Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Munsyari Dandadhar Janti MR Work Completed
Project: UDRP-RB UID: 2335 Sanction Cost: 258.61  lakh Length: 5.500 KM.
District: Pithoragarh Block: Munsiari Constituency: Dharchula Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 34        Package Name:  UDRP/PWD/07/16/RD/034        Tender Date: 04-07-2015        Current Status: Agreement signed        Achieved on Date: 21-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/16/RD/034      Contractor Name: Kunwar Construction JV
Start Date:  28-09-2015      Intended Completion Date:  15-04-2019      Original End Date:  27-12-2016
Total Bond Cost: 44139515.92 (441.4 lakh)        Variation Cost: 5725720.50 (57.26 lakh)    Hence Total Bond Cost is   49865236.42 (498.65 lakh) 
Sub Project Cost: 183.75  lakh        Variation Cost of Sub Project: 4537608.40  (45.38 lakh)       Total Sub Project Cost:   229.13 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 4502280 for 204 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works505.50 m55.1529-09-201531-01-2018505.50 m505.50 m29.555.15
2.GSB/RBI/G-10.70 KM7.0103-09-201620-12-20160.70 KM0.70 KM3.757.01
3.G-21.50 KM9.5412-09-201631-12-20161.50 KM1.50 KM5.19.54
4.G-31.50 KM15.7228-09-201607-10-20171.50 KM1.50 KM8.4115.72
5.PC/CC i/c Prime Coat, Tack Coat3.50 KM46.3401-05-201830-05-20184.70 KM4.70 KM24.7946.34
6.BM i/c Prime Coat, Tack Coat0.00 KM0.0021-04-201621-06-20160.00 KM0.00 KM00.00
7.Cause Way2.00 No6.9707-10-201715-04-20182.00 No2.00 No3.736.97
8.Culverts/Scupper 6.00 No20.0325-02-201615-04-20188.00 No8.00 No10.7220.03
9.longitudinal Drain2125.00 m13.7415-02-201631-03-20184500.00 m4500.00 m7.3513.74
10.Parapet440.00 No7.4806-08-201630-04-2018325.00 No325.00 No47.48
11.Road Furniture82.00 No2.0601-05-201830-05-201882.00 No82.00 No1.12.06
12.Other Allied Works & Finishing Work 2.00 Job2.9001-11-201730-05-20182.00 Job2.00 Job1.552.90
Total Amount: 186.94 100   186.94
Remarks: No Remarks       Work Program Made On: 21-11-2015        Updation of work program on: 29-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.08-January-201628.55  lakh
2.04-February-201616.07  lakh
3.05-March-20162.05  lakh
4.30-March-20160.23  lakh
5.12-May-201614.03  lakh
6.26-October-20167.22  lakh
7.08-December-20165.94  lakh
8.02-January-201710.14  lakh
9.06-February-20174.26  lakh
10.09-March-20171.93  lakh
11.30-April-20171.48  lakh
12.31-May-20174.44  lakh
13.31-August-20170.65  lakh
14.10-November-20173.56  lakh
15.16-February-201826.61  lakh
16.27-March-20183.37  lakh
17.16-May-201822.39  lakh
18.30-May-201841.43  lakh
19.07-August-201812.78  lakh
20.29-October-20185.10  lakh
21.07-December-20183.00  lakh
22.27-December-201819.56  lakh
23.15-February-201922.30  lakh
24.12-March-20194.00  lakh
25.30-March-201930.89  lakh
26.22-June-201916.09  lakh
Total 308.07  lakh
% Payment134.45 %
Advance Amount:  51.45  lakh        Recovered Amount:  51.45  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 434   No. of Test Done : 434    No. of Test Passed : 434   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.29
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 123
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-08-20183+575Slip clearanceShoyab AliJEUDRP R&B Munsyari See Pic
2.30-04-20183+300Rolling over sealcoatNeeraj Kumar TewariAEUDRP R&B Munsyari See Pic
3.07-04-20180+000Labour Health checkup C.H.C MunsyariLaxman Singh KorangaField EngineerDSC4 R&B WB Munsyari See Pic
4.03-02-20181+00Causeway work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
5.21-01-20181+050Causeway PQC casting work in progressLaxman Singh KorangaField EngineerDSC4 R&B WB Munsyari See Pic
6.17-01-20181+00Gabion wall in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
7.24-12-20170+950Wire create work in progressLaxman Singh KorangaField EngineerDSC4 R&B WB Munsyari See Pic
8.24-12-20170+975Wire create work in progressLaxman Singh KorangaField EngineerDSC4 R&B WB Munsyari See Pic
9.20-12-2017Chainage 0.950Wire crate wall in progressPrem PrakashAEUDRP R&B Munsyari See Pic
10.07-12-20174+650R/W work in progressLaxman Singh KorangaField EngineerDSC4 R&B WB Munsyari See Pic
11.26-11-20173+625Excavations for R/WLaxman Singh KorangaField EngineerDSC4 R&B WB Munsyari See Pic
12.21-11-20172+560Parapet work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
13.10-10-20172+900Abutment work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
14.10-09-20172+990Excavations for CalvertLaxman Singh KorangaField EngineerDSC4 R&B WB Munsyari See Pic
15.02-09-20173+525Road setellment due to heavy rainDinesh KumarREDSC4 R&B WB Munsyari See Pic
16.02-09-20173+525Setellment of road due to heavy rainDinesh KumarREDSC4 R&B WB Munsyari See Pic
17.23-07-20173+250Tree plantationLaxman Singh KorangaField EngineerDSC4 R&B WB Munsyari See Pic
18.11-07-20170+000Health Checkup report of Labour's CHC munsyariLaxman Singh KorangaField EngineerDSC4 R&B WB Munsyari See Pic
19.11-07-20170+000Health Checkup of Labour's in CHC MunsyariLaxman Singh KorangaField EngineerDSC4 R&B WB Munsyari See Pic
20.16-05-20172+625World bank mission inspectionNeeraj Kumar TewariAEUDRP R&B Munsyari See Pic