Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Jakhdhar-Dewar MR Work Completed
Project: UDRP-RB UID: 2524 Sanction Cost: 203.94  lakh Length: 3.000 KM.
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 106        Package Name:  UDRP/PWD/03/RD/095        Tender Date: 04-07-2015        Current Status: Agreement signed        Achieved on Date: 03-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/RD/095      Contractor Name: Vinod Kumar Chauhan
Start Date:  10-10-2015      Intended Completion Date:  06-06-2017      Original End Date:  09-01-2017
Total Bond Cost: 55718387.81 (557.18 lakh)        Variation Cost: 9792705.36 (97.93 lakh)    Hence Total Bond Cost is   65511093.17 (655.11 lakh) 
Sub Project Cost: 158.90  lakh        Variation Cost of Sub Project: 2417900.53  (24.18 lakh)       Total Sub Project Cost:   183.08 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works212.00 m10.7801-11-201515-06-2016212.00 m212.00 m6.4910.78
2.GSB/RBI/G-13.00 KM22.6801-01-201610-10-20163.00 KM3.00 KM13.6522.68
3.G-23.00 KM18.0115-05-201631-12-20163.00 KM3.00 KM10.8418.01
4.G-33.00 KM20.9630-09-201620-03-20173.00 KM3.00 KM12.6220.96
5.PC/CC i/c Prime Coat, Tack Coat3.00 KM38.1915-03-201730-04-20173.00 KM3.00 KM22.9938.19
6.Culverts/Scupper 6.00 No12.1201-12-201530-06-20166.00 No6.00 No7.312.12
7.longitudinal Drain3000.00 m19.7015-02-201615-10-20163000.00 m3000.00 m11.8619.70
8.Crash Barrier741.00 m19.7101-01-201731-01-2017741.00 m741.00 m11.8619.71
9.Parapet160.00 No3.8601-01-201731-01-2017160.00 No160.00 No2.323.86
10.Road Furniture15.00 No0.1401-01-201731-01-201715.00 No15.00 No0.080.14
Total Amount: 166.15 100   166.15
Remarks: No Remarks       Work Program Made On: 17-11-2015        Updation of work program on: 19-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-November-20154.49  lakh
2.28-January-20169.20  lakh
3.28-March-20165.97  lakh
4.02-May-20162.55  lakh
5.18-May-20167.94  lakh
6.28-June-201613.43  lakh
7.11-September-20168.71  lakh
8.24-October-201611.92  lakh
9.24-December-201611.05  lakh
10.28-February-20177.47  lakh
11.30-March-201723.67  lakh
12.18-May-201776.15  lakh
13.27-July-20174.42  lakh
Total 186.97  lakh
% Payment102.12 %
Advance Amount:  4.54  lakh        Recovered Amount:  4.54  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 316   No. of Test Done : 349    No. of Test Passed : 334   No. of Test Failed : 15   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 91.08
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 36
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-04-20171.025Premix carpet work rolling processSiddharth RangharJEUDRP R&B Guptkashi See Pic
2.12-04-20172.350 last HP BendPremix Carpet on HP BendSiddharth RangharJEUDRP R&B Guptkashi See Pic
3.09-04-20172.900Premix carpet surface before seal coat work in progressSiddharth RangharJEUDRP R&B Guptkashi See Pic
4.04-04-2017Chainage 3.000Premix carpet work startedSiddharth RangharJEUDRP R&B Guptkashi See Pic
5.27-02-20173.000 end point of roadCompaction of G3 layer dry rollingSiddharth RangharJEUDRP R&B Guptkashi See Pic
6.27-02-20172.600Top coat G3 laying started on jakdhar dewar Motor RoadSiddharth RangharJEUDRP R&B Guptkashi See Pic
7.26-02-20172.325Water sprinkling with tank on G2 jakdhar dewar MRSiddharth RangharJEUDRP R&B Guptkashi See Pic
8.25-02-20172.150Dry rolling of Grading no. 2Siddharth RangharJEUDRP R&B Guptkashi See Pic
9.25-02-20172.175Laying of G2 layer after dry compactionSiddharth RangharJEUDRP R&B Guptkashi See Pic
10.03-02-20172+600Gradation test of G1 layingAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
11.06-01-20170+200Thickness cheking of g3 check by CE sir & EE sirAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
12.06-01-20170+200Site inspection by CE sir &EE sirAnurag Rawat AEAEUDRP R&B Guptkashi See Pic
13.06-01-20171.550Thickness checking G1 G2 jakdhar dewar Cheif Sir visitSiddharth RangharJEUDRP R&B Guptkashi See Pic
14.19-12-20160.375Gradation G2Siddharth RangharJEUDRP R&B Guptkashi See Pic
15.25-04-2016Km 1 ch starting pointPreparation of subgrade for G-1 at junction pointShankar RamEEUDRP R&B Guptkashi See Pic
16.05-02-20161.0001 m span scupper steel reinforcement . preparation of slab castingSiddharth RangharJEDEA WB Guptkashi See Pic
17.12-01-20162+600B/w in progressAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
18.09-01-20160+135Bad block in scupperAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
19.09-01-20160+135Bad block in scupperAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic
20.09-01-20161+000Bad block in scupperAshish DhimanSite SupervisorDSC1 R&B WB Rudraprayag See Pic