Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Madmalne Bhotad MR Agreement signed
Project: UDRP-RB UID: 2390 Sanction Cost: 279.96  lakh Length: 3.249 KM.
District: Pithoragarh Block: Kanali Chhina Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Askot DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 137        Package Name:  UDRP/PWD/07/RD/121        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/RD/121      Contractor Name: R.G. Buildwell.
Start Date:  21-11-2017      Intended Completion Date:  20-02-2019     
Total Bond Cost: 108587704.9 (1085.88 lakh)        Variation Cost: 11680523.77 (116.81 lakh)    Hence Total Bond Cost is   120268228.67 (1202.68 lakh) 
Sub Project Cost: 241.67  lakh        Variation Cost of Sub Project: 9335865.47  (93.36 lakh)       Total Sub Project Cost:   335.03 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 18242784 for 336 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.83 KM48.6205-01-201830-03-20182.83 KM2.83 KM20.1248.62
2.R/Wall, B/ Wall Type Protection works914.00 m46.0125-01-201815-07-2018914.00 m850.00 m17.7142.79
3.G-24.60 KM28.3601-07-201831-08-20184.60 KM0.00 KM00.00
4.G-33.25 KM21.0415-07-201815-09-20183.25 KM0.00 KM00.00
5.PC/CC i/c Prime Coat, Tack Coat3.25 KM39.6115-09-201815-10-20183.25 KM0.00 KM00.00
6.Cause Way3.00 No7.1916-06-201831-08-20183.00 No0.00 No00.00
7.Culverts/Scupper 5.00 No24.7015-01-201831-08-20185.00 No3.00 No6.1314.82
8.longitudinal Drain3200.00 m1.0315-05-201830-06-20183200.00 m2000.00 m0.270.65
9.Crash Barrier110.00 m3.4115-01-201930-01-2019110.00 m0.00 m00.00
10.Parapet140.00 No4.5401-08-201830-09-2018140.00 No0.00 No00.00
11.Road Furniture233.00 No3.1001-01-201920-02-2019233.00 No0.00 No00.00
12.Other Allied Works & Finishing Work 1.00 Job14.0501-02-201920-02-20191.00 Job0.00 Job00.00
Total Amount: 241.66 44.23   106.88
Remarks: No Remarks       Work Program Made On: 04-01-2018        Updation of work program on: 17-05-2018       
Work Program Status:Program Failed
Financial Progress
SNo. Date Payment
1.16-February-201834.31  lakh
2.26-February-201820.58  lakh
3.28-March-201822.78  lakh
4.23-May-20184.38  lakh
5.30-June-20180.92  lakh
6.08-August-20181.66  lakh
7.25-September-201817.15  lakh
Total 101.78  lakh
% Payment30.38 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 146   No. of Test Done : 146    No. of Test Passed : 146   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.31
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 22
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-08-20181+200slip dew to SRMDTej Singh KunwarJEUDRP R&B Askot See Pic
2.18-08-20181+350Slip over Road dew to SRMDTej Singh KunwarJEUDRP R&B Askot See Pic
3.18-08-20181+000Slip & boulder Over road dew to SRMDTej Singh KunwarJEUDRP R&B Askot See Pic
4.18-08-20180+950Skip & boulder cleaningTej Singh KunwarJEUDRP R&B Askot See Pic
5.18-08-20180+950Road opening SRMD 2018-19Arun Kumar PandeyEEUDRP R&B Askot See Pic
6.04-08-2018Ch.1+450Construction scheduleTej Singh KunwarJEUDRP R&B Askot See Pic
7.28-05-2018Ch 1.200Construction of hill side drainSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
8.28-05-2018Ch 1.300Testing of gradation of WBM G2 materialSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
9.23-05-2018Labour CampChecking of labour camp by world bank teamSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
10.23-05-2018Ch 3.150Road H P Band inspection by world bank missionSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
11.23-05-2018Ch 1.550Inspection of road and culvert by world bank missionSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
12.23-05-2018Ch 0.800Inquiry with labour by world bank missionSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
13.23-05-2018Ch 0.230Checking of culvert by world Bank missionSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
14.18-04-20182+250Gradation of WBM G-2 and G-3Tej Singh KunwarJEUDRP R&B Askot See Pic
15.16-03-2018Chainage 0+400Water sample collecting for water quality testTej Singh KunwarJEUDRP R&B Askot See Pic
16.16-03-2018Chainage 0+075Noise level monitoring testTej Singh KunwarJEUDRP R&B Askot See Pic
17.16-03-20180+400Soil sample collecting for soil quality testTej Singh KunwarJEUDRP R&B Askot See Pic
18.15-03-2018Chainage1+375Construction of Breast wallTej Singh KunwarJEUDRP R&B Askot See Pic
19.15-03-2018Check 1+150Checking of Road Width by SE sirArun Kumar PandeyEEUDRP R&B Askot See Pic
20.15-03-2018Ch.3+249Visit by SE Sir,EE Sir, with staffAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic