Ogla Pathak Gaon narath-Bhagichauri MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2398 |
Sanction Cost: |
537.79 lakh |
Length:
|
12.500 KM. |
District: |
Pithoragarh |
Block: |
Kanali Chhina |
Constituency: |
Didihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Askot |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 36
Package Name: 
UDRP/PWD/07/17/RD/036
Tender Date: 14-08-2014
Current Status: Agreement signed
Achieved on Date: 09-12-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/17/RD/036
Contractor Name: Chandri Chand (JV with Pipaliya Engineering &
|
Start Date: 16-12-2014
Intended Completion Date: 20-02-2018
Original End Date: 15-03-2016 |
Total Bond Cost: 49911203 (499.11 lakh)
Variation Cost: 12752896.39 (127.53 lakh) Hence Total Bond Cost is 62664099.39 (626.64 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 6962724 for 279 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.81 KM | 27.39 | 16-12-2014 | 20-04-2015 | 1.81 KM | 1.81 KM | 3.72 | 27.39 | 2. | R/Wall, B/ Wall Type Protection works | 1842.00 m | 162.56 | 17-12-2014 | 15-01-2018 | 2002.00 m | 2002.00 m | 22.05 | 162.56 | 3. | GSB/RBI/G-1 | 8.88 KM | 83.68 | 17-12-2014 | 30-11-2017 | 8.88 KM | 8.88 KM | 11.35 | 83.68 | 4. | G-2 | 9.70 KM | 43.17 | 18-12-2014 | 02-12-2017 | 9.70 KM | 9.70 KM | 5.86 | 43.17 | 5. | G-3 | 12.50 KM | 84.41 | 25-04-2015 | 05-12-2017 | 10.50 KM | 10.50 KM | 11.45 | 84.41 | 6. | PC/CC i/c Prime Coat, Tack Coat | 12.50 KM | 139.89 | 24-05-2015 | 20-01-2018 | 12.20 KM | 12.20 KM | 18.98 | 139.89 | 7. | Cause Way | 27.00 No | 62.13 | 25-11-2015 | 15-01-2018 | 27.00 No | 27.00 No | 8.43 | 62.13 | 8. | Culverts/Scupper | 28.00 No | 95.77 | 09-01-2015 | 15-01-2018 | 26.00 No | 26.00 No | 12.99 | 95.77 | 9. | longitudinal Drain | 12325.00 m | 19.47 | 15-04-2015 | 31-12-2017 | 11840.00 m | 11840.00 m | 2.64 | 19.47 | 10. | Crash Barrier | 0.00 m | 0.00 | 01-01-2018 | 25-01-2018 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 240.00 No | 10.53 | 01-01-2016 | 25-01-2018 | 450.00 No | 450.00 No | 1.43 | 10.53 | 12. | Road Furniture | 171.00 No | 3.30 | 15-03-2015 | 31-01-2018 | 171.00 No | 171.00 No | 0.45 | 3.30 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 4.81 | 10-06-2017 | 31-01-2018 | 1.00 Job | 1.00 Job | 0.65 | 4.81 |
Total Amount: |
737.11 |
|
100 |
737.11 |
|
Remarks:
No Remarks
Work Program Made On:
04-10-2015 } ?>
Updation of work program on:
16-05-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 09-March-2015 | 43.96 lakh | 2. | 27-March-2015 | 50.00 lakh | 3. | 11-June-2015 | 17.04 lakh | 4. | 10-September-2015 | 14.60 lakh | 5. | 14-October-2015 | 6.14 lakh | 6. | 07-November-2015 | 11.86 lakh | 7. | 28-January-2016 | 12.09 lakh | 8. | 29-February-2016 | 21.61 lakh | 9. | 30-March-2016 | 17.36 lakh | 10. | 11-May-2016 | 25.91 lakh | 11. | 22-June-2016 | 15.39 lakh | 12. | 06-October-2016 | 10.72 lakh | 13. | 29-November-2016 | 11.70 lakh | 14. | 31-December-2016 | 14.18 lakh | 15. | 31-January-2017 | 18.62 lakh | 16. | 28-February-2017 | 30.47 lakh | 17. | 07-March-2017 | 14.76 lakh | 18. | 31-March-2017 | 30.38 lakh | 19. | 19-April-2017 | 31.87 lakh | 20. | 31-May-2017 | 4.62 lakh | 21. | 05-July-2017 | 20.27 lakh | 22. | 26-July-2017 | 15.72 lakh | 23. | 21-August-2017 | 12.63 lakh | 24. | 18-September-2017 | 12.84 lakh | 25. | 01-November-2017 | 28.46 lakh | 26. | 09-November-2017 | 14.34 lakh | 27. | 26-November-2017 | 12.36 lakh | 28. | 22-December-2017 | 20.99 lakh | 29. | 11-January-2018 | 16.63 lakh | 30. | 24-January-2018 | 14.54 lakh | 31. | 16-February-2018 | 17.58 lakh | 32. | 26-February-2018 | 26.25 lakh | 33. | 28-March-2018 | 7.76 lakh | 34. | 25-October-2018 | 3.00 lakh | 35. | 30-October-2018 | 9.00 lakh | 36. | 18-June-2019 | 0.22 lakh |
Total |
635.87 lakh |
% Payment |
101.5 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1048 No. of Test Done : 1069 No. of Test Passed : 1053 No. of Test Failed : 16 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.00 |
Number of Notice(s) issued: 90 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 135 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 17-05-2018 | 0+300 | Laying seal coat | Harish Singh Rajwar | JE | UDRP R&B Askot | See Pic |
2. | 14-03-2018 | 7+880 | Collecting PC & WBM sample for third party test | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
3. | 14-03-2018 | 12+150 | Collecting PC sample for third party test | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
4. | 14-03-2018 | 11+825 | Collecting PC sample for third party test | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
5. | 14-03-2018 | 10+500 | Collecting PC sample for third party test | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
6. | 14-03-2018 | 9+400 | Collecting PC sample for third party test | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
7. | 14-03-2018 | 8+550 | Collecting PC & WBM G3 sample for third party test | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
8. | 14-03-2018 | 7+850 | Collecting PC sample for third party test | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
9. | 14-03-2018 | 6+725 | Collecting PC sample for third party test | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
10. | 14-03-2018 | 5+400 | Collecting PC sample for third party test | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
11. | 14-03-2018 | 4+500 | Collecting PC sample for third party | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
12. | 14-03-2018 | 3+100 | Collecting PC sample for third party test | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
13. | 14-03-2018 | 2+500 | Collecting PC sample for third party test | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
14. | 14-03-2018 | 1+700 | Collecting. WBM & PC sample for third party test. | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
15. | 14-03-2018 | 0+075 | Collecting PC sample for third party test | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
16. | 09-12-2017 | Ch. 4+775 | Rolling of PC Laying | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
17. | 19-11-2017 | 4+625 | Box culvert slab casting | Harish Singh Rajwar | JE | UDRP R&B Askot | See Pic |
18. | 15-11-2017 | 4775 | Checking GSB thickness. Thickness found less than required. Instructed to increase it. | Arun Kumar Pandey | EE | UDRP R&B Askot | See Pic |
19. | 05-11-2017 | Ch. 7+390 | Laying of Seal Coat material | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
20. | 05-11-2017 | Ch.7+475 | Rolling of PC Laying | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
|
|