Khujeer bend to Chauki Barsil Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2530 |
Sanction Cost: |
82.65 lakh |
Length:
|
1.000 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 106
Package Name: 
UDRP/PWD/03/RD/095
Tender Date: 04-07-2015
Current Status: Agreement signed
Achieved on Date: 03-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/RD/095
Contractor Name: Vinod Kumar Chauhan
|
Start Date: 10-10-2015
Intended Completion Date: 06-06-2017
Original End Date: 09-01-2017 |
Total Bond Cost: 55718387.81 (557.18 lakh)
Variation Cost: 9792705.36 (97.93 lakh) Hence Total Bond Cost is 65511093.17 (655.11 lakh)
|
Sub Project Cost: 75.40 lakh
Variation Cost of Sub Project: 530790.32 (5.31 lakh)
Total Sub Project Cost:
80.71 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.00 KM | 2.48 | 30-10-2015 | 20-02-2016 | 1.00 KM | 1.00 KM | 3.29 | 2.48 | 2. | R/Wall, B/ Wall Type Protection works | 140.00 m | 17.65 | 08-11-2015 | 20-02-2016 | 140.00 m | 140.00 m | 23.41 | 17.65 | 3. | G-2 | 2.10 KM | 11.58 | 20-01-2016 | 12-04-2016 | 2.10 KM | 2.10 KM | 15.36 | 11.58 | 4. | G-3 | 1.05 KM | 7.38 | 30-01-2016 | 22-04-2016 | 1.05 KM | 1.05 KM | 9.79 | 7.38 | 5. | PC/CC i/c Prime Coat, Tack Coat | 1.05 KM | 12.66 | 08-04-2016 | 03-06-2017 | 1.05 KM | 1.05 KM | 16.79 | 12.66 | 6. | Cause Way | 3.00 No | 2.79 | 01-12-2015 | 28-02-2016 | 3.00 No | 3.00 No | 3.7 | 2.79 | 7. | Culverts/Scupper | 2.00 No | 4.07 | 15-12-2015 | 22-01-2016 | 2.00 No | 2.00 No | 5.4 | 4.07 | 8. | longitudinal Drain | 980.00 m | 1.89 | 18-02-2016 | 04-06-2017 | 980.00 m | 980.00 m | 2.51 | 1.89 | 9. | Crash Barrier | 100.00 m | 2.65 | 18-06-2016 | 18-08-2016 | 100.00 m | 100.00 m | 3.51 | 2.65 | 10. | Parapet | 35.00 No | 0.45 | 25-06-2016 | 25-09-2016 | 35.00 No | 35.00 No | 0.6 | 0.45 | 11. | Road Furniture | 6.00 No | 0.07 | 01-06-2016 | 30-06-2016 | 6.00 No | 6.00 No | 0.09 | 0.07 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 11.74 | 20-11-2016 | 20-12-2016 | 1.00 Job | 1.00 Job | 15.57 | 11.74 |
Total Amount: |
75.41 |
|
100 |
75.41 |
|
Remarks:
No Remarks
Work Program Made On:
17-11-2015 } ?>
Updation of work program on:
02-06-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-November-2015 | 4.80 lakh | 2. | 26-December-2015 | 7.74 lakh | 3. | 28-January-2016 | 15.88 lakh | 4. | 26-February-2016 | 14.01 lakh | 5. | 28-March-2016 | 24.22 lakh | 6. | 02-May-2016 | 14.94 lakh | 7. | 07-June-2016 | 3.88 lakh | 8. | 28-June-2016 | 1.04 lakh | 9. | 18-May-2017 | 5.70 lakh | 10. | 27-July-2017 | 1.26 lakh |
Total |
93.47 lakh |
% Payment | 115.81 % |
|
Advance Amount: 4.54 lakh
Recovered Amount: 4.54 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 316 No. of Test Done : 349 No. of Test Passed : 334 No. of Test Failed : 15 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 88 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-08-2016 | 1+000 | Land slides | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
2. | 03-08-2016 | 0+950 | Land slides | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
3. | 03-08-2016 | 0+700 | 3/4 road was-out and land slides | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
4. | 03-08-2016 | 0+590 | R/w demage and land slides | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
5. | 03-08-2016 | 0+520 | Land slides | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
6. | 03-08-2016 | 0+400 | Road settlement zone | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
7. | 03-08-2016 | 0+340 | Land slides | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
8. | 03-08-2016 | 0+250 | Land slides | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
9. | 03-08-2016 | 0+200 | Old R/W drmage and half road demage | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
10. | 03-08-2016 | 0+180 | Old r/w demage | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
11. | 03-08-2016 | 0+180 | Land slides | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
12. | 03-08-2016 | 0+070 | Land slides | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
13. | 12-05-2016 | Ch. 0.300 | Gradient checking | Pratyush Choudhary | MIS Expert | DSC1 R&B WB | See Pic |
14. | 12-05-2016 | Ch 0.150 | Thickness checking | Pratyush Choudhary | MIS Expert | DSC1 R&B WB | See Pic |
15. | 12-04-2016 | 0.990 | Site visit of R.S.Anand sir with EE sir,RE sir, AE sir, consultancy staff | Ajay Yadav | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
16. | 12-04-2016 | 0.020 | Pc laying | Ajay Yadav | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
17. | 11-04-2016 | 0.170 | Pc laying work in progress , AE sir checking of thickness | Ajay Yadav | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
18. | 11-04-2016 | 0.125 | PC laying, AE sir instruction to contractor Empolyee | Ajay Yadav | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
19. | 08-04-2016 | 5+250 | SE sir ,Transit walk syuni-taiti-pata motor road with all staff WB and DSC | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
20. | 08-04-2016 | 2+450 | G2 first layer material stacking | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
|
|