Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Chhenagad Uchola Motor Road Work Completed
Project: UDRP-RB UID: 2513 Sanction Cost: 412.54  lakh Length: 5.000 KM.
District: Rudraprayag Block: Jakholi Constituency: Rudraprayag Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 149        Package Name:  UDRP/PWD/03/40/RD/029B(N)        Tender Date: 11-06-2018        Current Status: Agreement signed        Achieved on Date: 24-08-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/40/RD/029B(N)      Contractor Name: Sky International
Start Date:  05-10-2018      Intended Completion Date:  25-06-2019      Original End Date:  04-06-2019
Total Bond Cost: 25776742 (257.77 lakh)        Variation Cost: 4346209.89 (43.46 lakh)    Hence Total Bond Cost is   30122951.89 (301.23 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence5.00 KM15.5205-10-201810-12-20185.00 KM5.00 KM6.0215.52
2.R/Wall, B/ Wall Type Protection works909.00 m50.8420-10-201820-02-2019909.00 m909.00 m19.7250.84
3.GSB/RBI/G-11.60 KM10.8701-01-201925-01-20191.60 KM1.60 KM4.2210.87
4.G-21.60 KM9.8026-01-201915-02-20191.60 KM1.60 KM3.89.80
5.G-32.20 KM15.6916-02-201915-03-20192.20 KM2.20 KM6.0915.69
6.PC/CC i/c Prime Coat, Tack Coat4.00 KM36.2816-03-201915-05-20194.00 KM4.00 KM14.0836.28
7.Cause Way5.00 No16.5725-11-201815-03-20195.00 No5.00 No6.4316.57
8.Culverts/Scupper 8.00 No21.9605-10-201815-03-20198.00 No8.00 No8.5221.96
9.longitudinal Drain5000.00 m34.2930-11-201810-03-20195000.00 m5000.00 m13.334.29
10.Crash Barrier500.00 m20.0015-12-201810-05-2019500.00 m500.00 m7.7620.00
11.Parapet300.00 No8.0415-12-201810-05-2019300.00 No300.00 No3.128.04
12.Road Furniture324.00 No6.4403-01-201930-05-2019324.00 No324.00 No2.56.44
13.Other Allied Works & Finishing Work 1.00 Job11.4701-01-201904-06-20191.00 Job1.00 Job4.4511.47
Total Amount: 257.77 100   257.77
Remarks: No Remarks       Work Program Made On: 17-11-2018        Updation of work program on:       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.13-June-201519.85  lakh
2.06-August-201520.46  lakh
3.24-September-201510.36  lakh
4.28-October-20158.63  lakh
5.30-December-201516.35  lakh
6.28-January-20165.37  lakh
7.17-February-201621.06  lakh
8.29-February-201621.87  lakh
9.02-May-20165.63  lakh
10.29-June-20167.50  lakh
11.25-October-201611.56  lakh
12.06-March-20175.85  lakh
13.22-June-20176.89  lakh
14.15-October-201717.70  lakh
15.29-May-201842.06  lakh
Previous Package Expenditure Total 221.14  lakh
SNo. Date Payment
1.31-December-201833.42  lakh
2.22-February-201923.04  lakh
3.04-April-201917.08  lakh
4.30-April-201933.33  lakh
5.16-May-201915.44  lakh
6.31-May-201921.23  lakh
7.25-June-201940.35  lakh
8.30-July-201950.59  lakh
Total 234.48  lakh
% Payment 77.84 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 86.56
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 114
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.14-08-20191+850SRMD debris falledAnurag DevJEUDRP R&B Guptkashi See Pic
2.24-06-20190.475Thickness checking AE Sir ... Chenagad Uchhola Motor Road PKG 29 N(A).Siddharth RangharJEUDRP R&B Guptkashi See Pic
3.06-05-20194+980Surface cleaning workAnurag DevJEUDRP R&B Guptkashi See Pic
4.06-05-20194+400PC work in progressAnurag DevJEUDRP R&B Guptkashi See Pic
5.06-05-20192+100Site visit by CME sir and EE sir.Anurag DevJEUDRP R&B Guptkashi See Pic
6.06-05-20191+000Slip clearance work.Anurag DevJEUDRP R&B Guptkashi See Pic
7.02-04-20194+800Surface cleaning work in progress.Anurag DevJEUDRP R&B Guptkashi See Pic
8.02-04-20191+350Reconstruction of dismental R/Wall.Anurag DevJEUDRP R&B Guptkashi See Pic
9.02-04-20190+850Stone collection work for WBM G-1.Anurag DevJEUDRP R&B Guptkashi See Pic
10.02-04-20190+750?sign boardAnurag DevJEUDRP R&B Guptkashi See Pic
11.02-04-20194+850Excavation for B/WallAnurag DevJEUDRP R&B Guptkashi See Pic
12.02-04-20193+900Catch pit work for scupper.Anurag DevJEUDRP R&B Guptkashi See Pic
13.02-04-20194+850SE, and EE sir visit.Anurag DevJEUDRP R&B Guptkashi See Pic
14.02-04-20191+325SE sir site visit.Anurag DevJEUDRP R&B Guptkashi See Pic
15.29-03-20194.950DPM sir inspection. in Chenagad Uchhola Motor Road Pkg 29 NB.Siddharth RangharJEUDRP R&B Guptkashi See Pic
16.27-02-20195+000Site inspection by SE and EE sir .Anurag DevJEUDRP R&B Guptkashi See Pic
17.27-02-20191+700Wing wall and scupper workAnurag DevJEUDRP R&B Guptkashi See Pic
18.27-02-20191+700Scupper work at ch 1+700Anurag DevJEUDRP R&B Guptkashi See Pic
19.15-02-20191+900DLC M10 for causewayAnurag DevJEUDRP R&B Guptkashi See Pic
20.31-01-2019LabWBM G3 grading test.Anurag DevJEUDRP R&B Guptkashi See Pic