Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Khujeer bend to Chauki Barsil Motor Road Work Completed
Project: UDRP-RB UID: 2530 Sanction Cost: 82.65  lakh Length: 1.000 KM.
District: Rudraprayag Block: August Muni Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 106        Package Name:  UDRP/PWD/03/RD/095        Tender Date: 04-07-2015        Current Status: Agreement signed        Achieved on Date: 03-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/RD/095      Contractor Name: Vinod Kumar Chauhan
Start Date:  10-10-2015      Intended Completion Date:  06-06-2017      Original End Date:  09-01-2017
Total Bond Cost: 55718387.81 (557.18 lakh)        Variation Cost: 9792705.36 (97.93 lakh)    Hence Total Bond Cost is   65511093.17 (655.11 lakh) 
Sub Project Cost: 75.40  lakh        Variation Cost of Sub Project: 530790.32  (5.31 lakh)       Total Sub Project Cost:   80.71 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.00 KM2.4830-10-201520-02-20161.00 KM1.00 KM3.292.48
2.R/Wall, B/ Wall Type Protection works140.00 m17.6508-11-201520-02-2016140.00 m140.00 m23.4117.65
3.G-22.10 KM11.5820-01-201612-04-20162.10 KM2.10 KM15.3611.58
4.G-31.05 KM7.3830-01-201622-04-20161.05 KM1.05 KM9.797.38
5.PC/CC i/c Prime Coat, Tack Coat1.05 KM12.6608-04-201603-06-20171.05 KM1.05 KM16.7912.66
6.Cause Way3.00 No2.7901-12-201528-02-20163.00 No3.00 No3.72.79
7.Culverts/Scupper 2.00 No4.0715-12-201522-01-20162.00 No2.00 No5.44.07
8.longitudinal Drain980.00 m1.8918-02-201604-06-2017980.00 m980.00 m2.511.89
9.Crash Barrier100.00 m2.6518-06-201618-08-2016100.00 m100.00 m3.512.65
10.Parapet35.00 No0.4525-06-201625-09-201635.00 No35.00 No0.60.45
11.Road Furniture6.00 No0.0701-06-201630-06-20166.00 No6.00 No0.090.07
12.Other Allied Works & Finishing Work 1.00 Job11.7420-11-201620-12-20161.00 Job1.00 Job15.5711.74
Total Amount: 75.41 100   75.41
Remarks: No Remarks       Work Program Made On: 17-11-2015        Updation of work program on: 02-06-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-November-20154.80  lakh
2.26-December-20157.74  lakh
3.28-January-201615.88  lakh
4.26-February-201614.01  lakh
5.28-March-201624.22  lakh
6.02-May-201614.94  lakh
7.07-June-20163.88  lakh
8.28-June-20161.04  lakh
9.18-May-20175.70  lakh
10.27-July-20171.26  lakh
Total 93.47  lakh
% Payment115.81 %
Advance Amount:  4.54  lakh        Recovered Amount:  4.54  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 316   No. of Test Done : 349    No. of Test Passed : 334   No. of Test Failed : 15   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 91.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 88
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.03-08-20161+000Land slidesVineet KumarJEUDRP R&B Guptkashi See Pic
2.03-08-20160+950Land slidesVineet KumarJEUDRP R&B Guptkashi See Pic
3.03-08-20160+7003/4 road was-out and land slidesVineet KumarJEUDRP R&B Guptkashi See Pic
4.03-08-20160+590R/w demage and land slidesVineet KumarJEUDRP R&B Guptkashi See Pic
5.03-08-20160+520Land slidesVineet KumarJEUDRP R&B Guptkashi See Pic
6.03-08-20160+400Road settlement zoneVineet KumarJEUDRP R&B Guptkashi See Pic
7.03-08-20160+340Land slidesVineet KumarJEUDRP R&B Guptkashi See Pic
8.03-08-20160+250Land slidesVineet KumarJEUDRP R&B Guptkashi See Pic
9.03-08-20160+200Old R/W drmage and half road demageVineet KumarJEUDRP R&B Guptkashi See Pic
10.03-08-20160+180Old r/w demageVineet KumarJEUDRP R&B Guptkashi See Pic
11.03-08-20160+180Land slidesVineet KumarJEUDRP R&B Guptkashi See Pic
12.03-08-20160+070Land slidesVineet KumarJEUDRP R&B Guptkashi See Pic
13.12-05-2016Ch. 0.300Gradient checkingPratyush ChoudharyMIS ExpertDSC1 R&B WB See Pic
14.12-05-2016Ch 0.150Thickness checkingPratyush ChoudharyMIS ExpertDSC1 R&B WB See Pic
15.12-04-20160.990Site visit of R.S.Anand sir with EE sir,RE sir, AE sir, consultancy staffAjay YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
16.12-04-20160.020Pc layingAjay YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
17.11-04-20160.170Pc laying work in progress , AE sir checking of thicknessAjay YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
18.11-04-20160.125PC laying, AE sir instruction to contractor EmpolyeeAjay YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
19.08-04-20165+250SE sir ,Transit walk syuni-taiti-pata motor road with all staff WB and DSCVineet KumarJEUDRP R&B Guptkashi See Pic
20.08-04-20162+450G2 first layer material stackingVineet KumarJEUDRP R&B Guptkashi See Pic