Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Badari kante Bora MR Work Completed
Project: UDRP-RB UID: 2375 Sanction Cost: 482.84  lakh Length: 6.000 KM.
District: Pithoragarh Block: Munakot Constituency: Pithoragarh Circle: Pithoragarh WB Circle
DEA: DEA Askot DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 113        Package Name:  UDRP/PWD/07/20/RD/102        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 14-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/20/RD/102      Contractor Name: Anupam Construction Co.
Start Date:  21-12-2015      Intended Completion Date:  15-05-2018      Original End Date:  21-03-2017
Total Bond Cost: 64083507.2 (640.84 lakh)        Variation Cost: 16723036.85 (167.23 lakh)    Hence Total Bond Cost is   80806544.05 (808.07 lakh) 
Sub Project Cost: 346.89  lakh        Variation Cost of Sub Project: 9171925.19  (91.72 lakh)       Total Sub Project Cost:   438.61 lakh
LD Analysis for Milestone1: calculated LD is Rs 2210898 for 69 days        LD Analysis for Milestone2: calculated LD is Rs 7786206 for 243 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.50 KM27.2421-12-201510-12-20171.50 KM1.50 KM7.4227.24
2.R/Wall, B/ Wall Type Protection works1252.00 m71.6701-02-201631-12-20171252.00 m1252.00 m19.5371.67
3.G-212.00 KM69.0710-04-201615-01-201812.00 KM12.00 KM18.8269.07
4.G-36.00 KM59.3805-03-201731-01-20186.00 KM6.00 KM16.1859.38
5.PC/CC i/c Prime Coat, Tack Coat6.00 KM76.0215-04-201728-02-20186.00 KM6.00 KM20.7276.02
6.Cause Way2.00 No8.3025-11-201731-12-20172.00 No2.00 No2.268.30
7.Culverts/Scupper 8.00 No27.6801-02-201631-12-20178.00 No8.00 No7.5427.68
8.longitudinal Drain5783.00 m13.2201-05-201631-12-20175783.00 m5783.00 m3.613.22
9.Crash Barrier100.00 m2.7001-03-201810-03-2018100.00 m100.00 m0.742.70
10.Parapet80.00 No2.8501-02-201810-02-201880.00 No80.00 No0.782.85
11.Road Furniture72.00 No2.5001-06-201630-03-201872.00 No72.00 No0.682.50
12.Other Allied Works & Finishing Work 1.00 Job6.3405-04-201730-03-20181.00 Job1.00 Job1.736.34
Total Amount: 366.97 100   366.97
Remarks: No Remarks       Work Program Made On: 20-01-2016        Updation of work program on: 28-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.12-February-201610.88  lakh
2.19-March-201618.86  lakh
3.30-April-20165.41  lakh
4.23-June-201614.89  lakh
5.12-August-201614.28  lakh
6.31-August-20167.99  lakh
7.26-October-201624.37  lakh
8.29-November-201611.71  lakh
9.31-December-20168.80  lakh
10.31-January-201711.54  lakh
11.28-February-20175.35  lakh
12.10-March-20175.58  lakh
13.31-March-20174.98  lakh
14.15-April-20172.17  lakh
15.31-May-201712.02  lakh
16.20-June-201723.51  lakh
17.30-June-201732.50  lakh
18.03-November-201714.96  lakh
19.22-December-201716.26  lakh
20.30-December-20177.40  lakh
21.12-January-20188.37  lakh
22.16-February-201812.60  lakh
23.26-February-201812.65  lakh
24.28-March-20185.61  lakh
25.23-April-201810.34  lakh
26.27-April-201821.34  lakh
27.22-May-201825.20  lakh
28.07-June-20188.21  lakh
29.30-June-201828.20  lakh
30.08-August-201817.87  lakh
31.26-September-201826.90  lakh
32.01-November-201810.00  lakh
33.27-November-201814.21  lakh
34.21-December-20187.53  lakh
35.19-January-201919.89  lakh
36.17-June-20192.92  lakh
Total 485.3  lakh
% Payment110.64 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 741   No. of Test Done : 752    No. of Test Passed : 745   No. of Test Failed : 7   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 80.42
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 36
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.24-04-2018Ch. 4+343Rolling of PC surfaceAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
2.05-08-2017Ch.4+750Soil sample collected for CBR Test by jointlyAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
3.02-08-20174+600Hill side portion is being moved to downManoj BhattREDSC2 R&B WB Pauri See Pic
4.02-08-20174+600Retaining wall damaged due to hill portion sattelementManoj BhattREDSC2 R&B WB Pauri See Pic
5.02-08-20174+600Walls damaged due to hill sattelement during rain.Manoj BhattREDSC2 R&B WB Pauri See Pic
6.21-05-2017Ch.1+575Gradation of WBM G3, Laying material Testing. Result Found OKAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
7.25-11-20161+150Preparation of slab castingShailendra Kumar SinghREDSC4 R&B WB Askot See Pic
8.18-09-20160+25Site visit by DPM,EE sir world Bank gradation of G_2Shailendra Kumar SinghREDSC4 R&B WB Askot See Pic
9.18-09-20161+300Site visit by DPM, EE sir thickness checking of G-2Shailendra Kumar SinghREDSC4 R&B WB Askot See Pic
10.18-09-20162+500Site visit by SE, EE Sir testing of AIV for G_2Shailendra Kumar SinghREDSC4 R&B WB Askot See Pic
11.13-06-2016Ch.- 4+050 To 4+075Breast wall work done.Vijayraj SinghJEUDRP R&B Uttarkashi See Pic
12.25-05-20162+575Site labTej Singh KunwarJEUDRP R&B Askot See Pic
13.25-05-20162+520Site lab with work programTej Singh KunwarJEUDRP R&B Askot See Pic
14.25-05-20162/520Site Testing labDeepak PantTechnical AssistantDSC4 R&B WB Pithoragarh See Pic
15.19-05-20163850Showing coolie wall construction.Arun Kumar PandeyEEUDRP R&B Askot See Pic
16.19-05-20163/850Coollie wallDeepak PantTechnical AssistantDSC4 R&B WB Pithoragarh See Pic
17.16-05-20164/500Breast wallDeepak PantTechnical AssistantDSC4 R&B WB Pithoragarh See Pic
18.16-05-20164/500Curing in breast wallDeepak PantTechnical AssistantDSC4 R&B WB Pithoragarh See Pic
19.06-05-20161/600Making subgrade and kachcha drainDeepak PantTechnical AssistantDSC4 R&B WB Pithoragarh See Pic
20.06-05-20160/800G2 checking by A.E. sirDeepak PantTechnical AssistantDSC4 R&B WB Pithoragarh See Pic