Kotkhal jagtoli MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2531 |
Sanction Cost: |
538.57 lakh |
Length:
|
7.000 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 43
Package Name: 
UDRP/PWD/03/39/RD/043
Tender Date: 16-06-2014
Current Status: Agreement signed
Achieved on Date: 25-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/39/RD/043
Contractor Name: Sahab Singh Rawat & Brothers
|
Start Date: 01-12-2014
Intended Completion Date: 03-05-2017
Original End Date: 29-02-2016 |
Total Bond Cost: 45857772.73 (458.58 lakh)
Variation Cost: 10679547.72 (106.8 lakh) Hence Total Bond Cost is 56537320.45 (565.37 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 596154 for 26 days
LD Analysis for Milestone2: calculated LD is Rs 412722 for 18 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.87 KM | 10.13 | 29-12-2015 | 30-04-2016 | 0.87 KM | 0.87 KM | 1.85 | 10.13 | 2. | R/Wall, B/ Wall Type Protection works | 663.00 m | 96.88 | 25-08-2015 | 15-04-2016 | 663.00 m | 663.00 m | 17.66 | 96.88 | 3. | GSB/RBI/G-1 | 6.91 KM | 80.75 | 20-08-2015 | 31-12-2016 | 6.91 KM | 6.91 KM | 14.72 | 80.75 | 4. | G-2 | 6.91 KM | 54.50 | 01-09-2015 | 31-01-2017 | 6.91 KM | 6.91 KM | 9.93 | 54.50 | 5. | G-3 | 6.91 KM | 54.95 | 01-09-2015 | 28-02-2017 | 6.91 KM | 6.91 KM | 10.02 | 54.95 | 6. | PC/CC i/c Prime Coat, Tack Coat | 6.91 KM | 121.42 | 02-02-2016 | 15-04-2017 | 6.91 KM | 6.91 KM | 22.13 | 121.42 | 7. | Cause Way | 3.00 No | 2.86 | 15-05-2016 | 31-07-2016 | 3.00 No | 3.00 No | 0.52 | 2.86 | 8. | Culverts/Scupper | 24.00 No | 53.60 | 15-08-2015 | 30-05-2016 | 24.00 No | 24.00 No | 9.77 | 53.60 | 9. | longitudinal Drain | 7250.00 m | 27.03 | 15-08-2015 | 31-01-2017 | 7250.00 m | 7250.00 m | 4.93 | 27.03 | 10. | Parapet | 140.00 No | 4.21 | 01-01-2017 | 31-01-2017 | 140.00 No | 140.00 No | 0.77 | 4.21 | 11. | Road Furniture | 36.00 No | 0.35 | 01-01-2017 | 31-01-2017 | 36.00 No | 36.00 No | 0.06 | 0.35 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 42.01 | 01-01-2017 | 31-01-2017 | 1.00 Job | 1.00 Job | 7.66 | 42.01 |
Total Amount: |
548.69 |
|
100 |
548.69 |
|
Remarks:
Lab not established
Work Program Made On:
28-09-2015 } ?>
Updation of work program on:
19-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2015 | 23.75 lakh | 2. | 09-June-2015 | 9.48 lakh | 3. | 13-August-2015 | 53.78 lakh | 4. | 24-September-2015 | 47.91 lakh | 5. | 26-December-2015 | 44.82 lakh | 6. | 30-January-2016 | 12.36 lakh | 7. | 04-May-2016 | 58.58 lakh | 8. | 18-May-2016 | 50.32 lakh | 9. | 29-June-2016 | 44.26 lakh | 10. | 27-October-2016 | 37.01 lakh | 11. | 09-March-2017 | 84.32 lakh | 12. | 22-May-2017 | 37.10 lakh | 13. | 04-August-2017 | 37.54 lakh |
Total |
541.23 lakh |
% Payment |
95.73 % |
|
Advance Amount: 46.71 lakh
Recovered Amount: 46.71 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 241 No. of Test Done : 240 No. of Test Passed : 229 No. of Test Failed : 11 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.67 |
Number of Notice(s) issued: 72 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 111 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-11-2017 | 8+950 | CME and EE sir site visit observation compliance of CE sir on dated 2-11-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
2. | 04-11-2017 | 9+160 | CME and EE sir site visit observation compliance of CE on dated 2-11-2017 | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
3. | 19-04-2017 | 7+700 | Rolling of seal coat | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
4. | 18-04-2017 | 7+700 | Premix carpet laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
5. | 18-04-2017 | 7+600 | Rolling of premix carpet | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
6. | 18-04-2017 | 7+325 | Compaction of premix carpet | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
7. | 17-04-2017 | 6+975 | Seal coat laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
8. | 17-04-2017 | 7+250 | Rolling of premix carpet | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
9. | 16-04-2017 | 7+025 | Rolling of premix carpet | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
10. | 14-04-2017 | 6+650 | Premix carpet laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
11. | 14-04-2017 | 6+800 | Premix carpet work | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
12. | 13-04-2017 | 6+600 | Premix carpet laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
13. | 13-04-2017 | 7+500 | Seal coat laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
14. | 12-04-2017 | CH 6.800 | Premix carpet laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
15. | 12-04-2017 | 7+00 | Rolling of seal coat | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
16. | 12-04-2017 | 7+000 | Rolling of seal coat | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
17. | 11-04-2017 | 7+300 | Laying of seal coat | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
18. | 11-04-2017 | 7+400 | Rolling of seal coat | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
19. | 10-04-2017 | 8+300 | Laying seal coat | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
20. | 10-04-2017 | 8+420 | Compaction at premix carpet | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
|
|