Munsyari Dandadhar Janti MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
2335 |
Sanction Cost: |
258.61 lakh |
Length:
|
5.500 KM. |
District: |
Pithoragarh |
Block: |
Munsiari |
Constituency: |
Dharchula |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 34
Package Name: 
UDRP/PWD/07/16/RD/034
Tender Date: 04-07-2015
Current Status: Agreement signed
Achieved on Date: 21-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/16/RD/034
Contractor Name: Kunwar Construction JV
|
Start Date: 28-09-2015
Intended Completion Date: 15-04-2019
Original End Date: 27-12-2016 |
Total Bond Cost: 44139515.92 (441.4 lakh)
Variation Cost: 5725720.50 (57.26 lakh) Hence Total Bond Cost is 49865236.42 (498.65 lakh)
|
Sub Project Cost: 183.75 lakh
Variation Cost of Sub Project: 4537608.40 (45.38 lakh)
Total Sub Project Cost:
229.13 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 4502280 for 204 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 505.50 m | 55.15 | 29-09-2015 | 31-01-2018 | 505.50 m | 505.50 m | 29.5 | 55.15 | 2. | GSB/RBI/G-1 | 0.70 KM | 7.01 | 03-09-2016 | 20-12-2016 | 0.70 KM | 0.70 KM | 3.75 | 7.01 | 3. | G-2 | 1.50 KM | 9.54 | 12-09-2016 | 31-12-2016 | 1.50 KM | 1.50 KM | 5.1 | 9.54 | 4. | G-3 | 1.50 KM | 15.72 | 28-09-2016 | 07-10-2017 | 1.50 KM | 1.50 KM | 8.41 | 15.72 | 5. | PC/CC i/c Prime Coat, Tack Coat | 3.50 KM | 46.34 | 01-05-2018 | 30-05-2018 | 4.70 KM | 4.70 KM | 24.79 | 46.34 | 6. | BM i/c Prime Coat, Tack Coat | 0.00 KM | 0.00 | 21-04-2016 | 21-06-2016 | 0.00 KM | 0.00 KM | 0 | 0.00 | 7. | Cause Way | 2.00 No | 6.97 | 07-10-2017 | 15-04-2018 | 2.00 No | 2.00 No | 3.73 | 6.97 | 8. | Culverts/Scupper | 6.00 No | 20.03 | 25-02-2016 | 15-04-2018 | 8.00 No | 8.00 No | 10.72 | 20.03 | 9. | longitudinal Drain | 2125.00 m | 13.74 | 15-02-2016 | 31-03-2018 | 4500.00 m | 4500.00 m | 7.35 | 13.74 | 10. | Parapet | 440.00 No | 7.48 | 06-08-2016 | 30-04-2018 | 325.00 No | 325.00 No | 4 | 7.48 | 11. | Road Furniture | 82.00 No | 2.06 | 01-05-2018 | 30-05-2018 | 82.00 No | 82.00 No | 1.1 | 2.06 | 12. | Other Allied Works & Finishing Work | 2.00 Job | 2.90 | 01-11-2017 | 30-05-2018 | 2.00 Job | 2.00 Job | 1.55 | 2.90 |
Total Amount: |
186.94 |
|
100 |
186.94 |
|
Remarks:
No Remarks
Work Program Made On:
21-11-2015 } ?>
Updation of work program on:
29-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 08-January-2016 | 28.55 lakh | 2. | 04-February-2016 | 16.07 lakh | 3. | 05-March-2016 | 2.05 lakh | 4. | 30-March-2016 | 0.23 lakh | 5. | 12-May-2016 | 14.03 lakh | 6. | 26-October-2016 | 7.22 lakh | 7. | 08-December-2016 | 5.94 lakh | 8. | 02-January-2017 | 10.14 lakh | 9. | 06-February-2017 | 4.26 lakh | 10. | 09-March-2017 | 1.93 lakh | 11. | 30-April-2017 | 1.48 lakh | 12. | 31-May-2017 | 4.44 lakh | 13. | 31-August-2017 | 0.65 lakh | 14. | 10-November-2017 | 3.56 lakh | 15. | 16-February-2018 | 26.61 lakh | 16. | 27-March-2018 | 3.37 lakh | 17. | 16-May-2018 | 22.39 lakh | 18. | 30-May-2018 | 41.43 lakh | 19. | 07-August-2018 | 12.78 lakh | 20. | 29-October-2018 | 5.10 lakh | 21. | 07-December-2018 | 3.00 lakh | 22. | 27-December-2018 | 19.56 lakh | 23. | 15-February-2019 | 22.30 lakh | 24. | 12-March-2019 | 4.00 lakh | 25. | 30-March-2019 | 30.89 lakh | 26. | 22-June-2019 | 16.09 lakh |
Total |
308.07 lakh |
% Payment | 134.45 % |
|
Advance Amount: 51.45 lakh
Recovered Amount: 51.45 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 434 No. of Test Done : 434 No. of Test Passed : 434 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.29 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 123 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 18-08-2018 | 3+575 | Slip clearance | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
2. | 30-04-2018 | 3+300 | Rolling over sealcoat | Neeraj Kumar Tewari | AE | UDRP R&B Munsyari | See Pic |
3. | 07-04-2018 | 0+000 | Labour Health checkup C.H.C Munsyari | Laxman Singh Koranga | Field Engineer | DSC4 R&B WB Munsyari | See Pic |
4. | 03-02-2018 | 1+00 | Causeway work in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
5. | 21-01-2018 | 1+050 | Causeway PQC casting work in progress | Laxman Singh Koranga | Field Engineer | DSC4 R&B WB Munsyari | See Pic |
6. | 17-01-2018 | 1+00 | Gabion wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
7. | 24-12-2017 | 0+950 | Wire create work in progress | Laxman Singh Koranga | Field Engineer | DSC4 R&B WB Munsyari | See Pic |
8. | 24-12-2017 | 0+975 | Wire create work in progress | Laxman Singh Koranga | Field Engineer | DSC4 R&B WB Munsyari | See Pic |
9. | 20-12-2017 | Chainage 0.950 | Wire crate wall in progress | Prem Prakash | AE | UDRP R&B Munsyari | See Pic |
10. | 07-12-2017 | 4+650 | R/W work in progress | Laxman Singh Koranga | Field Engineer | DSC4 R&B WB Munsyari | See Pic |
11. | 26-11-2017 | 3+625 | Excavations for R/W | Laxman Singh Koranga | Field Engineer | DSC4 R&B WB Munsyari | See Pic |
12. | 21-11-2017 | 2+560 | Parapet work in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
13. | 10-10-2017 | 2+900 | Abutment work in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
14. | 10-09-2017 | 2+990 | Excavations for Calvert | Laxman Singh Koranga | Field Engineer | DSC4 R&B WB Munsyari | See Pic |
15. | 02-09-2017 | 3+525 | Road setellment due to heavy rain | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
16. | 02-09-2017 | 3+525 | Setellment of road due to heavy rain | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
17. | 23-07-2017 | 3+250 | Tree plantation | Laxman Singh Koranga | Field Engineer | DSC4 R&B WB Munsyari | See Pic |
18. | 11-07-2017 | 0+000 | Health Checkup report of Labour's CHC munsyari | Laxman Singh Koranga | Field Engineer | DSC4 R&B WB Munsyari | See Pic |
19. | 11-07-2017 | 0+000 | Health Checkup of Labour's in CHC Munsyari | Laxman Singh Koranga | Field Engineer | DSC4 R&B WB Munsyari | See Pic |
20. | 16-05-2017 | 2+625 | World bank mission inspection | Neeraj Kumar Tewari | AE | UDRP R&B Munsyari | See Pic |
|
|