Nagjagai-Fagu MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2517 |
Sanction Cost: |
238.02 lakh |
Length:
|
4.000 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Kedarnath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 28
Package Name: 
UDRP/PWD/03/40/RD/028
Tender Date: 14-08-2014
Current Status: Agreement signed
Achieved on Date: 20-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/RD/028
Contractor Name: Sanjay Singh Negi
|
Start Date: 27-02-2015
Intended Completion Date: 30-12-2017
Original End Date: 26-05-2016 |
Total Bond Cost: 18180409.46 (181.8 lakh)
Variation Cost: 4321592.24 (43.22 lakh) Hence Total Bond Cost is 22502001.7 (225.02 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 1736190 for 191 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 550.00 m | 11.85 | 25-06-2015 | 31-08-2016 | 550.00 m | 550.00 m | 7.18 | 11.85 | 2. | GSB/RBI/G-1 | 3.30 KM | 19.93 | 25-05-2015 | 29-02-2016 | 3.30 KM | 3.30 KM | 12.07 | 19.93 | 3. | G-2 | 3.30 KM | 15.89 | 25-06-2015 | 15-03-2016 | 3.30 KM | 3.30 KM | 9.63 | 15.89 | 4. | G-3 | 3.30 KM | 23.40 | 25-07-2015 | 30-04-2016 | 3.30 KM | 3.30 KM | 14.17 | 23.40 | 5. | PC/CC i/c Prime Coat, Tack Coat | 3.30 KM | 30.53 | 15-03-2017 | 30-11-2017 | 3.30 KM | 3.30 KM | 18.49 | 30.53 | 6. | Culverts/Scupper | 8.00 No | 8.86 | 15-05-2015 | 31-12-2016 | 8.00 No | 8.00 No | 5.37 | 8.86 | 7. | longitudinal Drain | 3880.00 m | 7.04 | 15-03-2016 | 30-11-2017 | 3880.00 m | 3880.00 m | 4.26 | 7.04 | 8. | Crash Barrier | 2119.00 m | 38.35 | 17-08-2017 | 15-12-2017 | 2119.00 m | 2119.00 m | 23.23 | 38.35 | 9. | Parapet | 261.00 No | 7.98 | 16-08-2017 | 30-12-2017 | 261.00 No | 261.00 No | 4.83 | 7.98 | 10. | Road Furniture | 20.00 No | 1.26 | 15-12-2017 | 30-12-2017 | 20.00 No | 20.00 No | 0.76 | 1.26 |
Total Amount: |
165.09 |
|
100 |
165.09 |
|
Remarks:
Lab not established
Work Program Made On:
28-09-2015 } ?>
Updation of work program on:
24-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-March-2015 | 3.68 lakh | 2. | 31-March-2015 | 9.30 lakh | 3. | 13-June-2015 | 8.35 lakh | 4. | 24-June-2015 | 14.98 lakh | 5. | 31-October-2015 | 2.44 lakh | 6. | 26-December-2015 | 7.11 lakh | 7. | 10-March-2016 | 17.39 lakh | 8. | 02-May-2016 | 16.10 lakh | 9. | 02-June-2016 | 5.57 lakh | 10. | 21-September-2016 | 11.87 lakh | 11. | 26-October-2016 | 4.33 lakh | 12. | 31-July-2017 | 4.21 lakh | 13. | 15-October-2017 | 43.12 lakh | 14. | 18-November-2017 | 24.03 lakh | 15. | 22-December-2017 | 26.34 lakh | 16. | 23-March-2018 | 25.16 lakh |
Total |
223.98 lakh |
% Payment |
99.54 % |
|
Advance Amount: 44.36 lakh
Recovered Amount: 44.36 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 270 No. of Test Done : 306 No. of Test Passed : 285 No. of Test Failed : 21 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 81.61 |
Number of Notice(s) issued: 116 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 55 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-07-2018 | Km 5.00 salya-Tulanga motor road | Road opened for traffic | Ravi Bisht | JE | UDRP R&B Guptkashi | See Pic |
2. | 22-07-2018 | Km 5.00 salya tulanga motor road | Road cleaning in progress | Ravi Bisht | JE | UDRP R&B Guptkashi | See Pic |
3. | 22-07-2018 | Km 5.00 salya-tulanga motor marg | Road blocked due to slip | Ravi Bisht | JE | UDRP R&B Guptkashi | See Pic |
4. | 22-07-2018 | Km 3.00 salya- tulanga motor road | Road opened for traffic | Ravi Bisht | JE | UDRP R&B Guptkashi | See Pic |
5. | 22-07-2018 | Km 3.00 salya-tulanga motor road | Road blocked due to landslide | Ravi Bisht | JE | UDRP R&B Guptkashi | See Pic |
6. | 22-07-2018 | Km 3.000 | Road opening is in progress | Ravi Bisht | JE | UDRP R&B Guptkashi | See Pic |
7. | 19-07-2018 | 3.025 | SRMD JCB machine which was dumped in debris is taken out safely today by poclain ... road is open for communication today all vehicles are passed from km 3.00 safely. | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
8. | 19-01-2018 | 1.800 | Patch repair over PC . | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
9. | 22-11-2017 | 0+100 | Rolling on pc surface | Bhagwat Singh Bangari | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
10. | 16-11-2017 | 1+420 | Rolling over pc surface | Deepak Prasad | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
11. | 08-11-2017 | 1+010 | EE sir site visit ,seal coat laying | Bhagwat Singh Bangari | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
12. | 03-11-2017 | 0+890 | Seal coat rolling under process chainage ... 0+890 Nagjagai Fegu | Bhagwat Singh Bangari | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
13. | 31-10-2017 | 1+890 | Laying seal coat | Bhagwat Singh Bangari | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
14. | 27-10-2017 | 3.470 | Protection work by Retaining wall | Nandan Rawat | JE | UDRP R&B Guptkashi | See Pic |
15. | 26-10-2017 | 2.340 | Seal coat after Premix Carpet | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
16. | 24-10-2017 | 2.870 | Premix carpet work on progress rolling over seal coat. | Nandan Rawat | JE | UDRP R&B Guptkashi | See Pic |
17. | 23-10-2017 | 2.920 | Premix carpet work laying in progress Nagjagai fegu Motor Road | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
18. | 22-10-2017 | 2+750 | Nagjaigu fegu m/r Rolling of PC | Nandan Rawat | JE | UDRP R&B Guptkashi | See Pic |
19. | 11-10-2017 | 3+470 | Ee sir discussion to contractor about progress and work programe | Bhagwat Singh Bangari | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
20. | 10-10-2017 | 3+110 | Laying of pc work on progress | Bhagwat Singh Bangari | Site Supervisor | DSC4 R&B WB Rudraprayag | See Pic |
|
|