Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Madanpur Nani motor road Work Completed
Project: UDRP-RB UID: 2333 Sanction Cost: 972.41  lakh Length: 10.200 KM.
District: Pithoragarh Block: Gangolihat Constituency: Gangolihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 114        Package Name:  UDRP/PWD/07/15/RD/103        Tender Date: 10-04-2015        Current Status: Agreement signed        Achieved on Date: 21-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/15/RD/103      Contractor Name: GDS Infrastructure
Start Date:  28-07-2015      Intended Completion Date:  31-05-2018      Original End Date:  27-10-2016
Total Bond Cost: 76467874.61 (764.68 lakh)        Variation Cost: 16394378.87 (163.94 lakh)    Hence Total Bond Cost is   92862253.48 (928.62 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 688212 for 18 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence10.12 KM98.6428-07-201515-09-201710.12 KM10.12 KM10.998.64
2.R/Wall, B/ Wall Type Protection works2567.00 m269.9928-07-201530-09-20172567.00 m2567.00 m29.84269.99
3.G-210.12 KM115.3903-12-201515-01-201810.12 KM10.12 KM12.75115.39
4.G-310.12 KM75.4701-04-201631-01-201810.12 KM10.12 KM8.3475.47
5.PC/CC i/c Prime Coat, Tack Coat10.12 KM127.7115-04-201625-05-201810.12 KM10.12 KM14.12127.71
6.Cause Way6.00 No20.8725-02-201630-11-20165.00 No5.00 No2.3120.87
7.Culverts/Scupper 38.00 No105.0404-12-201531-07-201738.00 No38.00 No11.61105.04
8.longitudinal Drain9271.00 m35.4301-03-201630-04-20189271.00 m9271.00 m3.9235.43
9.Crash Barrier0.00 m0.0001-01-201708-01-20170.00 m0.00 m00.00
10.Parapet532.00 No5.7401-06-201615-03-2018430.00 No430.00 No0.635.74
11.Road Furniture955.00 No9.1201-05-201731-05-2018955.00 No955.00 No1.019.12
12.Other Allied Works & Finishing Work 2.00 Job41.3401-05-201831-05-20182.00 Job2.00 Job4.5741.34
Total Amount: 904.74 100   904.74
Remarks: No Remarks       Work Program Made On: 28-09-2015        Updation of work program on: 29-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-September-201546.66  lakh
2.31-October-201537.62  lakh
3.30-December-201588.56  lakh
4.18-February-201650.22  lakh
5.09-March-201640.83  lakh
6.30-March-201627.94  lakh
7.24-May-201670.12  lakh
8.30-June-201634.60  lakh
9.31-August-201613.75  lakh
10.30-September-201645.93  lakh
11.22-November-201622.42  lakh
12.02-January-201719.10  lakh
13.31-May-201730.71  lakh
14.21-June-201736.70  lakh
15.31-August-20176.36  lakh
16.10-November-201710.76  lakh
17.26-November-201748.20  lakh
18.07-December-201731.52  lakh
19.30-December-201734.25  lakh
20.16-February-201814.46  lakh
21.27-February-201846.26  lakh
22.27-March-201851.68  lakh
23.23-May-201838.70  lakh
24.29-September-201881.07  lakh
25.27-October-201815.00  lakh
26.22-June-20194.88  lakh
Total 948.3  lakh
% Payment 102.14 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 500   No. of Test Done : 500    No. of Test Passed : 500   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.23
Number of Notice(s) issued: 83

Mobile Pic Upload

Number of Pics Available on Web Repository: 235
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.14-01-20188+900Sure visit with EESir and AE sirDinesh KumarREDSC4 R&B WB Munsyari See Pic
2.05-01-20186+050Parapet work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
3.06-10-20178+600Width checking of WBM 1st layerDinesh KumarREDSC4 R&B WB Munsyari See Pic
4.06-10-20179+850Width checking during hill cuttingDinesh KumarREDSC4 R&B WB Munsyari See Pic
5.21-03-20177.450Plum work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
6.09-01-20176.700Hillside cuttingPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
7.07-01-20176.600Hillside cuttingPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
8.19-12-20166.425Hillside cuttingPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
9.19-12-20166.425Hillside cuttingPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
10.17-12-20161+300AIV Test for G2 aggregate result found 27 %Dinesh KumarREDSC4 R&B WB Munsyari See Pic
11.17-12-20162+125Dry R/ W work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
12.03-12-20162+300Site visit of TL sir and EE sir at ch 2+300Dinesh KumarREDSC4 R&B WB Munsyari See Pic
13.03-12-20162+700Rolling on pc surfaceDinesh KumarREDSC4 R&B WB Munsyari See Pic
14.08-11-20162.360Thickness checking of pc found 23mmPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
15.08-11-20162.350PC work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
16.06-11-20161.350PC work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
17.05-11-20161.800Premix carpetPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
18.05-11-20161.325Ambient air quality test runningPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
19.03-11-2016Chainage 1.400PC work in progressPrem PrakashAEUDRP R&B Munsyari See Pic
20.02-11-2016Chainage 1.500PC work in progressPrem PrakashAEUDRP R&B Munsyari See Pic