Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Madmanya katpatia MR Work Completed
Project: UDRP-RB UID: 2392 Sanction Cost: 697.53  lakh Length: 10.000 KM.
District: Pithoragarh Block: Munakot Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Askot DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 137        Package Name:  UDRP/PWD/07/RD/121        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/RD/121      Contractor Name: R.G. Buildwell.
Start Date:  21-11-2017      Intended Completion Date:  25-06-2019      Original End Date:  20-02-2019
Total Bond Cost: 108587704.9 (1085.88 lakh)        Variation Cost: 11680523.77 (116.81 lakh)    Hence Total Bond Cost is   120268228.67 (1202.68 lakh) 
Sub Project Cost: 616.15  lakh        Variation Cost of Sub Project: 3277768.50  (32.78 lakh)       Total Sub Project Cost:   648.93 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 23074950 for 425 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence10.00 KM179.0110-01-201825-08-201810.00 KM10.00 KM27.59179.01
2.R/Wall, B/ Wall Type Protection works1342.00 m92.4616-02-201815-03-20191342.00 m1342.00 m14.2592.46
3.G-27.25 KM35.6701-07-201825-05-20197.25 KM7.25 KM5.535.67
4.G-310.00 KM54.6001-07-201829-05-201910.00 KM10.00 KM8.4154.60
5.PC/CC i/c Prime Coat, Tack Coat10.00 KM105.8715-04-201903-06-201910.00 KM10.00 KM16.31105.87
6.Cause Way7.00 No34.3201-07-201820-05-20197.00 No7.00 No5.2934.32
7.Culverts/Scupper 17.00 No51.6301-07-201810-05-201917.00 No17.00 No7.9651.63
8.longitudinal Drain10000.00 m12.4901-06-201808-06-201910000.00 m10000.00 m1.9312.49
9.Crash Barrier483.00 m13.5201-05-201907-06-2019483.00 m483.00 m2.0813.52
10.Parapet695.00 No22.2115-04-201910-06-2019695.00 No695.00 No3.4222.21
11.Road Furniture658.00 No7.5725-04-201908-06-2019658.00 No658.00 No1.177.57
12.Other Allied Works & Finishing Work 1.00 Job39.5701-11-201810-06-20191.00 Job1.00 Job6.139.57
Total Amount: 648.92 100   648.92
Remarks: No Remarks       Work Program Made On: 06-01-2018        Updation of work program on: 22-05-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.16-February-201842.75  lakh
2.26-February-20181.87  lakh
3.28-March-201896.01  lakh
4.23-May-201819.18  lakh
5.30-June-20188.99  lakh
6.08-August-201814.34  lakh
7.25-September-201848.67  lakh
8.21-December-201822.42  lakh
9.31-December-20188.65  lakh
10.19-January-201935.32  lakh
11.13-February-201927.99  lakh
12.25-February-201922.44  lakh
13.30-March-201920.89  lakh
14.30-April-201976.01  lakh
15.17-May-201942.29  lakh
16.31-May-201943.18  lakh
17.18-June-201939.56  lakh
18.29-June-201965.80  lakh
Total 636.36  lakh
% Payment98.06 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 266   No. of Test Done : 266    No. of Test Passed : 266   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 91.94
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 17
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.03-05-20190+500Rolling over PC workTej Singh KunwarJEUDRP R&B Askot See Pic
2.29-04-20191+025PC work on progressTej Singh KunwarJEUDRP R&B Askot See Pic
3.29-04-20190+950PC work progress , E.E.sir checkingTej Singh KunwarJEUDRP R&B Askot See Pic
4.28-04-2019Ch 1+900PC work in progressTej Singh KunwarJEUDRP R&B Askot See Pic
5.03-04-20191+900Cube mould filling for strength testTej Singh KunwarJEUDRP R&B Askot See Pic
6.26-09-2018Ch-8+850Construction of wing wallTej Singh KunwarJEUDRP R&B Askot See Pic
7.18-08-20181+550mSlip under SRMDArun Kumar PandeyEEUDRP R&B Askot See Pic
8.04-08-2018Ch.4+850Construction schedule BoardTej Singh KunwarJEUDRP R&B Askot See Pic
9.20-06-2018Ch.2+275Breast wall construction work in progressTej Singh KunwarJEUDRP R&B Askot See Pic
10.23-05-2018Ch 0.000Board inspection by world bank teamSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
11.15-05-20187200mHill side cutting for widening.Arun Kumar PandeyEEUDRP R&B Askot See Pic
12.07-04-2018Chainage 12+950 site officeHealth camp organised at site in world health dayTej Singh KunwarJEUDRP R&B Askot See Pic
13.17-03-2018Chainage 0+00 start point of roadInformation sine boardHarish Singh RajwarJEUDRP R&B Askot See Pic
14.16-03-2018Chainage 0+000UDRP informatory sign boardTej Singh KunwarJEUDRP R&B Askot See Pic
15.16-03-2018Chainage 0+250Soil sample collecting for soil quality testTej Singh KunwarJEUDRP R&B Askot See Pic
16.16-03-2018Chainage 0+200Water sample collecting for water quality testTej Singh KunwarJEUDRP R&B Askot See Pic
17.16-03-2018Chainage 0+175Noise level monitoring testTej Singh KunwarJEUDRP R&B Askot See Pic