Chhenagad Uchola Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2513 |
Sanction Cost: |
412.54 lakh |
Length:
|
5.000 KM. |
District: |
Rudraprayag |
Block: |
Jakholi |
Constituency: |
Rudraprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 149
Package Name: 
UDRP/PWD/03/40/RD/029B(N)
Tender Date: 11-06-2018
Current Status: Agreement signed
Achieved on Date: 24-08-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/RD/029B(N)
Contractor Name: Sky International
|
Start Date: 05-10-2018
Intended Completion Date: 25-06-2019
Original End Date: 04-06-2019 |
Total Bond Cost: 25776742 (257.77 lakh)
Variation Cost: 4346209.89 (43.46 lakh) Hence Total Bond Cost is 30122951.89 (301.23 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 5.00 KM | 15.52 | 05-10-2018 | 10-12-2018 | 5.00 KM | 5.00 KM | 6.02 | 15.52 | 2. | R/Wall, B/ Wall Type Protection works | 909.00 m | 50.84 | 20-10-2018 | 20-02-2019 | 909.00 m | 909.00 m | 19.72 | 50.84 | 3. | GSB/RBI/G-1 | 1.60 KM | 10.87 | 01-01-2019 | 25-01-2019 | 1.60 KM | 1.60 KM | 4.22 | 10.87 | 4. | G-2 | 1.60 KM | 9.80 | 26-01-2019 | 15-02-2019 | 1.60 KM | 1.60 KM | 3.8 | 9.80 | 5. | G-3 | 2.20 KM | 15.69 | 16-02-2019 | 15-03-2019 | 2.20 KM | 2.20 KM | 6.09 | 15.69 | 6. | PC/CC i/c Prime Coat, Tack Coat | 4.00 KM | 36.28 | 16-03-2019 | 15-05-2019 | 4.00 KM | 4.00 KM | 14.08 | 36.28 | 7. | Cause Way | 5.00 No | 16.57 | 25-11-2018 | 15-03-2019 | 5.00 No | 5.00 No | 6.43 | 16.57 | 8. | Culverts/Scupper | 8.00 No | 21.96 | 05-10-2018 | 15-03-2019 | 8.00 No | 8.00 No | 8.52 | 21.96 | 9. | longitudinal Drain | 5000.00 m | 34.29 | 30-11-2018 | 10-03-2019 | 5000.00 m | 5000.00 m | 13.3 | 34.29 | 10. | Crash Barrier | 500.00 m | 20.00 | 15-12-2018 | 10-05-2019 | 500.00 m | 500.00 m | 7.76 | 20.00 | 11. | Parapet | 300.00 No | 8.04 | 15-12-2018 | 10-05-2019 | 300.00 No | 300.00 No | 3.12 | 8.04 | 12. | Road Furniture | 324.00 No | 6.44 | 03-01-2019 | 30-05-2019 | 324.00 No | 324.00 No | 2.5 | 6.44 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 11.47 | 01-01-2019 | 04-06-2019 | 1.00 Job | 1.00 Job | 4.45 | 11.47 |
Total Amount: |
257.77 |
|
100 |
257.77 |
|
Remarks:
No Remarks
Work Program Made On:
17-11-2018 } ?>
Updation of work program on:
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-June-2015 | 19.85 lakh | 2. | 06-August-2015 | 20.46 lakh | 3. | 24-September-2015 | 10.36 lakh | 4. | 28-October-2015 | 8.63 lakh | 5. | 30-December-2015 | 16.35 lakh | 6. | 28-January-2016 | 5.37 lakh | 7. | 17-February-2016 | 21.06 lakh | 8. | 29-February-2016 | 21.87 lakh | 9. | 02-May-2016 | 5.63 lakh | 10. | 29-June-2016 | 7.50 lakh | 11. | 25-October-2016 | 11.56 lakh | 12. | 06-March-2017 | 5.85 lakh | 13. | 22-June-2017 | 6.89 lakh | 14. | 15-October-2017 | 17.70 lakh | 15. | 29-May-2018 | 42.06 lakh |
Previous Package Expenditure Total |
221.14 lakh |
SNo. |
Date |
Payment |
1. | 31-December-2018 | 33.42 lakh | 2. | 22-February-2019 | 23.04 lakh | 3. | 04-April-2019 | 17.08 lakh | 4. | 30-April-2019 | 33.33 lakh | 5. | 16-May-2019 | 15.44 lakh | 6. | 31-May-2019 | 21.23 lakh | 7. | 25-June-2019 | 40.35 lakh | 8. | 30-July-2019 | 50.59 lakh |
Total |
234.48 lakh |
% Payment |
77.84 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 86.56 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 114 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 14-08-2019 | 1+850 | SRMD debris falled | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
2. | 24-06-2019 | 0.475 | Thickness checking AE Sir ... Chenagad Uchhola Motor Road PKG 29 N(A). | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
3. | 06-05-2019 | 4+980 | Surface cleaning work | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
4. | 06-05-2019 | 4+400 | PC work in progress | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
5. | 06-05-2019 | 2+100 | Site visit by CME sir and EE sir. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
6. | 06-05-2019 | 1+000 | Slip clearance work. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
7. | 02-04-2019 | 4+800 | Surface cleaning work in progress. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
8. | 02-04-2019 | 1+350 | Reconstruction of dismental R/Wall. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
9. | 02-04-2019 | 0+850 | Stone collection work for WBM G-1. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
10. | 02-04-2019 | 0+750 | ?sign board | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
11. | 02-04-2019 | 4+850 | Excavation for B/Wall | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
12. | 02-04-2019 | 3+900 | Catch pit work for scupper. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
13. | 02-04-2019 | 4+850 | SE, and EE sir visit. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
14. | 02-04-2019 | 1+325 | SE sir site visit. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
15. | 29-03-2019 | 4.950 | DPM sir inspection. in Chenagad Uchhola Motor Road Pkg 29 NB. | Siddharth Ranghar | JE | UDRP R&B Guptkashi | See Pic |
16. | 27-02-2019 | 5+000 | Site inspection by SE and EE sir . | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
17. | 27-02-2019 | 1+700 | Wing wall and scupper work | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
18. | 27-02-2019 | 1+700 | Scupper work at ch 1+700 | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
19. | 15-02-2019 | 1+900 | DLC M10 for causeway | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
20. | 31-01-2019 | Lab | WBM G3 grading test. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
|
|