Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Acholi jaakh Work Completed
Project: UDRP-RB UID: 2370 Sanction Cost: 331.29  lakh Length: 8.000 KM.
District: Pithoragarh Block: Pithoragarh(Bin) Constituency: Pithoragarh Circle: Pithoragarh WB Circle
DEA: DEA Askot DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 104        Package Name:  UDRP/PWD/07/15/RD/093        Tender Date: 18-02-2015        Current Status: Agreement signed        Achieved on Date: 01-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/15/RD/093      Contractor Name: M & P Infrastructure
Start Date:  08-07-2015      Intended Completion Date:  01-11-2018      Original End Date:  07-10-2016
Total Bond Cost: 66856998.32 (668.57 lakh)        Variation Cost: 3385916.26 (33.86 lakh)    Hence Total Bond Cost is   70242914.58 (702.43 lakh) 
Sub Project Cost: 331.29  lakh        Variation Cost of Sub Project: 4635126.41  (46.35 lakh)       Total Sub Project Cost:   377.64 lakh
LD Analysis for Milestone1: calculated LD is Rs 3409656 for 102 days        LD Analysis for Milestone2: calculated LD is Rs 8390428 for 251 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.67 KM27.0915-12-201531-10-20161.67 KM1.67 KM8.7727.09
2.R/Wall, B/ Wall Type Protection works527.75 m47.9820-08-201515-02-2017738.00 m738.00 m15.5247.98
3.G-21.00 KM0.0015-11-201620-05-20171.00 KM1.00 KM00.00
4.G-31.00 KM0.5015-11-201625-05-20171.00 KM1.00 KM0.160.50
5.BM i/c Prime Coat, Tack Coat1.00 KM32.3725-11-201605-06-20170.94 KM0.94 KM10.4732.37
6.SDBC i/c Tackcoat7.70 KM114.9625-11-201610-06-20177.58 KM7.58 KM37.19114.96
7.Cause Way2.00 No12.8401-08-201615-09-20172.00 No2.00 No4.1512.84
8.Culverts/Scupper 5.00 No16.1725-11-201520-05-20175.00 No5.00 No5.2316.17
9.longitudinal Drain7089.00 m15.4415-02-201630-11-20177600.00 m7600.00 m515.44
10.Crash Barrier350.00 m13.6501-10-201730-11-20171240.00 m1240.00 m4.4213.65
11.Parapet200.00 No3.1201-04-201730-11-201732.00 No32.00 No1.013.12
12.Road Furniture120.00 No9.7901-05-201630-11-2017120.00 No120.00 No3.179.79
13.Other Allied Works & Finishing Work 1.00 Job15.1801-05-201730-11-20171.00 Job1.00 Job4.9115.18
Total Amount: 309.09 100   309.09
Remarks: No Remarks       Work Program Made On: 28-09-2015        Updation of work program on: 08-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-October-20155.30  lakh
2.23-December-20157.83  lakh
3.12-April-20168.24  lakh
4.13-May-20164.41  lakh
5.30-June-201616.22  lakh
6.20-July-20161.25  lakh
7.03-September-201617.80  lakh
8.27-October-201611.98  lakh
9.05-December-20165.10  lakh
10.19-December-201656.38  lakh
11.31-December-201664.18  lakh
12.31-January-20176.14  lakh
13.28-February-20171.64  lakh
14.31-March-20170.82  lakh
15.31-May-20170.74  lakh
16.18-June-201731.80  lakh
17.11-July-20171.00  lakh
18.25-August-20170.10  lakh
19.25-October-20170.52  lakh
20.16-February-201843.27  lakh
21.07-March-20188.59  lakh
22.31-May-20187.53  lakh
23.23-August-201821.68  lakh
24.29-October-201820.15  lakh
25.01-November-20184.00  lakh
26.30-November-201815.09  lakh
27.09-March-201933.62  lakh
Total 395.38  lakh
% Payment104.7 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 589   No. of Test Done : 598    No. of Test Passed : 596   No. of Test Failed : 2   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 75
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-05-2018Ch 1.400Meeting with gram pradhan by world bank teamSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
2.16-03-2018Cha.4+450SDBC core thickness checking third party testTej Singh KunwarJEUDRP R&B Askot See Pic
3.15-03-20187+400SDBC sample core cutting for third party testTej Singh KunwarJEUDRP R&B Askot See Pic
4.15-03-2018Chainage 4+450SDBC sample core cutting for third party testTej Singh KunwarJEUDRP R&B Askot See Pic
5.15-03-2018Chainage 2+500SDBC Sample core cutting for third party testTej Singh KunwarJEUDRP R&B Askot See Pic
6.15-03-2018Chainage 1+450SDBC sample core cutting for third party testTej Singh KunwarJEUDRP R&B Askot See Pic
7.15-03-2018Chainage 0+500SDBC sampal core cutting for thired party testTej Singh KunwarJEUDRP R&B Askot See Pic
8.24-12-20170+400Labour Health checkupHarish Singh RajwarJEUDRP R&B Askot See Pic
9.05-08-2017Ch. 2+400Re-Test of SDBC for Bitumen Content. Result found OKAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
10.03-08-20173+550White washing on edge stone in progressManoj BhattREDSC2 R&B WB Pauri See Pic
11.12-06-2017Ch.3+150Rolling of SDBC surfaceAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
12.12-06-2017Hot Mix PlantBitumen content of BM material Testing by QC Incharge at plant. Found OKAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
13.12-06-20172+875Rolling of SDBC surfaceAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
14.12-06-2017Ch 3+075Undulation of SDBC surface checking by SE Sir with QC Incharge. Found OKAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
15.05-06-2017LaboratoryAIV Testing of 20mm,10mm aggregate for BM work.Abid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
16.09-03-2017Ch 6.600Checking of carriageway width by SE sir found 3.80mSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
17.17-12-2016Plant siteBitumen extraction test for SDBC work bitumen 5.05%Satendra Mohan UpadhyayAEUDRP R&B Askot See Pic
18.17-12-2016Ch 5.825SDBC laying work in progress Thickness checked in presence of CME is 26mmSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic
19.16-12-20165.275laying of sdbcRajesh ChauhanSite SupervisorDSC4 R&B WB Pithoragarh See Pic
20.16-12-2016Ch. 5.825Sdbc work in progress. Thickness found 26mm.Adarsh Gopal SinghCMEPIU UDRP R&B See Pic