Jhulaghat Talesur MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2385 |
Sanction Cost: |
400.82 lakh |
Length:
|
5.000 KM. |
District: |
Pithoragarh |
Block: |
Munakot |
Constituency: |
Didihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Askot |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 113
Package Name: 
UDRP/PWD/07/20/RD/102
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 14-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/20/RD/102
Contractor Name: Anupam Construction Co.
|
Start Date: 21-12-2015
Intended Completion Date: 15-05-2018
Original End Date: 21-03-2017 |
Total Bond Cost: 64083507.2 (640.84 lakh)
Variation Cost: 16723036.85 (167.23 lakh) Hence Total Bond Cost is 80806544.05 (808.07 lakh)
|
Sub Project Cost: 293.95 lakh
Variation Cost of Sub Project: 7551111.66 (75.51 lakh)
Total Sub Project Cost:
369.46 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2210898 for 69 days
LD Analysis for Milestone2: calculated LD is Rs 7786206 for 243 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.25 KM | 15.38 | 21-12-2015 | 10-12-2017 | 3.55 KM | 3.55 KM | 4.82 | 15.38 | 2. | R/Wall, B/ Wall Type Protection works | 990.00 m | 74.04 | 01-02-2016 | 25-11-2017 | 990.00 m | 990.00 m | 23.21 | 74.04 | 3. | G-2 | 10.25 KM | 58.74 | 10-04-2016 | 10-12-2017 | 10.25 KM | 10.25 KM | 18.41 | 58.74 | 4. | G-3 | 5.13 KM | 50.72 | 15-12-2016 | 15-12-2017 | 5.13 KM | 5.13 KM | 15.9 | 50.72 | 5. | PC/CC i/c Prime Coat, Tack Coat | 5.13 KM | 64.63 | 28-11-2017 | 31-12-2017 | 5.13 KM | 5.13 KM | 20.26 | 64.63 | 6. | Cause Way | 2.00 No | 11.27 | 20-11-2017 | 30-11-2017 | 2.00 No | 2.00 No | 3.53 | 11.27 | 7. | Culverts/Scupper | 5.00 No | 22.84 | 25-04-2016 | 10-12-2017 | 4.00 No | 4.00 No | 7.16 | 22.84 | 8. | longitudinal Drain | 4649.00 m | 9.25 | 25-05-2016 | 10-12-2017 | 4649.00 m | 4649.00 m | 2.9 | 9.25 | 9. | Crash Barrier | 100.00 m | 2.70 | 15-01-2018 | 25-01-2018 | 100.00 m | 100.00 m | 0.85 | 2.70 | 10. | Parapet | 110.00 No | 4.02 | 01-02-2018 | 10-02-2018 | 110.00 No | 110.00 No | 1.26 | 4.02 | 11. | Road Furniture | 100.00 No | 2.90 | 01-06-2016 | 30-03-2018 | 100.00 No | 100.00 No | 0.91 | 2.90 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 2.54 | 05-04-2017 | 30-03-2018 | 1.00 Job | 1.00 Job | 0.8 | 2.54 |
Total Amount: |
319.03 |
|
100 |
319.03 |
|
Remarks:
No Remarks
Work Program Made On:
20-01-2016 } ?>
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 12-February-2016 | 15.65 lakh | 2. | 19-March-2016 | 25.65 lakh | 3. | 30-April-2016 | 10.54 lakh | 4. | 23-June-2016 | 5.07 lakh | 5. | 12-August-2016 | 15.19 lakh | 6. | 31-August-2016 | 1.78 lakh | 7. | 30-September-2016 | 11.63 lakh | 8. | 26-October-2016 | 3.43 lakh | 9. | 31-December-2016 | 6.44 lakh | 10. | 31-January-2017 | 7.13 lakh | 11. | 28-February-2017 | 6.13 lakh | 12. | 10-March-2017 | 5.45 lakh | 13. | 31-March-2017 | 1.65 lakh | 14. | 15-April-2017 | 17.90 lakh | 15. | 20-June-2017 | 3.00 lakh | 16. | 03-November-2017 | 9.95 lakh | 17. | 22-December-2017 | 9.74 lakh | 18. | 30-December-2017 | 18.71 lakh | 19. | 12-January-2018 | 33.88 lakh | 20. | 16-February-2018 | 31.42 lakh | 21. | 26-February-2018 | 4.07 lakh | 22. | 28-March-2018 | 9.60 lakh | 23. | 23-April-2018 | 20.74 lakh | 24. | 22-May-2018 | 24.65 lakh | 25. | 07-June-2018 | 0.26 lakh | 26. | 30-June-2018 | 22.97 lakh | 27. | 08-August-2018 | 13.28 lakh | 28. | 26-September-2018 | 10.89 lakh | 29. | 01-November-2018 | 10.00 lakh | 30. | 27-November-2018 | 22.03 lakh | 31. | 21-December-2018 | 9.28 lakh | 32. | 19-January-2019 | 6.16 lakh | 33. | 17-June-2019 | 4.12 lakh |
Total |
398.39 lakh |
% Payment | 107.83 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 741 No. of Test Done : 752 No. of Test Passed : 745 No. of Test Failed : 7 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.04 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 28 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 02-04-2018 | HMP | Bitumen content of PC material testing. Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
2. | 17-01-2018 | Ch.0+400 | Rolling of PC layer | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
3. | 16-01-2018 | HMP | Bitumen content of PC material testing at HMP. Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
4. | 26-12-2017 | HMP | Bitumen content of PC material testing at HMP. Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
5. | 21-12-2017 | HMP | Bitumen content of PC material testing at HMP. Found OK. | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
6. | 10-08-2017 | 4+050 | Sattelement portion | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
7. | 08-04-2017 | Ch.0+450 | Gradation of WBM G2 testing by QC Incharge at site | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
8. | 06-10-2016 | 3+900 | Site visit by SE, EE, tlsir | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
9. | 21-09-2016 | 4+270 | G2Rejected material being scraped from site | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
10. | 21-09-2016 | 2+925 | G2Rejected material being scraped from site | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
11. | 21-09-2016 | 0+975 | Hill side cutting is in progress | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
12. | 02-08-2016 | 1+225 | G2 work is in progress | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
13. | 25-07-2016 | 1800 | Checking grading of G-II WBM | Arun Kumar Pandey | EE | UDRP R&B Askot | See Pic |
14. | 31-03-2016 | Bended Retaining Wall at CH.- 4+150 | Work in progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
15. | 27-03-2016 | 4/150 | R/wall | Deepak Pant | Technical Assistant | DSC4 R&B WB Pithoragarh | See Pic |
16. | 27-03-2016 | 4/275 | R/wall dry | Deepak Pant | Technical Assistant | DSC4 R&B WB Pithoragarh | See Pic |
17. | 26-03-2016 | 2/600 | Hill side cutting | Deepak Pant | Technical Assistant | DSC4 R&B WB Pithoragarh | See Pic |
18. | 02-03-2016 | R/wall | 0/575 | Deepak Pant | Technical Assistant | DSC4 R&B WB Pithoragarh | See Pic |
19. | 02-03-2016 | 4.915 | B/wall | Deepak Pant | Technical Assistant | DSC4 R&B WB Pithoragarh | See Pic |
20. | 02-03-2016 | 5/100 | Rwall | Deepak Pant | Technical Assistant | DSC4 R&B WB Pithoragarh | See Pic |
|
|