Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Madmalne Bhotad MR Agreement signed
Project: UDRP-RB UID: 2390 Sanction Cost: 279.96  lakh Length: 3.249 KM.
District: Pithoragarh Block: Kanali Chhina Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Askot DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 137        Package Name:  UDRP/PWD/07/RD/121        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/RD/121      Contractor Name: R.G. Buildwell.
Start Date:  21-11-2017      Intended Completion Date:  20-05-2019      Original End Date:  20-02-2019
Total Bond Cost: 108587704.9 (1085.88 lakh)        Variation Cost: 11680523.77 (116.81 lakh)    Hence Total Bond Cost is   120268228.67 (1202.68 lakh) 
Sub Project Cost: 241.67  lakh        Variation Cost of Sub Project: 9335865.47  (93.36 lakh)       Total Sub Project Cost:   335.03 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 23074950 for 425 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.83 KM51.1905-01-201830-03-20182.83 KM2.83 KM15.2851.19
2.R/Wall, B/ Wall Type Protection works1499.00 m92.3625-01-201825-03-2019914.00 m914.00 m27.5792.36
3.G-24.60 KM45.1501-07-201820-04-20194.60 KM4.60 KM13.4845.15
4.G-33.35 KM21.6415-12-201825-04-20193.35 KM3.35 KM6.4621.64
5.PC/CC i/c Prime Coat, Tack Coat3.35 KM40.7318-03-201930-04-20193.35 KM3.35 KM12.1640.73
6.Cause Way3.00 No7.1001-12-201825-04-20193.00 No3.00 No2.127.10
7.Culverts/Scupper 8.00 No33.2415-01-201825-04-20198.00 No8.00 No9.9233.24
8.longitudinal Drain3200.00 m6.9115-05-201820-05-20193200.00 m2000.00 m1.294.32
9.Crash Barrier110.00 m3.4108-05-201915-05-2019110.00 m110.00 m1.023.41
10.Parapet140.00 No4.5413-05-201920-05-2019140.00 No0.00 No00.00
11.Road Furniture233.00 No3.1012-05-201920-05-2019233.00 No100.00 No0.41.33
12.Other Allied Works & Finishing Work 1.00 Job25.6501-02-201920-05-20191.00 Job0.30 Job2.37.70
Total Amount: 335.02 91.98   308.17
Remarks: No Remarks       Work Program Made On: 04-01-2018        Updation of work program on: 10-05-2019       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.16-February-201834.31  lakh
2.26-February-201820.58  lakh
3.28-March-201822.78  lakh
4.23-May-20184.38  lakh
5.30-June-20180.92  lakh
6.08-August-20181.66  lakh
7.25-September-201817.15  lakh
8.21-December-201818.10  lakh
9.31-December-20189.02  lakh
10.19-January-201933.01  lakh
11.13-February-201917.51  lakh
12.25-February-201916.77  lakh
13.30-March-201919.14  lakh
14.20-April-201929.40  lakh
15.30-April-201918.00  lakh
16.17-May-20196.19  lakh
Total 268.92  lakh
% Payment80.27 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 266   No. of Test Done : 266    No. of Test Passed : 266   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.46
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 31
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.12-04-20192+875PC work progressTej Singh KunwarJEUDRP R&B Askot See Pic
2.12-04-20192+600Rolling over seal coatTej Singh KunwarJEUDRP R&B Askot See Pic
3.03-04-20193+250Water sprinkaling over G-3 layerTej Singh KunwarJEUDRP R&B Askot See Pic
4.30-03-20192+425Causway Top layer casting workTej Singh KunwarJEUDRP R&B Askot See Pic
5.24-03-20191+800Protection work progressTej Singh KunwarJEUDRP R&B Askot See Pic
6.24-03-20192+950Rolling over G-3 layerTej Singh KunwarJEUDRP R&B Askot See Pic
7.24-03-2019Ch.1+100Filling of concrete cubes for strength testTej Singh KunwarJEUDRP R&B Askot See Pic
8.24-03-2019Ch.1+100C/way top layer casting workTej Singh KunwarJEUDRP R&B Askot See Pic
9.31-12-2018Ch.2+800SE sir inspactionTej Singh KunwarJEUDRP R&B Askot See Pic
10.18-08-20181+200slip dew to SRMDTej Singh KunwarJEUDRP R&B Askot See Pic
11.18-08-20181+350Slip over Road dew to SRMDTej Singh KunwarJEUDRP R&B Askot See Pic
12.18-08-20181+000Slip & boulder Over road dew to SRMDTej Singh KunwarJEUDRP R&B Askot See Pic
13.18-08-20180+950Skip & boulder cleaningTej Singh KunwarJEUDRP R&B Askot See Pic
14.18-08-20180+950Road opening SRMD 2018-19Arun Kumar PandeyEEUDRP R&B Askot See Pic
15.04-08-2018Ch.1+450Construction scheduleTej Singh KunwarJEUDRP R&B Askot See Pic
16.28-05-2018Ch 1.200Construction of hill side drainSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
17.28-05-2018Ch 1.300Testing of gradation of WBM G2 materialSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
18.23-05-2018Labour CampChecking of labour camp by world bank teamSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
19.23-05-2018Ch 3.150Road H P Band inspection by world bank missionSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
20.23-05-2018Ch 1.550Inspection of road and culvert by world bank missionSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic