevJEUDRP R&B Guptkashi See Pic
7.23-11-20160+050Road width cheking by world bank teamAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
8.23-11-20160+070Pc Thickness checking by world bank teamAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
9.19-11-20162+600Rectangular Sign board quality good.Anurag DevJEUDRP R&B Guptkashi See Pic
10.22-10-20160+800Prime coatAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
11.22-10-20160+500Pc rollingAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
12.18-10-20161+550Pc rolling workAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
13.18-10-20161+475Primcoat ss1Ashish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
14.18-10-20161+450Rolling over seal coatAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
15.18-10-20161.500Seal coat thick checkAmod Kumar ThakurREDSC1 R&B WB Rudraprayag See Pic
16.18-10-20161+470Rolling seal coatAmod Kumar ThakurREDSC1 R&B WB Rudraprayag See Pic
17.18-10-20160+975MexwalAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
18.15-10-20161+460Solder work in progressAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
19.15-10-20161.450Parapet starterAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
20.07-10-20161+475Top coat & RollingAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic