Madmanya katpatia MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2392 |
Sanction Cost: |
697.53 lakh |
Length:
|
10.000 KM. |
District: |
Pithoragarh |
Block: |
Munakot |
Constituency: |
Didihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Askot |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 137
Package Name: 
UDRP/PWD/07/RD/121
Tender Date: 07-04-2017
Current Status: Agreement signed
Achieved on Date: 14-11-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/RD/121
Contractor Name: R.G. Buildwell.
|
Start Date: 21-11-2017
Intended Completion Date: 25-06-2019
Original End Date: 20-02-2019 |
Total Bond Cost: 108587704.9 (1085.88 lakh)
Variation Cost: 11680523.77 (116.81 lakh) Hence Total Bond Cost is 120268228.67 (1202.68 lakh)
|
Sub Project Cost: 616.15 lakh
Variation Cost of Sub Project: 3277768.50 (32.78 lakh)
Total Sub Project Cost:
648.93 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 23074950 for 425 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 10.00 KM | 179.01 | 10-01-2018 | 25-08-2018 | 10.00 KM | 10.00 KM | 27.59 | 179.01 | 2. | R/Wall, B/ Wall Type Protection works | 1342.00 m | 92.46 | 16-02-2018 | 15-03-2019 | 1342.00 m | 1342.00 m | 14.25 | 92.46 | 3. | G-2 | 7.25 KM | 35.67 | 01-07-2018 | 25-05-2019 | 7.25 KM | 7.25 KM | 5.5 | 35.67 | 4. | G-3 | 10.00 KM | 54.60 | 01-07-2018 | 29-05-2019 | 10.00 KM | 10.00 KM | 8.41 | 54.60 | 5. | PC/CC i/c Prime Coat, Tack Coat | 10.00 KM | 105.87 | 15-04-2019 | 03-06-2019 | 10.00 KM | 10.00 KM | 16.31 | 105.87 | 6. | Cause Way | 7.00 No | 34.32 | 01-07-2018 | 20-05-2019 | 7.00 No | 7.00 No | 5.29 | 34.32 | 7. | Culverts/Scupper | 17.00 No | 51.63 | 01-07-2018 | 10-05-2019 | 17.00 No | 17.00 No | 7.96 | 51.63 | 8. | longitudinal Drain | 10000.00 m | 12.49 | 01-06-2018 | 08-06-2019 | 10000.00 m | 10000.00 m | 1.93 | 12.49 | 9. | Crash Barrier | 483.00 m | 13.52 | 01-05-2019 | 07-06-2019 | 483.00 m | 483.00 m | 2.08 | 13.52 | 10. | Parapet | 695.00 No | 22.21 | 15-04-2019 | 10-06-2019 | 695.00 No | 695.00 No | 3.42 | 22.21 | 11. | Road Furniture | 658.00 No | 7.57 | 25-04-2019 | 08-06-2019 | 658.00 No | 658.00 No | 1.17 | 7.57 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 39.57 | 01-11-2018 | 10-06-2019 | 1.00 Job | 1.00 Job | 6.1 | 39.57 |
Total Amount: |
648.92 |
|
100 |
648.92 |
|
Remarks:
No Remarks
Work Program Made On:
06-01-2018 } ?>
Updation of work program on:
22-05-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-February-2018 | 42.75 lakh | 2. | 26-February-2018 | 1.87 lakh | 3. | 28-March-2018 | 96.01 lakh | 4. | 23-May-2018 | 19.18 lakh | 5. | 30-June-2018 | 8.99 lakh | 6. | 08-August-2018 | 14.34 lakh | 7. | 25-September-2018 | 48.67 lakh | 8. | 21-December-2018 | 22.42 lakh | 9. | 31-December-2018 | 8.65 lakh | 10. | 19-January-2019 | 35.32 lakh | 11. | 13-February-2019 | 27.99 lakh | 12. | 25-February-2019 | 22.44 lakh | 13. | 30-March-2019 | 20.89 lakh | 14. | 30-April-2019 | 76.01 lakh | 15. | 17-May-2019 | 42.29 lakh | 16. | 31-May-2019 | 43.18 lakh | 17. | 18-June-2019 | 39.56 lakh | 18. | 29-June-2019 | 65.80 lakh |
Total |
636.36 lakh |
% Payment | 98.06 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 266 No. of Test Done : 266 No. of Test Passed : 266 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.94 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 17 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-05-2019 | 0+500 | Rolling over PC work | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
2. | 29-04-2019 | 1+025 | PC work on progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
3. | 29-04-2019 | 0+950 | PC work progress , E.E.sir checking | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
4. | 28-04-2019 | Ch 1+900 | PC work in progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
5. | 03-04-2019 | 1+900 | Cube mould filling for strength test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
6. | 26-09-2018 | Ch-8+850 | Construction of wing wall | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
7. | 18-08-2018 | 1+550m | Slip under SRMD | Arun Kumar Pandey | EE | UDRP R&B Askot | See Pic |
8. | 04-08-2018 | Ch.4+850 | Construction schedule Board | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
9. | 20-06-2018 | Ch.2+275 | Breast wall construction work in progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
10. | 23-05-2018 | Ch 0.000 | Board inspection by world bank team | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
11. | 15-05-2018 | 7200m | Hill side cutting for widening. | Arun Kumar Pandey | EE | UDRP R&B Askot | See Pic |
12. | 07-04-2018 | Chainage 12+950 site office | Health camp organised at site in world health day | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
13. | 17-03-2018 | Chainage 0+00 start point of road | Information sine board | Harish Singh Rajwar | JE | UDRP R&B Askot | See Pic |
14. | 16-03-2018 | Chainage 0+000 | UDRP informatory sign board | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
15. | 16-03-2018 | Chainage 0+250 | Soil sample collecting for soil quality test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
16. | 16-03-2018 | Chainage 0+200 | Water sample collecting for water quality test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
17. | 16-03-2018 | Chainage 0+175 | Noise level monitoring test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
|
|