Acholi jaakh
Work Completed
|
Project: |
UDRP-RB |
UID: |
2370 |
Sanction Cost: |
331.29 lakh |
Length:
|
8.000 KM. |
District: |
Pithoragarh |
Block: |
Pithoragarh(Bin) |
Constituency: |
Pithoragarh |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Askot |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 104
Package Name: 
UDRP/PWD/07/15/RD/093
Tender Date: 18-02-2015
Current Status: Agreement signed
Achieved on Date: 01-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/15/RD/093
Contractor Name: M & P Infrastructure
|
Start Date: 08-07-2015
Intended Completion Date: 01-11-2018
Original End Date: 07-10-2016 |
Total Bond Cost: 66856998.32 (668.57 lakh)
Variation Cost: 3385916.26 (33.86 lakh) Hence Total Bond Cost is 70242914.58 (702.43 lakh)
|
Sub Project Cost: 331.29 lakh
Variation Cost of Sub Project: 4635126.41 (46.35 lakh)
Total Sub Project Cost:
377.64 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 3409656 for 102 days
LD Analysis for Milestone2: calculated LD is Rs 8390428 for 251 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.67 KM | 27.09 | 15-12-2015 | 31-10-2016 | 1.67 KM | 1.67 KM | 8.77 | 27.09 | 2. | R/Wall, B/ Wall Type Protection works | 527.75 m | 47.98 | 20-08-2015 | 15-02-2017 | 738.00 m | 738.00 m | 15.52 | 47.98 | 3. | G-2 | 1.00 KM | 0.00 | 15-11-2016 | 20-05-2017 | 1.00 KM | 1.00 KM | 0 | 0.00 | 4. | G-3 | 1.00 KM | 0.50 | 15-11-2016 | 25-05-2017 | 1.00 KM | 1.00 KM | 0.16 | 0.50 | 5. | BM i/c Prime Coat, Tack Coat | 1.00 KM | 32.37 | 25-11-2016 | 05-06-2017 | 0.94 KM | 0.94 KM | 10.47 | 32.37 | 6. | SDBC i/c Tackcoat | 7.70 KM | 114.96 | 25-11-2016 | 10-06-2017 | 7.58 KM | 7.58 KM | 37.19 | 114.96 | 7. | Cause Way | 2.00 No | 12.84 | 01-08-2016 | 15-09-2017 | 2.00 No | 2.00 No | 4.15 | 12.84 | 8. | Culverts/Scupper | 5.00 No | 16.17 | 25-11-2015 | 20-05-2017 | 5.00 No | 5.00 No | 5.23 | 16.17 | 9. | longitudinal Drain | 7089.00 m | 15.44 | 15-02-2016 | 30-11-2017 | 7600.00 m | 7600.00 m | 5 | 15.44 | 10. | Crash Barrier | 350.00 m | 13.65 | 01-10-2017 | 30-11-2017 | 1240.00 m | 1240.00 m | 4.42 | 13.65 | 11. | Parapet | 200.00 No | 3.12 | 01-04-2017 | 30-11-2017 | 32.00 No | 32.00 No | 1.01 | 3.12 | 12. | Road Furniture | 120.00 No | 9.79 | 01-05-2016 | 30-11-2017 | 120.00 No | 120.00 No | 3.17 | 9.79 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 15.18 | 01-05-2017 | 30-11-2017 | 1.00 Job | 1.00 Job | 4.91 | 15.18 |
Total Amount: |
309.09 |
|
100 |
309.09 |
|
Remarks:
No Remarks
Work Program Made On:
28-09-2015 } ?>
Updation of work program on:
08-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-October-2015 | 5.30 lakh | 2. | 23-December-2015 | 7.83 lakh | 3. | 12-April-2016 | 8.24 lakh | 4. | 13-May-2016 | 4.41 lakh | 5. | 30-June-2016 | 16.22 lakh | 6. | 20-July-2016 | 1.25 lakh | 7. | 03-September-2016 | 17.80 lakh | 8. | 27-October-2016 | 11.98 lakh | 9. | 05-December-2016 | 5.10 lakh | 10. | 19-December-2016 | 56.38 lakh | 11. | 31-December-2016 | 64.18 lakh | 12. | 31-January-2017 | 6.14 lakh | 13. | 28-February-2017 | 1.64 lakh | 14. | 31-March-2017 | 0.82 lakh | 15. | 31-May-2017 | 0.74 lakh | 16. | 18-June-2017 | 31.80 lakh | 17. | 11-July-2017 | 1.00 lakh | 18. | 25-August-2017 | 0.10 lakh | 19. | 25-October-2017 | 0.52 lakh | 20. | 16-February-2018 | 43.27 lakh | 21. | 07-March-2018 | 8.59 lakh | 22. | 31-May-2018 | 7.53 lakh | 23. | 23-August-2018 | 21.68 lakh | 24. | 29-October-2018 | 20.15 lakh | 25. | 01-November-2018 | 4.00 lakh | 26. | 30-November-2018 | 15.09 lakh | 27. | 09-March-2019 | 33.62 lakh |
Total |
395.38 lakh |
% Payment | 104.7 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 589 No. of Test Done : 598 No. of Test Passed : 596 No. of Test Failed : 2 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 75 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-05-2018 | Ch 1.400 | Meeting with gram pradhan by world bank team | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
2. | 16-03-2018 | Cha.4+450 | SDBC core thickness checking third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
3. | 15-03-2018 | 7+400 | SDBC sample core cutting for third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
4. | 15-03-2018 | Chainage 4+450 | SDBC sample core cutting for third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
5. | 15-03-2018 | Chainage 2+500 | SDBC Sample core cutting for third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
6. | 15-03-2018 | Chainage 1+450 | SDBC sample core cutting for third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
7. | 15-03-2018 | Chainage 0+500 | SDBC sampal core cutting for thired party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
8. | 24-12-2017 | 0+400 | Labour Health checkup | Harish Singh Rajwar | JE | UDRP R&B Askot | See Pic |
9. | 05-08-2017 | Ch. 2+400 | Re-Test of SDBC for Bitumen Content. Result found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
10. | 03-08-2017 | 3+550 | White washing on edge stone in progress | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
11. | 12-06-2017 | Ch.3+150 | Rolling of SDBC surface | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
12. | 12-06-2017 | Hot Mix Plant | Bitumen content of BM material Testing by QC Incharge at plant. Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
13. | 12-06-2017 | 2+875 | Rolling of SDBC surface | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
14. | 12-06-2017 | Ch 3+075 | Undulation of SDBC surface checking by SE Sir with QC Incharge. Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
15. | 05-06-2017 | Laboratory | AIV Testing of 20mm,10mm aggregate for BM work. | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
16. | 09-03-2017 | Ch 6.600 | Checking of carriageway width by SE sir found 3.80m | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
17. | 17-12-2016 | Plant site | Bitumen extraction test for SDBC work bitumen 5.05% | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
18. | 17-12-2016 | Ch 5.825 | SDBC laying work in progress
Thickness checked in presence of CME is 26mm | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
19. | 16-12-2016 | 5.275 | laying of sdbc | Rajesh Chauhan | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
20. | 16-12-2016 | Ch. 5.825 | Sdbc work in progress. Thickness found 26mm. | Adarsh Gopal Singh | CME | PIU UDRP R&B | See Pic |
|
|