Salya-Tulanga MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2519 |
Sanction Cost: |
444.87 lakh |
Length:
|
6.000 KM. |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 148
Package Name: 
UDRP/PWD/03/40/RD/029A(N)
Tender Date: 11-06-2018
Current Status: Agreement signed
Achieved on Date: 28-09-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/RD/029A(N)
Contractor Name: Sky International
|
Start Date: 05-10-2018
Intended Completion Date: 23-06-2019
Original End Date: 04-06-2019 |
Total Bond Cost: 29283453.75 (292.83 lakh)
Variation Cost: 1029306.35 (10.29 lakh) Hence Total Bond Cost is 30312760.1 (303.13 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 6.00 KM | 15.78 | 15-11-2018 | 20-12-2018 | 6.00 KM | 6.00 KM | 5.39 | 15.78 | 2. | R/Wall, B/ Wall Type Protection works | 835.00 m | 52.10 | 20-10-2018 | 30-03-2019 | 889.00 m | 889.00 m | 17.79 | 52.10 | 3. | GSB/RBI/G-1 | 2.10 KM | 17.13 | 10-12-2018 | 20-01-2019 | 1.76 KM | 1.76 KM | 5.85 | 17.13 | 4. | G-2 | 4.70 KM | 27.24 | 20-12-2018 | 10-02-2019 | 4.70 KM | 4.70 KM | 9.3 | 27.24 | 5. | G-3 | 6.00 KM | 35.77 | 15-01-2019 | 15-03-2019 | 6.00 KM | 6.00 KM | 12.22 | 35.77 | 6. | PC/CC i/c Prime Coat, Tack Coat | 6.00 KM | 49.12 | 15-03-2019 | 25-05-2019 | 6.00 KM | 6.00 KM | 16.77 | 49.12 | 7. | Cause Way | 2.00 No | 11.82 | 25-11-2018 | 20-12-2018 | 2.00 No | 2.00 No | 4.04 | 11.82 | 8. | Culverts/Scupper | 11.00 No | 31.60 | 15-11-2018 | 10-02-2019 | 13.00 No | 13.00 No | 10.79 | 31.60 | 9. | longitudinal Drain | 6.00 m | 22.15 | 05-12-2018 | 15-03-2019 | 6.00 m | 6.00 m | 7.56 | 22.15 | 10. | Parapet | 300.00 No | 8.35 | 15-11-2018 | 31-01-2019 | 300.00 No | 300.00 No | 2.85 | 8.35 | 11. | Road Furniture | 428.00 No | 11.00 | 01-02-2019 | 28-02-2019 | 428.00 No | 428.00 No | 3.76 | 11.00 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 10.77 | 15-11-2018 | 15-03-2019 | 1.00 Job | 1.00 Job | 3.68 | 10.77 |
Total Amount: |
292.83 |
|
100 |
292.83 |
|
Remarks:
Work Program Made On:
12-11-2018 } ?>
Updation of work program on:
12-11-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-June-2015 | 21.34 lakh | 2. | 06-August-2015 | 4.96 lakh | 3. | 24-September-2015 | 17.04 lakh | 4. | 28-October-2015 | 15.08 lakh | 5. | 07-December-2015 | 13.40 lakh | 6. | 30-December-2015 | 12.67 lakh | 7. | 28-January-2016 | 10.32 lakh | 8. | 29-February-2016 | 9.46 lakh | 9. | 07-April-2016 | 9.89 lakh | 10. | 25-October-2016 | 5.72 lakh | 11. | 06-March-2017 | 6.10 lakh | 12. | 22-June-2017 | 6.65 lakh | 13. | 15-October-2017 | 17.16 lakh | 14. | 29-May-2018 | 5.95 lakh |
Previous Package Expenditure Total |
155.74 lakh |
SNo. |
Date |
Payment |
1. | 31-December-2018 | 34.40 lakh | 2. | 22-February-2019 | 18.75 lakh | 3. | 04-April-2019 | 45.82 lakh | 4. | 30-April-2019 | 18.34 lakh | 5. | 16-May-2019 | 31.48 lakh | 6. | 01-June-2019 | 50.03 lakh | 7. | 19-June-2019 | 29.43 lakh | 8. | 10-July-2019 | 35.95 lakh | 9. | 30-July-2019 | 25.15 lakh |
Total |
289.35 lakh |
% Payment |
95.46 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 92.82 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 115 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-05-2019 | 4.600 | G3 laying after compaction.. | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
2. | 27-05-2019 | Chainage 4.100 Hp bend | CME Sir and EE Sir visit at Salya Tulangaa motor Road regarding progress. | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
3. | 06-05-2019 | 5+400 | Site visit by CME,EE and AE sir. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
4. | 02-05-2019 | 2.650 | P.c work at Salya Tulangaa motor Road. | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
5. | 07-04-2019 | 0.250 | Soil nail in progress for Hydroseeding work at Km 8 Guptkashi. | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
6. | 02-04-2019 | 2.300 | G3 wbm layed at chainage 2.300. with Stone screening | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
7. | 30-03-2019 | 0.400 | WBM laying in progress with compaction. | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
8. | 29-03-2019 | 5.200 | Exen Sir Visit at PKG no. 29N(A) regarding slow work progress. | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
9. | 29-03-2019 | 6.000 | Exen sir visit at Salya Tulangaa Motor Road Guptkashi division regarding slow work progress.of pkg29N(A) | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
10. | 02-03-2019 | 2.300 | G2 laying started on chainage 2.300 Salya Tulangaa Motor Road | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
11. | 28-02-2019 | 4.800 | SE sir visit at Salya Tulangaa Motor Road Pkg 29 N(A). | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
12. | 08-02-2019 | 1.275 | Wirecrates wall in progress at chainage 1.275 | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
13. | 08-02-2019 | 3.300 | Stone ballast breaking at chainage 3.300 | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
14. | 31-01-2019 | 3.200 | Stone Ballast breaking at chainage 3.200 | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
15. | 15-01-2019 | 0.975 | Coolie wall construction under process in km 1 | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
16. | 15-01-2019 | 1.200 | Stone collection for Wbm ballast . | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
17. | 09-01-2019 | 1.500 | Coolie wall construction in progress. | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
18. | 09-01-2019 | 1.400 | Hp bend improvement at chainage 1.400 | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
19. | 09-01-2019 | 1.250 | Parapet casting in progress. | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
20. | 07-01-2019 | 1.100 | Hard Rock cutting by Rock Breaker. | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
|
|