Khedakhal- Navasu-Hariyali Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2529 |
Sanction Cost: |
104.60 lakh |
Length:
|
2.000 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 105
Package Name: 
UDRP/PWD/03/RD/094
Tender Date: 18-03-2015
Current Status: Agreement signed
Achieved on Date: 21-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/RD/094
Contractor Name: Rajendra Singh Kuldeep Singh
|
Start Date: 28-09-2015
Intended Completion Date: 31-08-2017
Original End Date: 27-12-2016 |
Total Bond Cost: 60882905.22 (608.83 lakh)
Variation Cost: 3951257.62 (39.51 lakh) Hence Total Bond Cost is 64834162.84 (648.34 lakh)
|
Sub Project Cost: 86.20 lakh
Variation Cost of Sub Project: -201087.65 (-2.01 lakh)
Total Sub Project Cost:
84.19 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2404839 for 79 days
LD Analysis for Milestone2: calculated LD is Rs 5418498 for 178 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 490.00 m | 11.24 | 01-10-2015 | 30-06-2016 | 490.00 m | 490.00 m | 13.97 | 11.24 | 2. | GSB/RBI/G-1 | 1.10 KM | 11.68 | 02-11-2015 | 31-03-2016 | 1.10 KM | 1.10 KM | 14.52 | 11.68 | 3. | G-2 | 1.10 KM | 8.44 | 15-11-2015 | 05-06-2016 | 1.10 KM | 1.10 KM | 10.49 | 8.44 | 4. | G-3 | 1.10 KM | 10.97 | 15-05-2016 | 10-06-2016 | 1.10 KM | 1.10 KM | 13.63 | 10.97 | 5. | PC/CC i/c Prime Coat, Tack Coat | 2.00 KM | 25.88 | 15-06-2016 | 30-06-2016 | 2.00 KM | 2.00 KM | 32.16 | 25.88 | 6. | Culverts/Scupper | 1.00 No | 2.01 | 20-10-2015 | 28-02-2016 | 1.00 No | 1.00 No | 2.5 | 2.01 | 7. | longitudinal Drain | 1875.00 m | 5.35 | 20-06-2016 | 30-08-2016 | 1875.00 m | 1875.00 m | 6.65 | 5.35 | 8. | Crash Barrier | 270.00 m | 1.15 | 20-10-2016 | 20-12-2016 | 270.00 m | 270.00 m | 1.43 | 1.15 | 9. | Parapet | 80.00 No | 2.79 | 05-08-2016 | 30-08-2016 | 80.00 No | 80.00 No | 3.47 | 2.79 | 10. | Road Furniture | 25.00 No | 0.96 | 20-10-2016 | 10-08-2017 | 25.00 No | 25.00 No | 1.19 | 0.96 |
Total Amount: |
80.47 |
|
100 |
80.47 |
|
Remarks:
No Remarks
Work Program Made On:
17-11-2015 } ?>
Updation of work program on:
25-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-November-2015 | 2.12 lakh | 2. | 26-December-2015 | 0.86 lakh | 3. | 28-January-2016 | 2.68 lakh | 4. | 29-February-2016 | 1.51 lakh | 5. | 25-May-2016 | 8.47 lakh | 6. | 29-June-2016 | 33.83 lakh | 7. | 18-July-2016 | 15.88 lakh | 8. | 30-August-2016 | 3.16 lakh | 9. | 25-September-2016 | 5.81 lakh | 10. | 26-October-2016 | 0.11 lakh | 11. | 18-May-2017 | 0.41 lakh | 12. | 07-July-2017 | 0.90 lakh | 13. | 31-July-2017 | 5.46 lakh | 14. | 18-November-2017 | 3.00 lakh |
Total |
84.2 lakh |
% Payment | 100.01 % |
|
Advance Amount: 104.19 lakh
Recovered Amount: 104.19 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 267 No. of Test Done : 298 No. of Test Passed : 280 No. of Test Failed : 18 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 62 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-02-2017 | 1+150 | Village sign board | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
2. | 22-02-2017 | 0+230 | Sign board of hospital | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
3. | 16-12-2016 | 1.500 | Surface clean | Ajay Yadav | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
4. | 14-12-2016 | 1+500 | Road cleaning after land slides | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
5. | 14-12-2016 | 0+065 | Construction of R/W damage in rain seasonal. | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
6. | 14-12-2016 | 0+100 | Wall.reconstruction.at that ch.when damage in rain seasonal | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
7. | 14-12-2016 | 1+750 | Wall reconstruction at that ch.when damage in rain seasonal. | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
8. | 14-12-2016 | 1+680 | Parapit &wall construction.at that ch. When damages in rain seasonal. | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
9. | 14-12-2016 | 1+500 | Wire crates construction. at that ch. Slides in rain seasonal | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
10. | 14-12-2016 | 1+460 | Cleaning of road surface.when slides in rain seasonal. | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
11. | 14-12-2016 | 1+415 | Cleaning of road surface .when slide in rain seasonal. | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
12. | 14-12-2016 | 1+250 | Patches work .that change damage in rainy seasonal. | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
13. | 14-12-2016 | 0+465 | Wall construction.when damage in reany session. | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
14. | 06-12-2016 | 1. 900 | SE sir Gopeshwar checking thickness of pc, and grading. No. G1, G2, G3 | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
15. | 01-10-2016 | 1+600 | Land slides portion after cleaning. | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
16. | 16-09-2016 | 0+050 | R/W bended with plum | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
17. | 16-09-2016 | 0+475 | R/W with plum | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
18. | 15-09-2016 | 0+475 | R/W back filling work | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
19. | 06-09-2016 | 0+050 | Bended wall dry part filling work | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
20. | 06-09-2016 | 0+575 | Crash barrier fixed. | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
|
|