Badari kante Bora MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2375 |
Sanction Cost: |
482.84 lakh |
Length:
|
6.000 KM. |
District: |
Pithoragarh |
Block: |
Munakot |
Constituency: |
Pithoragarh |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Askot |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 113
Package Name: 
UDRP/PWD/07/20/RD/102
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 14-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/20/RD/102
Contractor Name: Anupam Construction Co.
|
Start Date: 21-12-2015
Intended Completion Date: 15-05-2018
Original End Date: 21-03-2017 |
Total Bond Cost: 64083507.2 (640.84 lakh)
Variation Cost: 16723036.85 (167.23 lakh) Hence Total Bond Cost is 80806544.05 (808.07 lakh)
|
Sub Project Cost: 346.89 lakh
Variation Cost of Sub Project: 9171925.19 (91.72 lakh)
Total Sub Project Cost:
438.61 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2210898 for 69 days
LD Analysis for Milestone2: calculated LD is Rs 7786206 for 243 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.50 KM | 27.24 | 21-12-2015 | 10-12-2017 | 1.50 KM | 1.50 KM | 7.42 | 27.24 | 2. | R/Wall, B/ Wall Type Protection works | 1252.00 m | 71.67 | 01-02-2016 | 31-12-2017 | 1252.00 m | 1252.00 m | 19.53 | 71.67 | 3. | G-2 | 12.00 KM | 69.07 | 10-04-2016 | 15-01-2018 | 12.00 KM | 12.00 KM | 18.82 | 69.07 | 4. | G-3 | 6.00 KM | 59.38 | 05-03-2017 | 31-01-2018 | 6.00 KM | 6.00 KM | 16.18 | 59.38 | 5. | PC/CC i/c Prime Coat, Tack Coat | 6.00 KM | 76.02 | 15-04-2017 | 28-02-2018 | 6.00 KM | 6.00 KM | 20.72 | 76.02 | 6. | Cause Way | 2.00 No | 8.30 | 25-11-2017 | 31-12-2017 | 2.00 No | 2.00 No | 2.26 | 8.30 | 7. | Culverts/Scupper | 8.00 No | 27.68 | 01-02-2016 | 31-12-2017 | 8.00 No | 8.00 No | 7.54 | 27.68 | 8. | longitudinal Drain | 5783.00 m | 13.22 | 01-05-2016 | 31-12-2017 | 5783.00 m | 5783.00 m | 3.6 | 13.22 | 9. | Crash Barrier | 100.00 m | 2.70 | 01-03-2018 | 10-03-2018 | 100.00 m | 100.00 m | 0.74 | 2.70 | 10. | Parapet | 80.00 No | 2.85 | 01-02-2018 | 10-02-2018 | 80.00 No | 80.00 No | 0.78 | 2.85 | 11. | Road Furniture | 72.00 No | 2.50 | 01-06-2016 | 30-03-2018 | 72.00 No | 72.00 No | 0.68 | 2.50 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 6.34 | 05-04-2017 | 30-03-2018 | 1.00 Job | 1.00 Job | 1.73 | 6.34 |
Total Amount: |
366.97 |
|
100 |
366.97 |
|
Remarks:
No Remarks
Work Program Made On:
20-01-2016 } ?>
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 12-February-2016 | 10.88 lakh | 2. | 19-March-2016 | 18.86 lakh | 3. | 30-April-2016 | 5.41 lakh | 4. | 23-June-2016 | 14.89 lakh | 5. | 12-August-2016 | 14.28 lakh | 6. | 31-August-2016 | 7.99 lakh | 7. | 26-October-2016 | 24.37 lakh | 8. | 29-November-2016 | 11.71 lakh | 9. | 31-December-2016 | 8.80 lakh | 10. | 31-January-2017 | 11.54 lakh | 11. | 28-February-2017 | 5.35 lakh | 12. | 10-March-2017 | 5.58 lakh | 13. | 31-March-2017 | 4.98 lakh | 14. | 15-April-2017 | 2.17 lakh | 15. | 31-May-2017 | 12.02 lakh | 16. | 20-June-2017 | 23.51 lakh | 17. | 30-June-2017 | 32.50 lakh | 18. | 03-November-2017 | 14.96 lakh | 19. | 22-December-2017 | 16.26 lakh | 20. | 30-December-2017 | 7.40 lakh | 21. | 12-January-2018 | 8.37 lakh | 22. | 16-February-2018 | 12.60 lakh | 23. | 26-February-2018 | 12.65 lakh | 24. | 28-March-2018 | 5.61 lakh | 25. | 23-April-2018 | 10.34 lakh | 26. | 27-April-2018 | 21.34 lakh | 27. | 22-May-2018 | 25.20 lakh | 28. | 07-June-2018 | 8.21 lakh | 29. | 30-June-2018 | 28.20 lakh | 30. | 08-August-2018 | 17.87 lakh | 31. | 26-September-2018 | 26.90 lakh | 32. | 01-November-2018 | 10.00 lakh | 33. | 27-November-2018 | 14.21 lakh | 34. | 21-December-2018 | 7.53 lakh | 35. | 19-January-2019 | 19.89 lakh | 36. | 17-June-2019 | 2.92 lakh |
Total |
485.3 lakh |
% Payment | 110.64 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 741 No. of Test Done : 752 No. of Test Passed : 745 No. of Test Failed : 7 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 80.42 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 36 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-04-2018 | Ch. 4+343 | Rolling of PC surface | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
2. | 05-08-2017 | Ch.4+750 | Soil sample collected for CBR Test by jointly | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
3. | 02-08-2017 | 4+600 | Hill side portion is being moved to down | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
4. | 02-08-2017 | 4+600 | Retaining wall damaged due to hill portion sattelement | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
5. | 02-08-2017 | 4+600 | Walls damaged due to hill sattelement during rain. | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
6. | 21-05-2017 | Ch.1+575 | Gradation of WBM G3, Laying material Testing. Result Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
7. | 25-11-2016 | 1+150 | Preparation of slab casting | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
8. | 18-09-2016 | 0+25 | Site visit by DPM,EE sir world Bank gradation of G_2 | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
9. | 18-09-2016 | 1+300 | Site visit by DPM, EE sir thickness checking of G-2 | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
10. | 18-09-2016 | 2+500 | Site visit by SE, EE Sir testing of AIV for G_2 | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
11. | 13-06-2016 | Ch.- 4+050 To 4+075 | Breast wall work done. | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
12. | 25-05-2016 | 2+575 | Site lab | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
13. | 25-05-2016 | 2+520 | Site lab with work program | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
14. | 25-05-2016 | 2/520 | Site Testing lab | Deepak Pant | Technical Assistant | DSC4 R&B WB Pithoragarh | See Pic |
15. | 19-05-2016 | 3850 | Showing coolie wall construction. | Arun Kumar Pandey | EE | UDRP R&B Askot | See Pic |
16. | 19-05-2016 | 3/850 | Coollie wall | Deepak Pant | Technical Assistant | DSC4 R&B WB Pithoragarh | See Pic |
17. | 16-05-2016 | 4/500 | Breast wall | Deepak Pant | Technical Assistant | DSC4 R&B WB Pithoragarh | See Pic |
18. | 16-05-2016 | 4/500 | Curing in breast wall | Deepak Pant | Technical Assistant | DSC4 R&B WB Pithoragarh | See Pic |
19. | 06-05-2016 | 1/600 | Making subgrade and kachcha drain | Deepak Pant | Technical Assistant | DSC4 R&B WB Pithoragarh | See Pic |
20. | 06-05-2016 | 0/800 | G2 checking by A.E. sir | Deepak Pant | Technical Assistant | DSC4 R&B WB Pithoragarh | See Pic |
|
|