Madmalne Bhotad MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2390 |
Sanction Cost: |
279.96 lakh |
Length:
|
3.249 KM. |
District: |
Pithoragarh |
Block: |
Kanali Chhina |
Constituency: |
Didihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Askot |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 137
Package Name: 
UDRP/PWD/07/RD/121
Tender Date: 07-04-2017
Current Status: Agreement signed
Achieved on Date: 14-11-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/RD/121
Contractor Name: R.G. Buildwell.
|
Start Date: 21-11-2017
Intended Completion Date: 25-06-2019
Original End Date: 20-02-2019 |
Total Bond Cost: 108587704.9 (1085.88 lakh)
Variation Cost: 11680523.77 (116.81 lakh) Hence Total Bond Cost is 120268228.67 (1202.68 lakh)
|
Sub Project Cost: 241.67 lakh
Variation Cost of Sub Project: 9335865.47 (93.36 lakh)
Total Sub Project Cost:
335.03 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 23074950 for 425 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.83 KM | 51.19 | 05-01-2018 | 30-03-2018 | 2.83 KM | 2.83 KM | 15.28 | 51.19 | 2. | R/Wall, B/ Wall Type Protection works | 1499.00 m | 92.36 | 25-01-2018 | 25-03-2019 | 914.00 m | 914.00 m | 27.57 | 92.36 | 3. | G-2 | 4.60 KM | 45.15 | 01-07-2018 | 20-04-2019 | 4.60 KM | 4.60 KM | 13.48 | 45.15 | 4. | G-3 | 3.35 KM | 21.64 | 15-12-2018 | 25-04-2019 | 3.35 KM | 3.35 KM | 6.46 | 21.64 | 5. | PC/CC i/c Prime Coat, Tack Coat | 3.35 KM | 40.73 | 18-03-2019 | 30-04-2019 | 3.35 KM | 3.35 KM | 12.16 | 40.73 | 6. | Cause Way | 6.00 No | 13.10 | 01-12-2018 | 26-05-2019 | 3.00 No | 3.00 No | 3.91 | 13.10 | 7. | Culverts/Scupper | 5.00 No | 27.24 | 15-01-2018 | 25-04-2019 | 8.00 No | 8.00 No | 8.13 | 27.24 | 8. | longitudinal Drain | 3200.00 m | 6.91 | 15-05-2018 | 31-05-2019 | 3200.00 m | 3200.00 m | 2.06 | 6.91 | 9. | Crash Barrier | 110.00 m | 3.41 | 08-05-2019 | 15-05-2019 | 110.00 m | 110.00 m | 1.02 | 3.41 | 10. | Parapet | 140.00 No | 4.54 | 13-05-2019 | 30-05-2019 | 140.00 No | 140.00 No | 1.36 | 4.54 | 11. | Road Furniture | 233.00 No | 3.10 | 12-05-2019 | 26-05-2019 | 233.00 No | 233.00 No | 0.93 | 3.10 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 25.65 | 01-02-2019 | 30-05-2019 | 1.00 Job | 1.00 Job | 7.66 | 25.65 |
Total Amount: |
335.02 |
|
100 |
335.02 |
|
Remarks:
No Remarks
Work Program Made On:
04-01-2018 } ?>
Updation of work program on:
22-05-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-February-2018 | 34.31 lakh | 2. | 26-February-2018 | 20.58 lakh | 3. | 28-March-2018 | 22.78 lakh | 4. | 23-May-2018 | 4.38 lakh | 5. | 30-June-2018 | 0.92 lakh | 6. | 08-August-2018 | 1.66 lakh | 7. | 25-September-2018 | 17.15 lakh | 8. | 21-December-2018 | 18.10 lakh | 9. | 31-December-2018 | 9.02 lakh | 10. | 19-January-2019 | 33.01 lakh | 11. | 13-February-2019 | 17.51 lakh | 12. | 25-February-2019 | 16.77 lakh | 13. | 30-March-2019 | 19.14 lakh | 14. | 20-April-2019 | 29.40 lakh | 15. | 30-April-2019 | 18.00 lakh | 16. | 17-May-2019 | 6.19 lakh | 17. | 31-May-2019 | 13.58 lakh | 18. | 18-June-2019 | 6.62 lakh | 19. | 29-June-2019 | 19.53 lakh |
Total |
308.65 lakh |
% Payment | 92.13 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 266 No. of Test Done : 266 No. of Test Passed : 266 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 94.46 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 31 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-04-2019 | 2+875 | PC work progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
2. | 12-04-2019 | 2+600 | Rolling over seal coat | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
3. | 03-04-2019 | 3+250 | Water sprinkaling over G-3 layer | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
4. | 30-03-2019 | 2+425 | Causway Top layer casting work | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
5. | 24-03-2019 | 1+800 | Protection work progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
6. | 24-03-2019 | 2+950 | Rolling over G-3 layer | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
7. | 24-03-2019 | Ch.1+100 | Filling of concrete cubes for strength test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
8. | 24-03-2019 | Ch.1+100 | C/way top layer casting work | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
9. | 31-12-2018 | Ch.2+800 | SE sir inspaction | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
10. | 18-08-2018 | 1+200 | slip dew to SRMD | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
11. | 18-08-2018 | 1+350 | Slip over Road dew to SRMD | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
12. | 18-08-2018 | 1+000 | Slip & boulder Over road dew to SRMD | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
13. | 18-08-2018 | 0+950 | Skip & boulder cleaning | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
14. | 18-08-2018 | 0+950 | Road opening SRMD 2018-19 | Arun Kumar Pandey | EE | UDRP R&B Askot | See Pic |
15. | 04-08-2018 | Ch.1+450 | Construction schedule | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
16. | 28-05-2018 | Ch 1.200 | Construction of hill side drain | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
17. | 28-05-2018 | Ch 1.300 | Testing of gradation of WBM G2 material | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
18. | 23-05-2018 | Labour Camp | Checking of labour camp by world bank team | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
19. | 23-05-2018 | Ch 3.150 | Road H P Band inspection by world bank mission | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
20. | 23-05-2018 | Ch 1.550 | Inspection of road and culvert by world bank mission | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
|
|