Shaid Pushker Singh Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2346 |
Sanction Cost: |
234.69 lakh |
Length:
|
1.875 KM. |
District: |
Pithoragarh |
Block: |
Munsiari |
Constituency: |
Dharchula |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 35
Package Name: 
UDRP/PWD/07/16/RD/035
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 27-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/16/RD/035
Contractor Name: Dwarika Projects Limited
|
Start Date: 03-11-2014
Intended Completion Date: 15-04-2019
Original End Date: 02-02-2016 |
Total Bond Cost: 78211526 (782.12 lakh)
Variation Cost: 21090687.36 (210.91 lakh) Hence Total Bond Cost is 99302213.36 (993.02 lakh)
|
Sub Project Cost: 156.71 lakh
Variation Cost of Sub Project: 6792592.53 (67.93 lakh)
Total Sub Project Cost:
224.64 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2111724 for 54 days
LD Analysis for Milestone2: calculated LD is Rs 1290498 for 33 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.20 KM | 3.70 | 16-09-2015 | 31-10-2017 | 1.20 KM | 1.20 KM | 2.07 | 3.70 | 2. | R/Wall, B/ Wall Type Protection works | 508.00 m | 43.91 | 03-11-2014 | 28-02-2018 | 508.00 m | 508.00 m | 24.51 | 43.91 | 3. | GSB/RBI/G-1 | 1.88 KM | 16.35 | 25-11-2015 | 02-03-2018 | 1.88 KM | 1.88 KM | 9.12 | 16.35 | 4. | G-2 | 1.88 KM | 10.44 | 15-02-2016 | 05-03-2018 | 1.88 KM | 1.88 KM | 5.83 | 10.44 | 5. | G-3 | 1.88 KM | 11.60 | 15-03-2018 | 15-04-2018 | 1.88 KM | 1.88 KM | 6.48 | 11.60 | 6. | PC/CC i/c Prime Coat, Tack Coat | 1.88 KM | 36.35 | 15-04-2018 | 15-05-2018 | 1.88 KM | 1.88 KM | 20.29 | 36.35 | 7. | Cause Way | 3.00 No | 4.15 | 25-12-2015 | 31-12-2016 | 3.00 No | 3.00 No | 2.32 | 4.15 | 8. | Culverts/Scupper | 10.00 No | 25.03 | 03-11-2014 | 15-03-2016 | 10.00 No | 10.00 No | 13.97 | 25.03 | 9. | longitudinal Drain | 1590.00 m | 12.29 | 01-05-2015 | 31-03-2018 | 1590.00 m | 1590.00 m | 6.86 | 12.29 | 10. | Crash Barrier | 250.00 m | 5.91 | 01-05-2018 | 20-05-2018 | 250.00 m | 250.00 m | 3.3 | 5.91 | 11. | Parapet | 100.00 No | 4.05 | 01-02-2018 | 31-03-2018 | 100.00 No | 100.00 No | 2.26 | 4.05 | 12. | Road Furniture | 29.00 No | 1.16 | 15-05-2018 | 31-05-2018 | 27.00 No | 27.00 No | 0.65 | 1.16 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 4.23 | 15-05-2018 | 31-05-2018 | 1.00 Job | 1.00 Job | 2.36 | 4.23 |
Total Amount: |
179.17 |
|
100 |
179.17 |
|
Remarks:
No Remarks
Work Program Made On:
25-09-2015 } ?>
Updation of work program on:
29-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2015 | 13.24 lakh | 2. | 06-June-2015 | 6.87 lakh | 3. | 22-August-2015 | 25.90 lakh | 4. | 29-September-2015 | 13.02 lakh | 5. | 08-January-2016 | 21.97 lakh | 6. | 18-March-2016 | 1.45 lakh | 7. | 27-July-2016 | 4.40 lakh | 8. | 31-March-2017 | 1.77 lakh | 9. | 16-February-2018 | 17.84 lakh | 10. | 27-February-2018 | 8.37 lakh | 11. | 27-March-2018 | 7.29 lakh | 12. | 30-May-2018 | 51.90 lakh | 13. | 07-August-2018 | 21.17 lakh | 14. | 29-October-2018 | 13.35 lakh | 15. | 20-November-2018 | 0.45 lakh | 16. | 26-December-2018 | 2.00 lakh | 17. | 27-December-2018 | 7.78 lakh | 18. | 12-March-2019 | 2.30 lakh | 19. | 31-May-2019 | 1.51 lakh | 20. | 22-June-2019 | 2.87 lakh |
Total |
225.45 lakh |
% Payment | 100.36 % |
|
Advance Amount: 88.43 lakh
Recovered Amount: 88.43 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 438 No. of Test Done : 443 No. of Test Passed : 438 No. of Test Failed : 5 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.97 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 62 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 17-01-2018 | 0+600 | Gabion wall work in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
2. | 17-01-2018 | 0+020 | Plum concrete wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
3. | 15-01-2018 | 0+600 | Wire create work | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
4. | 02-01-2018 | 0+220 | B/wall banded | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
5. | 31-12-2017 | 0+220 | Breast wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
6. | 31-12-2017 | 0+425 | Plum concrete for wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
7. | 27-12-2017 | 0+220 | B/wall banded | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
8. | 21-12-2017 | 0+220 | R/wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
9. | 19-12-2017 | 0+450 | Edge wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
10. | 19-12-2017 | 0+280 | Edge wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
11. | 19-12-2017 | 0+220 | R/wall 1:5 | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
12. | 18-12-2017 | 0+300 | Edge wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
13. | 18-12-2017 | 0+220 | R/wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
14. | 17-12-2017 | 0+220 | R/wall rr1:5 | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
15. | 16-12-2017 | 0+200 | Excavation of edging wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
16. | 16-12-2017 | 0+300 | Excavation of edging wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
17. | 15-12-2017 | 0+650 | R /wall dry | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
18. | 15-12-2017 | 0+0220 | R/wall | Ravindra Singh Dafouti | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
19. | 08-12-2017 | 0+500 | CE sir site visit | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
20. | 08-12-2017 | 0+500 | CE sir visit | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
|
|