Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kotkhal jagtoli MR Work Completed
Project: UDRP-RB UID: 2531 Sanction Cost: 538.57  lakh Length: 7.000 KM.
District: Rudraprayag Block: August Muni Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 43        Package Name:  UDRP/PWD/03/39/RD/043        Tender Date: 16-06-2014        Current Status: Agreement signed        Achieved on Date: 25-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/39/RD/043      Contractor Name: Sahab Singh Rawat & Brothers
Start Date:  01-12-2014      Intended Completion Date:  03-05-2017      Original End Date:  29-02-2016
Total Bond Cost: 45857772.73 (458.58 lakh)        Variation Cost: 10679547.72 (106.8 lakh)    Hence Total Bond Cost is   56537320.45 (565.37 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 596154 for 26 days        LD Analysis for Milestone2: calculated LD is Rs 412722 for 18 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.87 KM10.1329-12-201530-04-20160.87 KM0.87 KM1.8510.13
2.R/Wall, B/ Wall Type Protection works663.00 m96.8825-08-201515-04-2016663.00 m663.00 m17.6696.88
3.GSB/RBI/G-16.91 KM80.7520-08-201531-12-20166.91 KM6.91 KM14.7280.75
4.G-26.91 KM54.5001-09-201531-01-20176.91 KM6.91 KM9.9354.50
5.G-36.91 KM54.9501-09-201528-02-20176.91 KM6.91 KM10.0254.95
6.PC/CC i/c Prime Coat, Tack Coat6.91 KM121.4202-02-201615-04-20176.91 KM6.91 KM22.13121.42
7.Cause Way3.00 No2.8615-05-201631-07-20163.00 No3.00 No0.522.86
8.Culverts/Scupper 24.00 No53.6015-08-201530-05-201624.00 No24.00 No9.7753.60
9.longitudinal Drain7250.00 m27.0315-08-201531-01-20177250.00 m7250.00 m4.9327.03
10.Parapet140.00 No4.2101-01-201731-01-2017140.00 No140.00 No0.774.21
11.Road Furniture36.00 No0.3501-01-201731-01-201736.00 No36.00 No0.060.35
12.Other Allied Works & Finishing Work 1.00 Job42.0101-01-201731-01-20171.00 Job1.00 Job7.6642.01
Total Amount: 548.69 100   548.69
Remarks: Lab not established       Work Program Made On: 28-09-2015        Updation of work program on: 19-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-March-201523.75  lakh
2.09-June-20159.48  lakh
3.13-August-201553.78  lakh
4.24-September-201547.91  lakh
5.26-December-201544.82  lakh
6.30-January-201612.36  lakh
7.04-May-201658.58  lakh
8.18-May-201650.32  lakh
9.29-June-201644.26  lakh
10.27-October-201637.01  lakh
11.09-March-201784.32  lakh
12.22-May-201737.10  lakh
13.04-August-201737.54  lakh
Total 541.23  lakh
% Payment 95.73 %
Advance Amount:  46.71  lakh        Recovered Amount:  46.71  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 241   No. of Test Done : 240    No. of Test Passed : 229   No. of Test Failed : 11   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.67
Number of Notice(s) issued: 72

Mobile Pic Upload

Number of Pics Available on Web Repository: 111
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-11-20178+950CME and EE sir site visit observation compliance of CE sir on dated 2-11-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
2.04-11-20179+160CME and EE sir site visit observation compliance of CE on dated 2-11-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
3.19-04-20177+700Rolling of seal coatNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
4.18-04-20177+700Premix carpet layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
5.18-04-20177+600Rolling of premix carpetNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
6.18-04-20177+325Compaction of premix carpetNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
7.17-04-20176+975Seal coat layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
8.17-04-20177+250Rolling of premix carpetNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
9.16-04-20177+025Rolling of premix carpetNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
10.14-04-20176+650Premix carpet layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
11.14-04-20176+800Premix carpet workNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
12.13-04-20176+600Premix carpet layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
13.13-04-20177+500Seal coat layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
14.12-04-2017CH 6.800Premix carpet layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
15.12-04-20177+00Rolling of seal coatNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
16.12-04-20177+000Rolling of seal coatNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
17.11-04-20177+300Laying of seal coatNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
18.11-04-20177+400Rolling of seal coatNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
19.10-04-20178+300Laying seal coatNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
20.10-04-20178+420Compaction at premix carpetNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic