Kusumgarh-sursal motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2532 |
Sanction Cost: |
209.12 lakh |
Length:
|
3.000 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 65
Package Name: 
UDRP/PWD/03/40/RD/055
Tender Date: 24-12-2014
Current Status: Agreement signed
Achieved on Date: 01-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/RD/055
Contractor Name: Bhatt & Thapliyal Engineering
|
Start Date: 08-07-2015
Intended Completion Date: 30-05-2017
Original End Date: 07-10-2016 |
Total Bond Cost: 43975819.08 (439.76 lakh)
Variation Cost: 5398141.22 (53.98 lakh) Hence Total Bond Cost is 49373960.3 (493.74 lakh)
|
Sub Project Cost: 180.71 lakh
Variation Cost of Sub Project: 4954438.64 (49.54 lakh)
Total Sub Project Cost:
230.25 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 549700 for 25 days
LD Analysis for Milestone2: calculated LD is Rs 637652 for 29 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.85 KM | 9.98 | 20-08-2015 | 20-03-2016 | 2.85 KM | 2.85 KM | 4.43 | 9.98 | 2. | R/Wall, B/ Wall Type Protection works | 220.00 m | 23.20 | 15-09-2015 | 30-03-2016 | 220.00 m | 220.00 m | 10.29 | 23.20 | 3. | G-2 | 5.70 KM | 34.45 | 15-01-2016 | 05-10-2016 | 5.70 KM | 5.70 KM | 15.28 | 34.45 | 4. | G-3 | 2.85 KM | 34.45 | 01-12-2016 | 28-02-2017 | 2.85 KM | 2.85 KM | 15.28 | 34.45 | 5. | PC/CC i/c Prime Coat, Tack Coat | 2.85 KM | 37.53 | 01-04-2017 | 15-05-2017 | 2.85 KM | 2.85 KM | 16.64 | 37.53 | 6. | Cause Way | 1.00 No | 2.86 | 15-05-2016 | 30-08-2016 | 1.00 No | 1.00 No | 1.27 | 2.86 | 7. | Culverts/Scupper | 12.00 No | 25.18 | 20-10-2015 | 30-04-2016 | 12.00 No | 12.00 No | 11.17 | 25.18 | 8. | longitudinal Drain | 2850.00 m | 12.70 | 15-05-2016 | 31-01-2017 | 2850.00 m | 2850.00 m | 5.63 | 12.70 | 9. | Crash Barrier | 100.00 m | 19.39 | 30-09-2016 | 30-10-2016 | 100.00 m | 100.00 m | 8.6 | 19.39 | 10. | Road Furniture | 55.00 No | 1.63 | 01-05-2017 | 30-05-2017 | 55.00 No | 55.00 No | 0.72 | 1.63 | 11. | Other Allied Works & Finishing Work | 1.00 Job | 24.12 | 01-05-2017 | 30-05-2017 | 1.00 Job | 1.00 Job | 10.7 | 24.12 |
Total Amount: |
225.49 |
|
100 |
225.49 |
|
Remarks:
No Remarks
Work Program Made On:
28-09-2015 } ?>
Updation of work program on:
19-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2015 | 9.38 lakh | 2. | 26-February-2016 | 34.69 lakh | 3. | 21-March-2016 | 17.55 lakh | 4. | 23-August-2016 | 8.89 lakh | 5. | 03-October-2016 | 25.04 lakh | 6. | 09-March-2017 | 17.08 lakh | 7. | 04-August-2017 | 116.40 lakh |
Total |
229.03 lakh |
% Payment | 99.47 % |
|
Advance Amount: 27.54 lakh
Recovered Amount: 27.54 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 287 No. of Test Done : 298 No. of Test Passed : 284 No. of Test Failed : 14 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 60 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-05-2017 | 2+810 | Superelvation checked at HP bend found 10% | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
2. | 24-04-2017 | Ch. 1.350 | PC laying in progress | Rahul Panwar | Survey Engineer | NH Srinagar | See Pic |
3. | 14-04-2017 | 2+850 | PC surface checking by EE sir at kusumgarh sursal motar road | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
4. | 07-01-2017 | O+080 | Thickness cheking of g3 by CE sir and EE sir | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
5. | 07-01-2017 | 0+080 | C.E. and E.E. sir visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
6. | 28-09-2016 | Ch. 1+025 | Casting of 2m span culvert | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
7. | 28-09-2016 | CH. 1+025 | Reinforcement in 2 m span culvert | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
8. | 27-09-2016 | Chz | B /wall bended | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
9. | 19-09-2016 | Ch. 0+125 | Casting of 2 m span culvert | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
10. | 19-09-2016 | CH. 0+125 | Reinforcement of 2m span culvert | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
11. | 24-08-2016 | 1+600 | Construction of damaged r/wall | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
12. | 03-08-2016 | 1+600 | Construction of r/wall in damaged area.. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
13. | 20-07-2016 | 2+250 | Land slide E&B | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
14. | 20-07-2016 | 2.400 | Damaged r/wall | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
15. | 20-07-2016 | 2+275 | Damaged R/wall | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
16. | 20-07-2016 | 2.000 | Land slide | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
17. | 20-07-2016 | 2+275 | srmd:Collapse r/wall | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
18. | 20-07-2016 | 2+00 | Earthen boulder | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
19. | 20-07-2016 | 1+600 | srmd:Collpase r/wall due to heavy rain fall | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
20. | 15-07-2016 | 1+625 | Road block due to damaged r/w. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
|
|