Nainipatal Madmaley MR (Ch-7 to 13.162 Km)
Work Completed
|
Project: |
UDRP-RB |
UID: |
2357 |
Sanction Cost: |
270.39 lakh |
Length:
|
6.162 KM. |
District: |
Pithoragarh |
Block: |
Munakot |
Constituency: |
Didihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Askot |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
BR |
|
Procurement: |
Package No.: 137
Package Name: 
UDRP/PWD/07/RD/121
Tender Date: 07-04-2017
Current Status: Agreement signed
Achieved on Date: 14-11-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/RD/121
Contractor Name: R.G. Buildwell.
|
Start Date: 21-11-2017
Intended Completion Date: 25-06-2019
Original End Date: 20-02-2019 |
Total Bond Cost: 108587704.9 (1085.88 lakh)
Variation Cost: 11680523.77 (116.81 lakh) Hence Total Bond Cost is 120268228.67 (1202.68 lakh)
|
Sub Project Cost: 228.06 lakh
Variation Cost of Sub Project: -933110.20 (-9.33 lakh)
Total Sub Project Cost:
218.73 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 23074950 for 425 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.86 KM | 18.75 | 21-11-2017 | 15-01-2018 | 1.86 KM | 1.86 KM | 8.57 | 18.75 | 2. | R/Wall, B/ Wall Type Protection works | 382.00 m | 27.47 | 21-11-2017 | 30-12-2018 | 290.00 m | 290.00 m | 12.56 | 27.47 | 3. | G-2 | 1.00 KM | 4.73 | 25-05-2018 | 03-03-2019 | 1.00 KM | 1.00 KM | 2.16 | 4.73 | 4. | G-3 | 1.25 KM | 6.48 | 25-05-2018 | 03-03-2019 | 1.25 KM | 1.25 KM | 2.96 | 6.48 | 5. | PC/CC i/c Prime Coat, Tack Coat | 6.16 KM | 68.42 | 15-09-2018 | 15-03-2019 | 6.16 KM | 6.16 KM | 31.28 | 68.42 | 6. | Cause Way | 3.00 No | 18.12 | 26-05-2018 | 10-01-2019 | 3.00 No | 3.00 No | 8.29 | 18.12 | 7. | Culverts/Scupper | 7.00 No | 21.68 | 16-12-2017 | 30-09-2018 | 7.00 No | 7.00 No | 9.91 | 21.68 | 8. | longitudinal Drain | 6126.00 m | 3.77 | 01-02-2018 | 20-05-2019 | 6126.00 m | 6126.00 m | 1.72 | 3.77 | 9. | Crash Barrier | 200.00 m | 5.80 | 01-03-2019 | 07-05-2019 | 200.00 m | 200.00 m | 2.65 | 5.80 | 10. | Parapet | 500.00 No | 14.58 | 01-06-2018 | 07-05-2019 | 500.00 No | 500.00 No | 6.67 | 14.58 | 11. | Road Furniture | 489.00 No | 5.60 | 01-03-2018 | 25-05-2019 | 489.00 No | 489.00 No | 2.56 | 5.60 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 23.33 | 15-12-2018 | 30-05-2019 | 1.00 Job | 1.00 Job | 10.66 | 23.33 |
Total Amount: |
218.73 |
|
100 |
218.73 |
|
Remarks:
No Remarks
Work Program Made On:
04-01-2018 } ?>
Updation of work program on:
22-05-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-December-2017 | 14.58 lakh | 2. | 16-February-2018 | 15.32 lakh | 3. | 26-February-2018 | 0.86 lakh | 4. | 28-March-2018 | 5.27 lakh | 5. | 23-May-2018 | 2.47 lakh | 6. | 30-June-2018 | 14.30 lakh | 7. | 08-August-2018 | 3.00 lakh | 8. | 25-September-2018 | 16.61 lakh | 9. | 21-December-2018 | 1.59 lakh | 10. | 31-December-2018 | 5.58 lakh | 11. | 19-January-2019 | 37.31 lakh | 12. | 13-February-2019 | 30.10 lakh | 13. | 25-February-2019 | 3.41 lakh | 14. | 30-March-2019 | 7.87 lakh | 15. | 17-May-2019 | 5.99 lakh | 16. | 31-May-2019 | 3.45 lakh | 17. | 18-June-2019 | 2.66 lakh | 18. | 29-June-2019 | 25.71 lakh |
Total |
196.08 lakh |
% Payment | 89.64 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 266 No. of Test Done : 266 No. of Test Passed : 266 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 32 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-03-2019 | 11+950 | PC work in progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
2. | 24-03-2019 | 8+200 | Rolling work progress over seal coat | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
3. | 23-03-2019 | 7+475 | SE ,WB PWD vizit at pakage 121 | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
4. | 01-02-2019 | Ch-7+000 | Snow fall at pakage 121 | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
5. | 01-02-2019 | 11+400 | CME PIU site vizit | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
6. | 28-12-2018 | 12+700 | PC work on progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
7. | 30-08-2018 | Ch.12+400 | Casting of culvert slab | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
8. | 30-08-2018 | 12+675 | 1m span slab casting work | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
9. | 04-08-2018 | Ch.9+975 | Construction schedule informatory Board | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
10. | 20-06-2018 | 13.050 | Aggregate impact value checking | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
11. | 20-06-2018 | Ch.8+850 | H.P.stone filling work in back of culvert abutments | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
12. | 28-05-2018 | Ch 8.425 | Construction of culvert in progress | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
13. | 23-05-2018 | Site Office | Meeting with Sarpanch by world bank mission | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
14. | 23-05-2018 | Labour camp | Checking of labour camp | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
15. | 23-05-2018 | Site lab | Inspection of Site Lab by world bank mission | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
16. | 22-05-2018 | Ch 12.500 | inspection of culvert by world bank mission | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
17. | 22-05-2018 | Ch 10.025 | Site inspection by world Bank mission | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
18. | 22-05-2018 | Ch 8.425 | Inspection of culvert by world bank mission | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
19. | 22-05-2018 | Ch 0.00 | World bank mission visit | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
20. | 11-05-2018 | Ch 12.225 | Construction of hill side drain | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
|
|