Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ogla Pathak Gaon narath-Bhagichauri MR Work Completed
Project: UDRP-RB UID: 2398 Sanction Cost: 537.79  lakh Length: 12.500 KM.
District: Pithoragarh Block: Kanali Chhina Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Askot DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 36        Package Name:  UDRP/PWD/07/17/RD/036        Tender Date: 14-08-2014        Current Status: Agreement signed        Achieved on Date: 09-12-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/17/RD/036      Contractor Name: Chandri Chand (JV with Pipaliya Engineering &
Start Date:  16-12-2014      Intended Completion Date:  20-02-2018      Original End Date:  15-03-2016
Total Bond Cost: 49911203 (499.11 lakh)        Variation Cost: 12752896.39 (127.53 lakh)    Hence Total Bond Cost is   62664099.39 (626.64 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 6962724 for 279 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.81 KM27.3916-12-201420-04-20151.81 KM1.81 KM3.7227.39
2.R/Wall, B/ Wall Type Protection works1842.00 m162.5617-12-201415-01-20182002.00 m2002.00 m22.05162.56
3.GSB/RBI/G-18.88 KM83.6817-12-201430-11-20178.88 KM8.88 KM11.3583.68
4.G-29.70 KM43.1718-12-201402-12-20179.70 KM9.70 KM5.8643.17
5.G-312.50 KM84.4125-04-201505-12-201710.50 KM10.50 KM11.4584.41
6.PC/CC i/c Prime Coat, Tack Coat12.50 KM139.8924-05-201520-01-201812.20 KM12.20 KM18.98139.89
7.Cause Way27.00 No62.1325-11-201515-01-201827.00 No27.00 No8.4362.13
8.Culverts/Scupper 28.00 No95.7709-01-201515-01-201826.00 No26.00 No12.9995.77
9.longitudinal Drain12325.00 m19.4715-04-201531-12-201711840.00 m11840.00 m2.6419.47
10.Crash Barrier0.00 m0.0001-01-201825-01-20180.00 m0.00 m00.00
11.Parapet240.00 No10.5301-01-201625-01-2018450.00 No450.00 No1.4310.53
12.Road Furniture171.00 No3.3015-03-201531-01-2018171.00 No171.00 No0.453.30
13.Other Allied Works & Finishing Work 1.00 Job4.8110-06-201731-01-20181.00 Job1.00 Job0.654.81
Total Amount: 737.11 100   737.11
Remarks: No Remarks       Work Program Made On: 04-10-2015        Updation of work program on: 16-05-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.09-March-201543.96  lakh
2.27-March-201550.00  lakh
3.11-June-201517.04  lakh
4.10-September-201514.60  lakh
5.14-October-20156.14  lakh
6.07-November-201511.86  lakh
7.28-January-201612.09  lakh
8.29-February-201621.61  lakh
9.30-March-201617.36  lakh
10.11-May-201625.91  lakh
11.22-June-201615.39  lakh
12.06-October-201610.72  lakh
13.29-November-201611.70  lakh
14.31-December-201614.18  lakh
15.31-January-201718.62  lakh
16.28-February-201730.47  lakh
17.07-March-201714.76  lakh
18.31-March-201730.38  lakh
19.19-April-201731.87  lakh
20.31-May-20174.62  lakh
21.05-July-201720.27  lakh
22.26-July-201715.72  lakh
23.21-August-201712.63  lakh
24.18-September-201712.84  lakh
25.01-November-201728.46  lakh
26.09-November-201714.34  lakh
27.26-November-201712.36  lakh
28.22-December-201720.99  lakh
29.11-January-201816.63  lakh
30.24-January-201814.54  lakh
31.16-February-201817.58  lakh
32.26-February-201826.25  lakh
33.28-March-20187.76  lakh
34.25-October-20183.00  lakh
35.30-October-20189.00  lakh
36.18-June-20190.22  lakh
Total 635.87  lakh
% Payment 101.5 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1048   No. of Test Done : 1069    No. of Test Passed : 1053   No. of Test Failed : 16   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.00
Number of Notice(s) issued: 90

Mobile Pic Upload

Number of Pics Available on Web Repository: 135
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.17-05-20180+300Laying seal coatHarish Singh RajwarJEUDRP R&B Askot See Pic
2.14-03-20187+880Collecting PC & WBM sample for third party testBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
3.14-03-201812+150Collecting PC sample for third party testBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
4.14-03-201811+825Collecting PC sample for third party testBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
5.14-03-201810+500Collecting PC sample for third party testBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
6.14-03-20189+400Collecting PC sample for third party testBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
7.14-03-20188+550Collecting PC & WBM G3 sample for third party testBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
8.14-03-20187+850Collecting PC sample for third party testBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
9.14-03-20186+725Collecting PC sample for third party testBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
10.14-03-20185+400Collecting PC sample for third party testBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
11.14-03-20184+500Collecting PC sample for third partyBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
12.14-03-20183+100Collecting PC sample for third party testBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
13.14-03-20182+500Collecting PC sample for third party testBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
14.14-03-20181+700Collecting. WBM & PC sample for third party test.Baldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
15.14-03-20180+075Collecting PC sample for third party testBaldev AryaSite SupervisorDSC4 R&B WB Pithoragarh See Pic
16.09-12-2017Ch. 4+775Rolling of PC LayingAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
17.19-11-20174+625Box culvert slab castingHarish Singh RajwarJEUDRP R&B Askot See Pic
18.15-11-20174775Checking GSB thickness. Thickness found less than required. Instructed to increase it.Arun Kumar PandeyEEUDRP R&B Askot See Pic
19.05-11-2017Ch. 7+390Laying of Seal Coat materialAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
20.05-11-2017Ch.7+475Rolling of PC LayingAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic