Kandai-Barangana Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2527 |
Sanction Cost: |
366.66 lakh |
Length:
|
4.400 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 105
Package Name: 
UDRP/PWD/03/RD/094
Tender Date: 18-03-2015
Current Status: Agreement signed
Achieved on Date: 21-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/RD/094
Contractor Name: Rajendra Singh Kuldeep Singh
|
Start Date: 28-09-2015
Intended Completion Date: 31-08-2017
Original End Date: 27-12-2016 |
Total Bond Cost: 60882905.22 (608.83 lakh)
Variation Cost: 3951257.62 (39.51 lakh) Hence Total Bond Cost is 64834162.84 (648.34 lakh)
|
Sub Project Cost: 338.93 lakh
Variation Cost of Sub Project: 354862.89 (3.55 lakh)
Total Sub Project Cost:
342.48 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2404839 for 79 days
LD Analysis for Milestone2: calculated LD is Rs 5418498 for 178 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 4.00 KM | 16.85 | 01-10-2015 | 31-03-2016 | 4.00 KM | 4.00 KM | 6.48 | 16.85 | 2. | R/Wall, B/ Wall Type Protection works | 500.00 m | 91.89 | 01-10-2015 | 30-08-2016 | 500.00 m | 500.00 m | 35.36 | 91.89 | 3. | G-2 | 7.60 KM | 26.23 | 01-03-2016 | 31-08-2016 | 7.60 KM | 7.60 KM | 10.09 | 26.23 | 4. | G-3 | 3.80 KM | 32.64 | 15-11-2016 | 15-01-2017 | 3.80 KM | 3.80 KM | 12.56 | 32.64 | 5. | PC/CC i/c Prime Coat, Tack Coat | 3.80 KM | 60.36 | 15-03-2017 | 15-04-2017 | 3.80 KM | 3.80 KM | 23.23 | 60.36 | 6. | Cause Way | 2.00 No | 4.55 | 01-01-2017 | 31-01-2017 | 2.00 No | 2.00 No | 1.75 | 4.55 | 7. | Culverts/Scupper | 16.00 No | 11.19 | 20-10-2015 | 30-09-2016 | 16.00 No | 16.00 No | 4.31 | 11.19 | 8. | longitudinal Drain | 3900.00 m | 13.20 | 01-05-2016 | 10-08-2017 | 3900.00 m | 3900.00 m | 5.08 | 13.20 | 9. | Crash Barrier | 50.00 m | 1.15 | 20-03-2017 | 30-04-2017 | 50.00 m | 50.00 m | 0.44 | 1.15 | 10. | Parapet | 65.00 No | 1.59 | 01-02-2017 | 15-05-2017 | 65.00 No | 65.00 No | 0.61 | 1.59 | 11. | Road Furniture | 23.00 No | 0.23 | 15-05-2017 | 10-08-2017 | 23.00 No | 23.00 No | 0.09 | 0.23 |
Total Amount: |
259.88 |
|
100 |
259.88 |
|
Remarks:
No Remarks
Work Program Made On:
17-11-2015 } ?>
Updation of work program on:
25-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-November-2015 | 13.31 lakh | 2. | 26-December-2015 | 17.62 lakh | 3. | 28-January-2016 | 19.67 lakh | 4. | 29-February-2016 | 3.20 lakh | 5. | 25-May-2016 | 27.75 lakh | 6. | 29-June-2016 | 12.04 lakh | 7. | 18-July-2016 | 9.36 lakh | 8. | 30-August-2016 | 15.13 lakh | 9. | 25-September-2016 | 9.15 lakh | 10. | 26-October-2016 | 5.63 lakh | 11. | 24-December-2016 | 18.07 lakh | 12. | 28-February-2017 | 34.20 lakh | 13. | 30-March-2017 | 33.76 lakh | 14. | 18-May-2017 | 24.27 lakh | 15. | 25-May-2017 | 17.36 lakh | 16. | 07-July-2017 | 13.53 lakh | 17. | 31-July-2017 | 25.07 lakh | 18. | 23-September-2017 | 21.79 lakh | 19. | 18-November-2017 | 26.09 lakh |
Total |
347 lakh |
% Payment | 101.32 % |
|
Advance Amount: 104.19 lakh
Recovered Amount: 104.19 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 267 No. of Test Done : 298 No. of Test Passed : 280 No. of Test Failed : 18 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 83.50 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 93 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 05-08-2017 | 3+200 | Srmd | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
2. | 01-07-2017 | 0+100 | Geologist inspection at kandai barangna motor road with QC and AE | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
3. | 18-04-2017 | Change 1+330 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
4. | 04-04-2017 | Chainage 1+300 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
5. | 01-04-2017 | Chainage 1+970 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
6. | 31-03-2017 | 1+620 | Premix carpet laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
7. | 30-03-2017 | 1+550 | Seal coat laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
8. | 30-03-2017 | 1+750 | Premix carpet laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
9. | 29-03-2017 | Labour huts | SE sir inspection at labour huts | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
10. | 29-03-2017 | 2+100 | SE sir visit.checking temp. Of mixing and laying PC | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
11. | 29-03-2017 | 2+200 | Laying premix carpet work | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
12. | 27-03-2017 | Chainage 2+620 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
13. | 25-03-2017 | 2+700 | Laying of premix carpet | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
14. | 25-03-2017 | Chainage 3+320 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
15. | 24-03-2017 | Chainage 1+870 | Water sprinkling on WBM-G3 | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
16. | 24-03-2017 | Chainage 3+170 | Laying of seal coat type-C | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
17. | 24-03-2017 | Chainage 3+290 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
18. | 23-03-2017 | 3+120 | Laying of seal coat type-C | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
19. | 23-03-2017 | Chainage 3+100 | Laying of seal coat type-C | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
20. | 23-03-2017 | Chainage 3+120 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
|
|