Pathali-Paldwari motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2537 |
Sanction Cost: |
210.78 lakh |
Length:
|
2.600 KM. |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 66
Package Name: 
UDRP/PWD/03/40/RD/056
Tender Date: 24-12-2014
Current Status: Agreement signed
Achieved on Date: 02-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/RD/056
Contractor Name: R. B. Group Developers & Builders
|
Start Date: 09-09-2015
Intended Completion Date: 28-02-2017
Original End Date: 08-12-2016 |
Total Bond Cost: 32989287.78 (329.89 lakh)
Variation Cost: 1571927.14 (15.72 lakh) Hence Total Bond Cost is 34561214.92 (345.61 lakh)
|
Sub Project Cost: 188.97 lakh
Variation Cost of Sub Project: -3694236.41 (-36.94 lakh)
Total Sub Project Cost:
152.03 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 758770 for 46 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.60 KM | 17.30 | 05-10-2015 | 30-05-2016 | 1.60 KM | 1.60 KM | 10.2 | 17.30 | 2. | R/Wall, B/ Wall Type Protection works | 710.00 m | 47.75 | 01-10-2015 | 15-09-2016 | 710.00 m | 710.00 m | 28.15 | 47.75 | 3. | G-2 | 3.20 KM | 17.01 | 01-12-2015 | 15-09-2016 | 3.20 KM | 3.20 KM | 10.03 | 17.01 | 4. | G-3 | 1.60 KM | 8.50 | 15-05-2016 | 10-10-2016 | 1.60 KM | 1.60 KM | 5.01 | 8.50 | 5. | PC/CC i/c Prime Coat, Tack Coat | 1.60 KM | 31.14 | 10-10-2016 | 25-10-2016 | 1.60 KM | 1.60 KM | 18.36 | 31.14 | 6. | Cause Way | 2.00 No | 2.83 | 01-03-2016 | 15-04-2016 | 2.00 No | 2.00 No | 1.67 | 2.83 | 7. | Culverts/Scupper | 4.00 No | 21.92 | 01-12-2015 | 31-10-2016 | 4.00 No | 4.00 No | 12.93 | 21.92 | 8. | longitudinal Drain | 1600.00 m | 7.96 | 15-05-2016 | 31-10-2016 | 1600.00 m | 1600.00 m | 4.69 | 7.96 | 9. | Crash Barrier | 300.00 m | 1.37 | 01-07-2016 | 30-09-2016 | 300.00 m | 300.00 m | 0.81 | 1.37 | 10. | Parapet | 205.00 No | 12.45 | 20-09-2016 | 30-10-2016 | 205.00 No | 205.00 No | 7.34 | 12.45 | 11. | Road Furniture | 27.00 No | 1.37 | 15-11-2016 | 08-12-2016 | 27.00 No | 27.00 No | 0.81 | 1.37 |
Total Amount: |
169.6 |
|
100 |
169.6 |
|
Remarks:
No Remarks
Work Program Made On:
30-10-2015 } ?>
Updation of work program on:
19-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2015 | 8.46 lakh | 2. | 28-January-2016 | 13.69 lakh | 3. | 29-February-2016 | 16.72 lakh | 4. | 02-May-2016 | 4.04 lakh | 5. | 18-May-2016 | 0.24 lakh | 6. | 09-June-2016 | 0.05 lakh | 7. | 29-June-2016 | 25.06 lakh | 8. | 02-August-2016 | 11.27 lakh | 9. | 14-September-2016 | 29.25 lakh | 10. | 26-October-2016 | 28.37 lakh | 11. | 16-February-2017 | 10.17 lakh | 12. | 24-May-2017 | 3.53 lakh |
Total |
150.85 lakh |
% Payment | 99.22 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 309 No. of Test Done : 324 No. of Test Passed : 312 No. of Test Failed : 12 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 64 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 13-12-2016 | 1+475 | R/wall completed | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
2. | 13-12-2016 | 1+550 | Completed r/wall | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
3. | 13-12-2016 | 2+525 | Slip clearnce from road | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
4. | 13-12-2016 | 2+120 | Old r/wall damaged in rainy season constructed new r/wall | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
5. | 25-11-2016 | 0+00 | World Bank visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
6. | 25-11-2016 | 0+00 | World Bank visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
7. | 23-11-2016 | 0+050 | Road width cheking by world bank team | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
8. | 23-11-2016 | 0+070 | Pc Thickness checking by world bank team | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
9. | 19-11-2016 | 2+600 | Rectangular Sign board quality good. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
10. | 22-10-2016 | 0+800 | Prime coat | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
11. | 22-10-2016 | 0+500 | Pc rolling | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
12. | 18-10-2016 | 1+550 | Pc rolling work | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
13. | 18-10-2016 | 1+475 | Primcoat ss1 | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
14. | 18-10-2016 | 1+450 | Rolling over seal coat | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
15. | 18-10-2016 | 1.500 | Seal coat thick check | Amod Kumar Thakur | RE | DSC1 R&B WB Rudraprayag | See Pic |
16. | 18-10-2016 | 1+470 | Rolling seal coat | Amod Kumar Thakur | RE | DSC1 R&B WB Rudraprayag | See Pic |
17. | 18-10-2016 | 0+975 | Mexwal | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
18. | 15-10-2016 | 1+460 | Solder work in progress | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
19. | 15-10-2016 | 1.450 | Parapet starter | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
20. | 07-10-2016 | 1+475 | Top coat & Rolling | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
|
|