Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kandai-Barangana Motor Road Work Completed
Project: UDRP-RB UID: 2527 Sanction Cost: 366.66  lakh Length: 4.400 KM.
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 105        Package Name:  UDRP/PWD/03/RD/094        Tender Date: 18-03-2015        Current Status: Agreement signed        Achieved on Date: 21-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/RD/094      Contractor Name: Rajendra Singh Kuldeep Singh
Start Date:  28-09-2015      Intended Completion Date:  31-08-2017      Original End Date:  27-12-2016
Total Bond Cost: 60882905.22 (608.83 lakh)        Variation Cost: 3951257.62 (39.51 lakh)    Hence Total Bond Cost is   64834162.84 (648.34 lakh) 
Sub Project Cost: 338.93  lakh        Variation Cost of Sub Project: 354862.89  (3.55 lakh)       Total Sub Project Cost:   342.48 lakh
LD Analysis for Milestone1: calculated LD is Rs 2404839 for 79 days        LD Analysis for Milestone2: calculated LD is Rs 5418498 for 178 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence4.00 KM16.8501-10-201531-03-20164.00 KM4.00 KM6.4816.85
2.R/Wall, B/ Wall Type Protection works500.00 m91.8901-10-201530-08-2016500.00 m500.00 m35.3691.89
3.G-27.60 KM26.2301-03-201631-08-20167.60 KM7.60 KM10.0926.23
4.G-33.80 KM32.6415-11-201615-01-20173.80 KM3.80 KM12.5632.64
5.PC/CC i/c Prime Coat, Tack Coat3.80 KM60.3615-03-201715-04-20173.80 KM3.80 KM23.2360.36
6.Cause Way2.00 No4.5501-01-201731-01-20172.00 No2.00 No1.754.55
7.Culverts/Scupper 16.00 No11.1920-10-201530-09-201616.00 No16.00 No4.3111.19
8.longitudinal Drain3900.00 m13.2001-05-201610-08-20173900.00 m3900.00 m5.0813.20
9.Crash Barrier50.00 m1.1520-03-201730-04-201750.00 m50.00 m0.441.15
10.Parapet65.00 No1.5901-02-201715-05-201765.00 No65.00 No0.611.59
11.Road Furniture23.00 No0.2315-05-201710-08-201723.00 No23.00 No0.090.23
Total Amount: 259.88 100   259.88
Remarks: No Remarks       Work Program Made On: 17-11-2015        Updation of work program on: 25-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-November-201513.31  lakh
2.26-December-201517.62  lakh
3.28-January-201619.67  lakh
4.29-February-20163.20  lakh
5.25-May-201627.75  lakh
6.29-June-201612.04  lakh
7.18-July-20169.36  lakh
8.30-August-201615.13  lakh
9.25-September-20169.15  lakh
10.26-October-20165.63  lakh
11.24-December-201618.07  lakh
12.28-February-201734.20  lakh
13.30-March-201733.76  lakh
14.18-May-201724.27  lakh
15.25-May-201717.36  lakh
16.07-July-201713.53  lakh
17.31-July-201725.07  lakh
18.23-September-201721.79  lakh
19.18-November-201726.09  lakh
Total 347  lakh
% Payment101.32 %
Advance Amount:  104.19  lakh        Recovered Amount:  104.19  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 267   No. of Test Done : 298    No. of Test Passed : 280   No. of Test Failed : 18   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 83.50
Number of Notice(s) issued: 1

Mobile Pic Upload

Number of Pics Available on Web Repository: 93
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.05-08-20173+200SrmdPrashant KumarQCDSC WB SPW Rudraprayag See Pic
2.01-07-20170+100Geologist inspection at kandai barangna motor road with QC and AENaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
3.18-04-2017Change 1+330Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic
4.04-04-2017Chainage 1+300Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic
5.01-04-2017Chainage 1+970Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic
6.31-03-20171+620Premix carpet layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
7.30-03-20171+550Seal coat layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
8.30-03-20171+750Premix carpet layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
9.29-03-2017Labour hutsSE sir inspection at labour hutsNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
10.29-03-20172+100SE sir visit.checking temp. Of mixing and laying PCNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
11.29-03-20172+200Laying premix carpet workNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
12.27-03-2017Chainage 2+620Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic
13.25-03-20172+700Laying of premix carpetNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
14.25-03-2017Chainage 3+320Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic
15.24-03-2017Chainage 1+870Water sprinkling on WBM-G3Parvindar SinghJEUDRP R&B Guptkashi See Pic
16.24-03-2017Chainage 3+170Laying of seal coat type-CParvindar SinghJEUDRP R&B Guptkashi See Pic
17.24-03-2017Chainage 3+290Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic
18.23-03-20173+120Laying of seal coat type-CParvindar SinghJEUDRP R&B Guptkashi See Pic
19.23-03-2017Chainage 3+100Laying of seal coat type-CParvindar SinghJEUDRP R&B Guptkashi See Pic
20.23-03-2017Chainage 3+120Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic