Khedakhal- Navasu-Hariyali Motor Road Work Completed
Project: UDRP-RB UID: 2529 Sanction Cost: 104.60  lakh Length: 2.000 KM.
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 105        Package Name:  UDRP/PWD/03/RD/094        Tender Date: 18-03-2015        Current Status: Agreement signed        Achieved on Date: 21-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/RD/094      Contractor Name: Rajendra Singh Kuldeep Singh
Start Date:  28-09-2015      Intended Completion Date:  31-08-2017      Original End Date:  27-12-2016
Total Bond Cost: 60882905.22 (608.83 lakh)        Variation Cost: 3951257.62 (39.51 lakh)    Hence Total Bond Cost is   64834162.84 (648.34 lakh) 
Sub Project Cost: 86.20  lakh        Variation Cost of Sub Project: -201087.65  (-2.01 lakh)       Total Sub Project Cost:   84.19 lakh
LD Analysis for Milestone1: calculated LD is Rs 2404839 for 79 days        LD Analysis for Milestone2: calculated LD is Rs 5418498 for 178 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works490.00 m11.2401-10-201530-06-2016490.00 m490.00 m13.9711.24
2.GSB/RBI/G-11.10 KM11.6802-11-201531-03-20161.10 KM1.10 KM14.5211.68
3.G-21.10 KM8.4415-11-201505-06-20161.10 KM1.10 KM10.498.44
4.G-31.10 KM10.9715-05-201610-06-20161.10 KM1.10 KM13.6310.97
5.PC/CC i/c Prime Coat, Tack Coat2.00 KM25.8815-06-201630-06-20162.00 KM2.00 KM32.1625.88
6.Culverts/Scupper 1.00 No2.0120-10-201528-02-20161.00 No1.00 No2.52.01
7.longitudinal Drain1875.00 m5.3520-06-201630-08-20161875.00 m1875.00 m6.655.35
8.Crash Barrier270.00 m1.1520-10-201620-12-2016270.00 m270.00 m1.431.15
9.Parapet80.00 No2.7905-08-201630-08-201680.00 No80.00 No3.472.79
10.Road Furniture25.00 No0.9620-10-201610-08-201725.00 No25.00 No1.190.96
Total Amount: 80.47 100   80.47
Remarks: No Remarks       Work Program Made On: 17-11-2015        Updation of work program on: 25-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-November-20152.12  lakh
2.26-December-20150.86  lakh
3.28-January-20162.68  lakh
4.29-February-20161.51  lakh
5.25-May-20168.47  lakh
6.29-June-201633.83  lakh
7.18-July-201615.88  lakh
8.30-August-20163.16  lakh
9.25-September-20165.81  lakh
10.26-October-20160.11  lakh
11.18-May-20170.41  lakh
12.07-July-20170.90  lakh
13.31-July-20175.46  lakh
14.18-November-20173.00  lakh
Total 84.2  lakh
% Payment100.01 %
Advance Amount:  104.19  lakh        Recovered Amount:  104.19  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 267   No. of Test Done : 298    No. of Test Passed : 280   No. of Test Failed : 18   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 62
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.22-02-20171+150Village sign boardParvindar SinghJEUDRP R&B Guptkashi See Pic
2.22-02-20170+230Sign board of hospitalParvindar SinghJEUDRP R&B Guptkashi See Pic
3.16-12-20161.500Surface cleanAjay YadavSite SupervisorDSC1 R&B WB Rudraprayag See Pic
4.14-12-20161+500Road cleaning after land slidesVineet KumarJEUDRP R&B Guptkashi See Pic
5.14-12-20160+065Construction of R/W damage in rain seasonal.Naresh Kumar RathorAEUDRP R&B Guptkashi See Pic
6.14-12-20160+100Wall.reconstruction.at that ch.when damage in rain seasonalNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
7.14-12-20161+750Wall reconstruction at that ch.when damage in rain seasonal.Naresh Kumar RathorAEUDRP R&B Guptkashi See Pic
8.14-12-20161+680Parapit &wall construction.at that ch. When damages in rain seasonal.Naresh Kumar RathorAEUDRP R&B Guptkashi See Pic
9.14-12-20161+500Wire crates construction. at that ch. Slides in rain seasonalNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
10.14-12-20161+460Cleaning of road surface.when slides in rain seasonal.Naresh Kumar RathorAEUDRP R&B Guptkashi See Pic
11.14-12-20161+415Cleaning of road surface .when slide in rain seasonal.Naresh Kumar RathorAEUDRP R&B Guptkashi See Pic
12.14-12-20161+250Patches work .that change damage in rainy seasonal.Naresh Kumar RathorAEUDRP R&B Guptkashi See Pic
13.14-12-20160+465Wall construction.when damage in reany session.Naresh Kumar RathorAEUDRP R&B Guptkashi See Pic
14.06-12-20161. 900SE sir Gopeshwar checking thickness of pc, and grading. No. G1, G2, G3Naresh Kumar RathorAEUDRP R&B Guptkashi See Pic
15.01-10-20161+600Land slides portion after cleaning.Vineet KumarJEUDRP R&B Guptkashi See Pic
16.16-09-20160+050R/W bended with plumVineet KumarJEUDRP R&B Guptkashi See Pic
17.16-09-20160+475R/W with plumVineet KumarJEUDRP R&B Guptkashi See Pic
18.15-09-20160+475R/W back filling workVineet KumarJEUDRP R&B Guptkashi See Pic
19.06-09-20160+050Bended wall dry part filling workVineet KumarJEUDRP R&B Guptkashi See Pic
20.06-09-20160+575Crash barrier fixed.Vineet KumarJEUDRP R&B Guptkashi See Pic