Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

jaakh meladungari Work Completed
Project: UDRP-RB UID: 2419 Sanction Cost: 337.28  lakh Length: 7.000 KM.
District: Pithoragarh Block: Pithoragarh(Bin) Constituency: Pithoragarh Circle:
DEA: DEA Askot DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 104        Package Name:  UDRP/PWD/07/15/RD/093        Tender Date: 18-02-2015        Current Status: Agreement signed        Achieved on Date: 01-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/15/RD/093      Contractor Name: M & P Infrastructure
Start Date:  08-07-2015      Intended Completion Date:  01-11-2018      Original End Date:  07-10-2016
Total Bond Cost: 66856998.32 (668.57 lakh)        Variation Cost: 3385916.26 (33.86 lakh)    Hence Total Bond Cost is   70242914.58 (702.43 lakh) 
Sub Project Cost: 337.28  lakh        Variation Cost of Sub Project: -1249210.15  (-12.49 lakh)       Total Sub Project Cost:   324.79 lakh
LD Analysis for Milestone1: calculated LD is Rs 3409656 for 102 days        LD Analysis for Milestone2: calculated LD is Rs 8390428 for 251 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.57 KM30.3515-04-201631-10-20162.57 KM2.57 KM8.1730.35
2.R/Wall, B/ Wall Type Protection works939.60 m98.5620-08-201515-11-2017906.00 m906.00 m26.5398.56
3.G-21.60 KM37.9201-03-201715-09-20170.30 KM0.30 KM10.2137.92
4.G-36.50 KM47.2610-02-201730-09-20176.50 KM6.50 KM12.7247.26
5.PC/CC i/c Prime Coat, Tack Coat6.50 KM102.2105-04-201730-11-20176.50 KM6.50 KM27.51102.21
6.Cause Way0.00 No0.0001-09-201715-10-20170.00 No0.00 No00.00
7.Culverts/Scupper 9.00 No17.2701-12-201530-09-20177.00 No7.00 No4.6517.27
8.longitudinal Drain6186.80 m9.4815-01-201715-10-20176186.80 m6186.80 m2.559.48
9.Crash Barrier300.00 m17.9201-11-201715-11-20171400.00 m1400.00 m4.8217.92
10.Parapet200.00 No3.1016-10-201715-11-201772.00 No72.00 No0.843.10
11.Road Furniture116.00 No7.4701-05-201630-11-2017116.00 No116.00 No2.017.47
Total Amount: 371.54 100   371.54
Remarks: No Remarks       Work Program Made On: 04-10-2015        Updation of work program on: 16-05-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-October-20157.09  lakh
2.23-December-20158.94  lakh
3.12-April-20168.19  lakh
4.13-May-20165.24  lakh
5.20-July-201618.63  lakh
6.03-September-20166.45  lakh
7.27-October-20166.68  lakh
8.05-December-20169.60  lakh
9.19-December-20166.29  lakh
10.31-December-20161.05  lakh
11.31-January-20173.34  lakh
12.28-February-20175.08  lakh
13.31-March-20175.31  lakh
14.31-May-20178.97  lakh
15.18-June-201722.35  lakh
16.11-July-201720.32  lakh
17.25-August-201713.99  lakh
18.25-October-20176.85  lakh
19.03-November-201712.58  lakh
20.17-November-201720.72  lakh
21.26-November-201726.04  lakh
22.30-November-201718.19  lakh
23.16-February-201835.64  lakh
24.07-March-201812.96  lakh
25.31-May-201817.82  lakh
26.23-August-201813.77  lakh
27.01-November-20184.00  lakh
28.09-March-20194.67  lakh
Total 330.76  lakh
% Payment101.84 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 589   No. of Test Done : 598    No. of Test Passed : 596   No. of Test Failed : 2   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 83.78
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 56
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.16-03-20184+850Rolling work progress in PC workTej Singh KunwarJEUDRP R&B Askot See Pic
2.15-03-2018Chainage 3+575PC & WBM G-3 sample collection for third party testTej Singh KunwarJEUDRP R&B Askot See Pic
3.15-03-2018Chainage 09+475WBM G-3 sample collection for third party testTej Singh KunwarJEUDRP R&B Askot See Pic
4.01-12-20170+400Labour Health checkupHarish Singh RajwarJEUDRP R&B Askot See Pic
5.01-12-2017HMPBitumen content of seal coat material Testing at HMP. Found OKAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
6.30-11-2017HMPBitumen content of PC material Testing at HMPAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
7.28-11-2017Plant sitePreparing PC material by plantSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
8.28-11-2017Plant siteChecking of bitumen content of PC materialSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
9.28-11-2017Plant siteFinding bitumen contentSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
10.28-11-2017Ch.0+650Rolling of PC LayingAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
11.26-11-2017HMPBitumen content of PC material Testing at HMP. Found OKAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
12.26-11-2017HMPBitumen content of PC material Testing at HMPAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
13.26-11-2017Ch1+400Rolling of PC LayingAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
14.09-11-2017Ch.0+050R/wallTej Singh KunwarJEUDRP R&B Askot See Pic
15.09-11-2017Ch.4+975W.B.M.Top Surface cleaning for P.C.workTej Singh KunwarJEUDRP R&B Askot See Pic
16.09-11-2017Ch-6+200Construction of culvert Abutment.Tej Singh KunwarJEUDRP R&B Askot See Pic
17.22-08-2017Ch.0+075Compliance pic remarks of pic id 29567Abid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
18.03-08-20170+075RR dry stone masonry in Retaining Wall.Manoj BhattREDSC2 R&B WB Pauri See Pic
19.07-04-2017LaboratoryAIV Test of course aggregate for concrete workAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
20.09-03-2017Ch 3.250Checking road width by SE sirSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic