Madkot Bauna
Work Completed
|
Project: |
UDRP-RB |
UID: |
2334 |
Sanction Cost: |
3429.70 lakh |
Length:
|
24.500 KM. |
District: |
Pithoragarh |
Block: |
Munsiari |
Constituency: |
Dharchula |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 112
Package Name: 
UDRP/PWD/07/16/RD/101
Tender Date: 10-04-2015
Current Status: Agreement signed
Achieved on Date: 26-08-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/16/RD/101
Contractor Name: M/S.Dalip Singh Adhikari
|
Start Date: 02-09-2015
Intended Completion Date: 30-04-2018
Original End Date: 01-12-2016 |
Total Bond Cost: 210812767.6 (2108.13 lakh)
Variation Cost: 123739530.79 (1237.4 lakh) Hence Total Bond Cost is 334552298.39 (3345.52 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 23.63 KM | 305.62 | 02-09-2015 | 30-01-2017 | 23.63 KM | 23.63 KM | 10.13 | 305.62 | 2. | R/Wall, B/ Wall Type Protection works | 9298.00 m | 922.94 | 02-09-2015 | 30-12-2017 | 9298.00 m | 9298.00 m | 30.58 | 922.94 | 3. | G-2 | 23.63 KM | 424.28 | 15-02-2016 | 15-10-2017 | 23.63 KM | 23.63 KM | 14.06 | 424.28 | 4. | G-3 | 23.63 KM | 200.44 | 31-10-2016 | 28-01-2018 | 23.63 KM | 23.63 KM | 6.64 | 200.44 | 5. | PC/CC i/c Prime Coat, Tack Coat | 24.13 KM | 376.17 | 20-05-2017 | 15-01-2018 | 24.13 KM | 24.13 KM | 12.46 | 376.17 | 6. | Cause Way | 29.00 No | 122.65 | 01-02-2016 | 30-01-2018 | 26.00 No | 26.00 No | 4.06 | 122.65 | 7. | Culverts/Scupper | 141.00 No | 438.18 | 02-09-2015 | 30-01-2018 | 130.00 No | 130.00 No | 14.52 | 438.18 | 8. | longitudinal Drain | 23333.00 m | 59.57 | 01-10-2016 | 31-12-2017 | 23333.00 m | 23333.00 m | 1.97 | 59.57 | 9. | Crash Barrier | 2910.00 m | 72.75 | 01-04-2017 | 22-05-2017 | 2910.00 m | 2910.00 m | 2.41 | 72.75 | 10. | Parapet | 1231.00 No | 38.22 | 15-01-2017 | 15-03-2018 | 2300.00 No | 2300.00 No | 1.27 | 38.22 | 11. | Road Furniture | 1786.00 No | 19.02 | 01-04-2018 | 30-04-2018 | 1786.00 No | 1786.00 No | 0.63 | 19.02 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 38.53 | 01-04-2018 | 30-04-2018 | 1.00 Job | 1.00 Job | 1.28 | 38.53 |
Total Amount: |
3018.37 |
|
100 |
3018.37 |
|
Remarks:
No Remarks
Work Program Made On:
28-09-2015 } ?>
Updation of work program on:
13-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-September-2015 | 154.61 lakh | 2. | 30-October-2015 | 107.20 lakh | 3. | 26-December-2015 | 121.48 lakh | 4. | 30-January-2016 | 120.51 lakh | 5. | 29-February-2016 | 405.36 lakh | 6. | 30-March-2016 | 73.62 lakh | 7. | 24-May-2016 | 55.48 lakh | 8. | 30-July-2016 | 71.97 lakh | 9. | 26-October-2016 | 123.29 lakh | 10. | 23-December-2016 | 126.46 lakh | 11. | 30-January-2017 | 122.28 lakh | 12. | 24-February-2017 | 110.65 lakh | 13. | 31-March-2017 | 195.51 lakh | 14. | 30-April-2017 | 79.91 lakh | 15. | 31-May-2017 | 133.32 lakh | 16. | 21-June-2017 | 104.87 lakh | 17. | 30-June-2017 | 135.56 lakh | 18. | 13-July-2017 | 22.71 lakh | 19. | 31-August-2017 | 7.87 lakh | 20. | 10-November-2017 | 92.79 lakh | 21. | 26-November-2017 | 140.59 lakh | 22. | 26-December-2017 | 95.73 lakh | 23. | 14-January-2018 | 55.79 lakh | 24. | 16-February-2018 | 95.56 lakh | 25. | 27-February-2018 | 88.23 lakh | 26. | 27-March-2018 | 120.86 lakh | 27. | 20-April-2018 | 101.97 lakh | 28. | 23-May-2018 | 106.15 lakh | 29. | 06-June-2018 | 22.31 lakh | 30. | 29-September-2018 | 70.38 lakh | 31. | 29-October-2018 | 152.87 lakh |
Total |
3415.89 lakh |
% Payment |
102.11 % |
|
Advance Amount: 210.00 lakh
Recovered Amount: 210.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1124 No. of Test Done : 1149 No. of Test Passed : 1124 No. of Test Failed : 25 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.18 |
Number of Notice(s) issued: 90 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 276 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 02-04-2018 | 22+ 650 | Rolling on pc surface . | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
2. | 02-04-2018 | 22+650 | Rolling on PC Surface with tandem Roller . | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
3. | 02-04-2018 | 22+600 | PC work in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
4. | 01-04-2018 | 22+750 | Rolling work on Seal coat at madkote-bona motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
5. | 01-04-2018 | 22+890 | Rolling work on PC at madkote-bona motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
6. | 01-04-2018 | 24+020 | Rolling work on PC at madkote-bona motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
7. | 01-04-2018 | 23+100 | Rolling work on PC at madkote-bona motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
8. | 31-03-2018 | 22+600 | Laying PC at madkote-bona motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
9. | 30-03-2018 | Km23 | Pri mix carpet rolling work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
10. | 19-03-2018 | 16+400 | Air pollution test | Ajay Rathore | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
11. | 19-03-2018 | 00+010 | Noice test | Ajay Rathore | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
12. | 03-02-2018 | 20+750 | Steel reinforcement for bed bl0ck in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
13. | 17-01-2018 | 16+400 | Collie wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
14. | 17-01-2018 | 16+700 | Parapet work in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
15. | 16-01-2018 | 16+700 | Parapet casting in progress | Ajay Rathore | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
16. | 16-01-2018 | 16+700 | Parapet work in progress at madkote-Bona motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
17. | 19-12-2017 | 19+850 | Wire crate work in progress | Ajay Rathore | Site Supervisor | DSC4 R&B WB Munsyari | See Pic |
18. | 08-12-2017 | 24+000 | CE sir site visit | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
19. | 08-12-2017 | 24+100 | CE sir site visit | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
20. | 08-12-2017 | 10+500 | Shoulder and Drain work in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
|
|