Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kusumgarh-sursal motor road Work Completed
Project: UDRP-RB UID: 2532 Sanction Cost: 209.12  lakh Length: 3.000 KM.
District: Rudraprayag Block: August Muni Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 65        Package Name:  UDRP/PWD/03/40/RD/055        Tender Date: 24-12-2014        Current Status: Agreement signed        Achieved on Date: 01-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/40/RD/055      Contractor Name: Bhatt & Thapliyal Engineering
Start Date:  08-07-2015      Intended Completion Date:  30-05-2017      Original End Date:  07-10-2016
Total Bond Cost: 43975819.08 (439.76 lakh)        Variation Cost: 5398141.22 (53.98 lakh)    Hence Total Bond Cost is   49373960.3 (493.74 lakh) 
Sub Project Cost: 180.71  lakh        Variation Cost of Sub Project: 4954438.64  (49.54 lakh)       Total Sub Project Cost:   230.25 lakh
LD Analysis for Milestone1: calculated LD is Rs 549700 for 25 days        LD Analysis for Milestone2: calculated LD is Rs 637652 for 29 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.85 KM9.9820-08-201520-03-20162.85 KM2.85 KM4.439.98
2.R/Wall, B/ Wall Type Protection works220.00 m23.2015-09-201530-03-2016220.00 m220.00 m10.2923.20
3.G-25.70 KM34.4515-01-201605-10-20165.70 KM5.70 KM15.2834.45
4.G-32.85 KM34.4501-12-201628-02-20172.85 KM2.85 KM15.2834.45
5.PC/CC i/c Prime Coat, Tack Coat2.85 KM37.5301-04-201715-05-20172.85 KM2.85 KM16.6437.53
6.Cause Way1.00 No2.8615-05-201630-08-20161.00 No1.00 No1.272.86
7.Culverts/Scupper 12.00 No25.1820-10-201530-04-201612.00 No12.00 No11.1725.18
8.longitudinal Drain2850.00 m12.7015-05-201631-01-20172850.00 m2850.00 m5.6312.70
9.Crash Barrier100.00 m19.3930-09-201630-10-2016100.00 m100.00 m8.619.39
10.Road Furniture55.00 No1.6301-05-201730-05-201755.00 No55.00 No0.721.63
11.Other Allied Works & Finishing Work 1.00 Job24.1201-05-201730-05-20171.00 Job1.00 Job10.724.12
Total Amount: 225.49 100   225.49
Remarks: No Remarks       Work Program Made On: 28-09-2015        Updation of work program on: 19-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-20159.38  lakh
2.26-February-201634.69  lakh
3.21-March-201617.55  lakh
4.23-August-20168.89  lakh
5.03-October-201625.04  lakh
6.09-March-201717.08  lakh
7.04-August-2017116.40  lakh
Total 229.03  lakh
% Payment99.47 %
Advance Amount:  27.54  lakh        Recovered Amount:  27.54  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 287   No. of Test Done : 298    No. of Test Passed : 284   No. of Test Failed : 14   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 60
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-05-20172+810Superelvation checked at HP bend found 10%Anurag Rawat AEAEUDRP R&B Guptkashi See Pic
2.24-04-2017Ch. 1.350PC laying in progressRahul PanwarSurvey EngineerNH Srinagar See Pic
3.14-04-20172+850PC surface checking by EE sir at kusumgarh sursal motar roadAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
4.07-01-2017O+080Thickness cheking of g3 by CE sir and EE sirAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
5.07-01-20170+080C.E. and E.E. sir visitAnurag DevJEUDRP R&B Guptkashi See Pic
6.28-09-2016Ch. 1+025Casting of 2m span culvertRahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
7.28-09-2016CH. 1+025Reinforcement in 2 m span culvertRahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
8.27-09-2016ChzB /wall bendedRahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
9.19-09-2016Ch. 0+125Casting of 2 m span culvertRahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
10.19-09-2016CH. 0+125Reinforcement of 2m span culvertRahul PanwarSite SupervisorDSC1 R&B WB Rudraprayag See Pic
11.24-08-20161+600Construction of damaged r/wallAnurag DevJEUDRP R&B Guptkashi See Pic
12.03-08-20161+600Construction of r/wall in damaged area..Anurag DevJEUDRP R&B Guptkashi See Pic
13.20-07-20162+250Land slide E&BAnurag DevJEUDRP R&B Guptkashi See Pic
14.20-07-20162.400Damaged r/wallAnurag DevJEUDRP R&B Guptkashi See Pic
15.20-07-20162+275Damaged R/wallAnurag DevJEUDRP R&B Guptkashi See Pic
16.20-07-20162.000Land slideAnurag DevJEUDRP R&B Guptkashi See Pic
17.20-07-20162+275srmd:Collapse r/wallAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
18.20-07-20162+00Earthen boulderAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
19.20-07-20161+600srmd:Collpase r/wall due to heavy rain fallAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
20.15-07-20161+625Road block due to damaged r/w.Anurag DevJEUDRP R&B Guptkashi See Pic