Shishu Mandir-Nanasen Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2347 |
Sanction Cost: |
182.38 lakh |
Length:
|
2.750 KM. |
District: |
Pithoragarh |
Block: |
Munsiari |
Constituency: |
Dharchula |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 35
Package Name: 
UDRP/PWD/07/16/RD/035
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 27-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/16/RD/035
Contractor Name: Dwarika Projects Limited
|
Start Date: 03-11-2014
Intended Completion Date: 15-04-2019
Original End Date: 02-02-2016 |
Total Bond Cost: 78211526 (782.12 lakh)
Variation Cost: 21090687.36 (210.91 lakh) Hence Total Bond Cost is 99302213.36 (993.02 lakh)
|
Sub Project Cost: 153.83 lakh
Variation Cost of Sub Project: -3648851.57 (-36.49 lakh)
Total Sub Project Cost:
117.34 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2111724 for 54 days
LD Analysis for Milestone2: calculated LD is Rs 1290498 for 33 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 308.00 m | 38.53 | 01-06-2015 | 15-10-2017 | 214.00 m | 214.00 m | 29.68 | 38.53 | 2. | G-3 | 1.25 KM | 4.47 | 15-02-2016 | 30-04-2016 | 1.25 KM | 1.25 KM | 3.44 | 4.47 | 3. | PC/CC i/c Prime Coat, Tack Coat | 2.75 KM | 48.49 | 01-04-2015 | 15-06-2016 | 2.75 KM | 2.75 KM | 37.35 | 48.49 | 4. | Cause Way | 1.00 No | 2.86 | 01-02-2017 | 10-02-2018 | 1.00 No | 1.00 No | 2.2 | 2.86 | 5. | Culverts/Scupper | 2.00 No | 4.87 | 25-12-2017 | 10-02-2018 | 1.00 No | 1.00 No | 3.75 | 4.87 | 6. | longitudinal Drain | 2215.00 m | 18.81 | 25-09-2015 | 31-12-2017 | 2215.00 m | 2215.00 m | 14.49 | 18.81 | 7. | Parapet | 275.00 No | 5.71 | 11-01-2016 | 02-05-2016 | 250.00 No | 250.00 No | 4.4 | 5.71 | 8. | Road Furniture | 41.00 No | 1.53 | 01-02-2018 | 15-03-2018 | 39.00 No | 39.00 No | 1.18 | 1.53 | 9. | Other Allied Works & Finishing Work | 1.00 Job | 4.55 | 01-02-2018 | 15-03-2018 | 1.00 Job | 1.00 Job | 3.51 | 4.55 |
Total Amount: |
129.82 |
|
100 |
129.82 |
|
Remarks:
No Remarks
Work Program Made On:
25-09-2015 } ?>
Updation of work program on:
29-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-August-2015 | 17.56 lakh | 2. | 29-September-2015 | 2.27 lakh | 3. | 08-January-2016 | 6.83 lakh | 4. | 18-March-2016 | 5.37 lakh | 5. | 30-June-2016 | 39.50 lakh | 6. | 27-July-2016 | 4.14 lakh | 7. | 31-March-2017 | 7.86 lakh | 8. | 26-November-2017 | 0.27 lakh | 9. | 16-February-2018 | 3.14 lakh | 10. | 27-February-2018 | 3.35 lakh | 11. | 30-May-2018 | 0.83 lakh | 12. | 07-August-2018 | 13.20 lakh | 13. | 20-November-2018 | 10.21 lakh | 14. | 26-December-2018 | 1.00 lakh | 15. | 27-December-2018 | 13.01 lakh | 16. | 15-February-2019 | 9.41 lakh | 17. | 12-March-2019 | 7.83 lakh | 18. | 31-May-2019 | 11.85 lakh | 19. | 22-June-2019 | 6.83 lakh |
Total |
164.46 lakh |
% Payment | 140.16 % |
|
Advance Amount: 88.43 lakh
Recovered Amount: 88.43 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 438 No. of Test Done : 443 No. of Test Passed : 438 No. of Test Failed : 5 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.71 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 58 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-02-2018 | 0*300 | Wire crate wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
2. | 03-02-2018 | 0*350 | Edge wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
3. | 21-11-2017 | 2+300 | White washing on parapet in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
4. | 10-10-2017 | 1+751 | Checking of chocked drain | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
5. | 22-07-2017 | 1+600 | Tree planting | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
6. | 22-07-2017 | 0+850 | Tree planting | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
7. | 22-07-2017 | 0+750 | Tree planting | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
8. | 06-10-2016 | 2+230 | Visit for S.E. Sir | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
9. | 06-10-2016 | 0+150 | Excavation in pacca drain | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
10. | 18-07-2016 | 2+500 | Road damage by havie ranfall | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
11. | 13-06-2016 | 1+580 | Visit for TL sir & RE sir | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
12. | 13-06-2016 | 0+600 | Excavation in k.c.drain | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
13. | 07-06-2016 | 0+000 | Tack coat | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
14. | 28-05-2016 | 0+700 | Side drain excavation in progress | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
15. | 28-05-2016 | 0+675 | Drain excavation in progress | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
16. | 27-05-2016 | 0+015 | Tack coat | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
17. | 27-05-2016 | 0+000 | Surface cleaning | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
18. | 27-05-2016 | Tack coat | Tack coat | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
19. | 27-05-2016 | 2+675 | P.C.Work in progress | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
20. | 26-05-2016 | 2+675 | Surface cleaning | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
|
|