Kamsal Jagoth motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2526 |
Sanction Cost: |
272.24 lakh |
Length:
|
6.400 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 65
Package Name: 
UDRP/PWD/03/40/RD/055
Tender Date: 24-12-2014
Current Status: Agreement signed
Achieved on Date: 01-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/RD/055
Contractor Name: Bhatt & Thapliyal Engineering
|
Start Date: 08-07-2015
Intended Completion Date: 30-05-2017
Original End Date: 07-10-2016 |
Total Bond Cost: 43975819.08 (439.76 lakh)
Variation Cost: 5398141.22 (53.98 lakh) Hence Total Bond Cost is 49373960.3 (493.74 lakh)
|
Sub Project Cost: 259.03 lakh
Variation Cost of Sub Project: 443702.58 (4.44 lakh)
Total Sub Project Cost:
263.47 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 549700 for 25 days
LD Analysis for Milestone2: calculated LD is Rs 637652 for 29 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 6.16 KM | 9.39 | 20-07-2015 | 30-05-2016 | 6.16 KM | 6.16 KM | 4.02 | 9.39 | 2. | R/Wall, B/ Wall Type Protection works | 1280.00 m | 80.40 | 20-07-2015 | 15-06-2016 | 1280.00 m | 1280.00 m | 34.4 | 80.40 | 3. | G-2 | 1.20 KM | 6.89 | 15-05-2016 | 31-08-2016 | 1.20 KM | 1.20 KM | 2.95 | 6.89 | 4. | PC/CC i/c Prime Coat, Tack Coat | 6.16 KM | 78.94 | 15-04-2016 | 25-11-2016 | 6.16 KM | 6.16 KM | 33.77 | 78.94 | 5. | Cause Way | 4.00 No | 8.46 | 20-08-2015 | 31-08-2016 | 4.00 No | 4.00 No | 3.62 | 8.46 | 6. | Culverts/Scupper | 5.00 No | 14.90 | 20-08-2015 | 30-03-2016 | 5.00 No | 5.00 No | 6.38 | 14.90 | 7. | longitudinal Drain | 5700.00 m | 19.42 | 20-08-2015 | 30-11-2016 | 5700.00 m | 5700.00 m | 8.31 | 19.42 | 8. | Crash Barrier | 50.00 m | 8.45 | 15-05-2016 | 30-09-2016 | 50.00 m | 50.00 m | 3.62 | 8.45 | 9. | Parapet | 150.00 No | 6.59 | 15-05-2016 | 30-09-2016 | 150.00 No | 150.00 No | 2.82 | 6.59 | 10. | Road Furniture | 32.00 No | 0.30 | 01-06-2016 | 31-10-2016 | 32.00 No | 32.00 No | 0.13 | 0.30 |
Total Amount: |
233.74 |
|
100 |
233.74 |
|
Remarks:
No Remarks
Work Program Made On:
01-09-2015 } ?>
Updation of work program on:
19-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-August-2015 | 13.60 lakh | 2. | 31-October-2015 | 29.37 lakh | 3. | 26-February-2016 | 33.30 lakh | 4. | 21-March-2016 | 18.63 lakh | 5. | 18-May-2016 | 42.17 lakh | 6. | 29-June-2016 | 46.35 lakh | 7. | 23-August-2016 | 18.10 lakh | 8. | 03-October-2016 | 12.29 lakh | 9. | 09-March-2017 | 22.67 lakh | 10. | 04-August-2017 | 25.80 lakh |
Total |
262.28 lakh |
% Payment | 99.55 % |
|
Advance Amount: 27.54 lakh
Recovered Amount: 27.54 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 287 No. of Test Done : 298 No. of Test Passed : 284 No. of Test Failed : 14 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 178 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-02-2017 | Ch 6.100 | Site inspection by se sir adb appda circle Srinagar at kamsal jagot motor road | Rahul Panwar | Survey Engineer | NH Srinagar | See Pic |
2. | 07-01-2017 | 4+650 | C.E., E.E, sir visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
3. | 07-01-2017 | 0+150 | C.E., E.E. sir visit. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
4. | 15-09-2016 | 2+625 | Premature stripping of PC surface and forming rutting on the surface due to seepage of ground water.Instructed to rectify with khadanja with 1:2:4 CC | Sam Allen Matthews | TL | DSC1 R&B WB | See Pic |
5. | 15-09-2016 | 2+625 | Site visit along with EE,AE,RE.Found premature stripping of PC due to seepage of ground water.Suggested for Stone Soling with CC 1:2:4 | Sam Allen Matthews | TL | DSC1 R&B WB | See Pic |
6. | 31-08-2016 | 5+150 | slip clearance work on progress | Jagat Chand Ramola | JE | UDRP R&B Guptkashi | See Pic |
7. | 28-07-2016 | Ch. 3+800 | Parapet Casting | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
8. | 28-07-2016 | Ch. 3+850 | Parapet shuttering fix | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
9. | 27-07-2016 | 2300 | Slip due to heavy rainfall | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
10. | 24-07-2016 | Ch. 2225 | B/w damage due to slip | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
11. | 24-07-2016 | Ch. 3+450 | Parapet | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
12. | 20-07-2016 | 3700 | slip | Jagat Chand Ramola | JE | UDRP R&B Guptkashi | See Pic |
13. | 20-07-2016 | 4175 | bwall and wire create demage due to slip | Jagat Chand Ramola | JE | UDRP R&B Guptkashi | See Pic |
14. | 19-07-2016 | ch. 4450 | srmd:slip | Jagat Chand Ramola | JE | UDRP R&B Guptkashi | See Pic |
15. | 19-07-2016 | 5+700 | srmd:slip | Jagat Chand Ramola | JE | UDRP R&B Guptkashi | See Pic |
16. | 19-07-2016 | Ch. 2+400 | Slip | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
17. | 19-07-2016 | Ch. 3775 | W/c damage due to slip | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
18. | 19-07-2016 | CH 5+300 | Slip | Rahul Panwar | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
19. | 19-07-2016 | 6+00 | Sinking zone | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
20. | 19-07-2016 | 6+00 | Bended r/wall | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
|
|