jaakh meladungari
Work Completed
|
Project: |
UDRP-RB |
UID: |
2419 |
Sanction Cost: |
337.28 lakh |
Length:
|
7.000 KM. |
District: |
Pithoragarh |
Block: |
Pithoragarh(Bin) |
Constituency: |
Pithoragarh |
Circle: |
|
DEA: |
DEA Askot |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 104
Package Name: 
UDRP/PWD/07/15/RD/093
Tender Date: 18-02-2015
Current Status: Agreement signed
Achieved on Date: 01-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/15/RD/093
Contractor Name: M & P Infrastructure
|
Start Date: 08-07-2015
Intended Completion Date: 01-11-2018
Original End Date: 07-10-2016 |
Total Bond Cost: 66856998.32 (668.57 lakh)
Variation Cost: 3385916.26 (33.86 lakh) Hence Total Bond Cost is 70242914.58 (702.43 lakh)
|
Sub Project Cost: 337.28 lakh
Variation Cost of Sub Project: -1249210.15 (-12.49 lakh)
Total Sub Project Cost:
324.79 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 3409656 for 102 days
LD Analysis for Milestone2: calculated LD is Rs 8390428 for 251 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.57 KM | 30.35 | 15-04-2016 | 31-10-2016 | 2.57 KM | 2.57 KM | 8.17 | 30.35 | 2. | R/Wall, B/ Wall Type Protection works | 939.60 m | 98.56 | 20-08-2015 | 15-11-2017 | 906.00 m | 906.00 m | 26.53 | 98.56 | 3. | G-2 | 1.60 KM | 37.92 | 01-03-2017 | 15-09-2017 | 0.30 KM | 0.30 KM | 10.21 | 37.92 | 4. | G-3 | 6.50 KM | 47.26 | 10-02-2017 | 30-09-2017 | 6.50 KM | 6.50 KM | 12.72 | 47.26 | 5. | PC/CC i/c Prime Coat, Tack Coat | 6.50 KM | 102.21 | 05-04-2017 | 30-11-2017 | 6.50 KM | 6.50 KM | 27.51 | 102.21 | 6. | Cause Way | 0.00 No | 0.00 | 01-09-2017 | 15-10-2017 | 0.00 No | 0.00 No | 0 | 0.00 | 7. | Culverts/Scupper | 9.00 No | 17.27 | 01-12-2015 | 30-09-2017 | 7.00 No | 7.00 No | 4.65 | 17.27 | 8. | longitudinal Drain | 6186.80 m | 9.48 | 15-01-2017 | 15-10-2017 | 6186.80 m | 6186.80 m | 2.55 | 9.48 | 9. | Crash Barrier | 300.00 m | 17.92 | 01-11-2017 | 15-11-2017 | 1400.00 m | 1400.00 m | 4.82 | 17.92 | 10. | Parapet | 200.00 No | 3.10 | 16-10-2017 | 15-11-2017 | 72.00 No | 72.00 No | 0.84 | 3.10 | 11. | Road Furniture | 116.00 No | 7.47 | 01-05-2016 | 30-11-2017 | 116.00 No | 116.00 No | 2.01 | 7.47 |
Total Amount: |
371.54 |
|
100 |
371.54 |
|
Remarks:
No Remarks
Work Program Made On:
04-10-2015 } ?>
Updation of work program on:
16-05-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-October-2015 | 7.09 lakh | 2. | 23-December-2015 | 8.94 lakh | 3. | 12-April-2016 | 8.19 lakh | 4. | 13-May-2016 | 5.24 lakh | 5. | 20-July-2016 | 18.63 lakh | 6. | 03-September-2016 | 6.45 lakh | 7. | 27-October-2016 | 6.68 lakh | 8. | 05-December-2016 | 9.60 lakh | 9. | 19-December-2016 | 6.29 lakh | 10. | 31-December-2016 | 1.05 lakh | 11. | 31-January-2017 | 3.34 lakh | 12. | 28-February-2017 | 5.08 lakh | 13. | 31-March-2017 | 5.31 lakh | 14. | 31-May-2017 | 8.97 lakh | 15. | 18-June-2017 | 22.35 lakh | 16. | 11-July-2017 | 20.32 lakh | 17. | 25-August-2017 | 13.99 lakh | 18. | 25-October-2017 | 6.85 lakh | 19. | 03-November-2017 | 12.58 lakh | 20. | 17-November-2017 | 20.72 lakh | 21. | 26-November-2017 | 26.04 lakh | 22. | 30-November-2017 | 18.19 lakh | 23. | 16-February-2018 | 35.64 lakh | 24. | 07-March-2018 | 12.96 lakh | 25. | 31-May-2018 | 17.82 lakh | 26. | 23-August-2018 | 13.77 lakh | 27. | 01-November-2018 | 4.00 lakh | 28. | 09-March-2019 | 4.67 lakh |
Total |
330.76 lakh |
% Payment | 101.84 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 589 No. of Test Done : 598 No. of Test Passed : 596 No. of Test Failed : 2 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 83.78 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 56 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 16-03-2018 | 4+850 | Rolling work progress in PC work | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
2. | 15-03-2018 | Chainage 3+575 | PC & WBM G-3 sample collection for third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
3. | 15-03-2018 | Chainage 09+475 | WBM G-3 sample collection for third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
4. | 01-12-2017 | 0+400 | Labour Health checkup | Harish Singh Rajwar | JE | UDRP R&B Askot | See Pic |
5. | 01-12-2017 | HMP | Bitumen content of seal coat material Testing at HMP. Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
6. | 30-11-2017 | HMP | Bitumen content of PC material Testing at HMP | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
7. | 28-11-2017 | Plant site | Preparing PC material by plant | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
8. | 28-11-2017 | Plant site | Checking of bitumen content of PC material | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
9. | 28-11-2017 | Plant site | Finding bitumen content | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
10. | 28-11-2017 | Ch.0+650 | Rolling of PC Laying | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
11. | 26-11-2017 | HMP | Bitumen content of PC material Testing at HMP. Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
12. | 26-11-2017 | HMP | Bitumen content of PC material Testing at HMP | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
13. | 26-11-2017 | Ch1+400 | Rolling of PC Laying | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
14. | 09-11-2017 | Ch.0+050 | R/wall | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
15. | 09-11-2017 | Ch.4+975 | W.B.M.Top Surface cleaning for P.C.work | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
16. | 09-11-2017 | Ch-6+200 | Construction of culvert Abutment. | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
17. | 22-08-2017 | Ch.0+075 | Compliance pic remarks of pic id 29567 | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
18. | 03-08-2017 | 0+075 | RR dry stone masonry in Retaining Wall. | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
19. | 07-04-2017 | Laboratory | AIV Test of course aggregate for concrete work | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
20. | 09-03-2017 | Ch 3.250 | Checking road width by SE sir | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
|
|