Jakhdhar-Dewar MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2524 |
Sanction Cost: |
203.94 lakh |
Length:
|
3.000 KM. |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 106
Package Name: 
UDRP/PWD/03/RD/095
Tender Date: 04-07-2015
Current Status: Agreement signed
Achieved on Date: 03-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/RD/095
Contractor Name: Vinod Kumar Chauhan
|
Start Date: 10-10-2015
Intended Completion Date: 06-06-2017
Original End Date: 09-01-2017 |
Total Bond Cost: 55718387.81 (557.18 lakh)
Variation Cost: 9792705.36 (97.93 lakh) Hence Total Bond Cost is 65511093.17 (655.11 lakh)
|
Sub Project Cost: 158.90 lakh
Variation Cost of Sub Project: 2417900.53 (24.18 lakh)
Total Sub Project Cost:
183.08 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 212.00 m | 10.78 | 01-11-2015 | 15-06-2016 | 212.00 m | 212.00 m | 6.49 | 10.78 | 2. | GSB/RBI/G-1 | 3.00 KM | 22.68 | 01-01-2016 | 10-10-2016 | 3.00 KM | 3.00 KM | 13.65 | 22.68 | 3. | G-2 | 3.00 KM | 18.01 | 15-05-2016 | 31-12-2016 | 3.00 KM | 3.00 KM | 10.84 | 18.01 | 4. | G-3 | 3.00 KM | 20.96 | 30-09-2016 | 20-03-2017 | 3.00 KM | 3.00 KM | 12.62 | 20.96 | 5. | PC/CC i/c Prime Coat, Tack Coat | 3.00 KM | 38.19 | 15-03-2017 | 30-04-2017 | 3.00 KM | 3.00 KM | 22.99 | 38.19 | 6. | Culverts/Scupper | 6.00 No | 12.12 | 01-12-2015 | 30-06-2016 | 6.00 No | 6.00 No | 7.3 | 12.12 | 7. | longitudinal Drain | 3000.00 m | 19.70 | 15-02-2016 | 15-10-2016 | 3000.00 m | 3000.00 m | 11.86 | 19.70 | 8. | Crash Barrier | 741.00 m | 19.71 | 01-01-2017 | 31-01-2017 | 741.00 m | 741.00 m | 11.86 | 19.71 | 9. | Parapet | 160.00 No | 3.86 | 01-01-2017 | 31-01-2017 | 160.00 No | 160.00 No | 2.32 | 3.86 | 10. | Road Furniture | 15.00 No | 0.14 | 01-01-2017 | 31-01-2017 | 15.00 No | 15.00 No | 0.08 | 0.14 |
Total Amount: |
166.15 |
|
100 |
166.15 |
|
Remarks:
No Remarks
Work Program Made On:
17-11-2015 } ?>
Updation of work program on:
19-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-November-2015 | 4.49 lakh | 2. | 28-January-2016 | 9.20 lakh | 3. | 28-March-2016 | 5.97 lakh | 4. | 02-May-2016 | 2.55 lakh | 5. | 18-May-2016 | 7.94 lakh | 6. | 28-June-2016 | 13.43 lakh | 7. | 11-September-2016 | 8.71 lakh | 8. | 24-October-2016 | 11.92 lakh | 9. | 24-December-2016 | 11.05 lakh | 10. | 28-February-2017 | 7.47 lakh | 11. | 30-March-2017 | 23.67 lakh | 12. | 18-May-2017 | 76.15 lakh | 13. | 27-July-2017 | 4.42 lakh |
Total |
186.97 lakh |
% Payment | 102.12 % |
|
Advance Amount: 4.54 lakh
Recovered Amount: 4.54 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 316 No. of Test Done : 349 No. of Test Passed : 334 No. of Test Failed : 15 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.08 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 36 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-04-2017 | 1.025 | Premix carpet work rolling process | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
2. | 12-04-2017 | 2.350 last HP Bend | Premix Carpet on HP Bend | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
3. | 09-04-2017 | 2.900 | Premix carpet surface before seal coat work in progress | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
4. | 04-04-2017 | Chainage 3.000 | Premix carpet work started | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
5. | 27-02-2017 | 3.000 end point of road | Compaction of G3 layer dry rolling | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
6. | 27-02-2017 | 2.600 | Top coat G3 laying started on jakdhar dewar Motor Road | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
7. | 26-02-2017 | 2.325 | Water sprinkling with tank on G2 jakdhar dewar MR | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
8. | 25-02-2017 | 2.150 | Dry rolling of Grading no. 2 | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
9. | 25-02-2017 | 2.175 | Laying of G2 layer after dry compaction | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
10. | 03-02-2017 | 2+600 | Gradation test of G1 laying | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
11. | 06-01-2017 | 0+200 | Thickness cheking of g3 check by CE sir & EE sir | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
12. | 06-01-2017 | 0+200 | Site inspection by CE sir &EE sir | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
13. | 06-01-2017 | 1.550 | Thickness checking G1 G2 jakdhar dewar Cheif Sir visit | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
14. | 19-12-2016 | 0.375 | Gradation G2 | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
15. | 25-04-2016 | Km 1 ch starting point | Preparation of subgrade for G-1 at junction point | Shankar Ram | EE | UDRP R&B Guptkashi | See Pic |
16. | 05-02-2016 | 1.000 | 1 m span scupper steel reinforcement . preparation of slab casting | Siddharth Ranghar | JE | DEA WB Guptkashi | See Pic |
17. | 12-01-2016 | 2+600 | B/w in progress | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
18. | 09-01-2016 | 0+135 | Bad block in scupper | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
19. | 09-01-2016 | 0+135 | Bad block in scupper | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
20. | 09-01-2016 | 1+000 | Bad block in scupper | Ashish Dhiman | Site Supervisor | DSC1 R&B WB Rudraprayag | See Pic |
|
|