Kunalta motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2331 |
Sanction Cost: |
1220.10 lakh |
Length:
|
10.500 KM. |
District: |
Pithoragarh |
Block: |
Gangolihat |
Constituency: |
Gangolihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 136
Package Name: 
UDRP/PWD/07/RD/120
Tender Date: 07-04-2017
Current Status: Agreement signed
Achieved on Date: 14-11-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/RD/120
Contractor Name: Dinesh Chandra Patni
|
Start Date: 21-11-2017
Intended Completion Date: 15-06-2019
Original End Date: 20-02-2019 |
Total Bond Cost: 103717243.78 (1037.17 lakh)
Variation Cost: 17501106.75 (175.01 lakh) Hence Total Bond Cost is 121218350.53 (1212.18 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 11305262 for 218 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 10.18 KM | 92.52 | 21-11-2017 | 31-03-2018 | 10.18 KM | 10.18 KM | 7.63 | 92.52 | 2. | R/Wall, B/ Wall Type Protection works | 2749.00 m | 327.67 | 01-01-2018 | 31-12-2018 | 2749.00 m | 2749.00 m | 27.03 | 327.67 | 3. | G-2 | 20.36 KM | 173.42 | 01-03-2018 | 30-09-2018 | 20.36 KM | 20.36 KM | 14.31 | 173.42 | 4. | G-3 | 10.18 KM | 97.75 | 01-06-2018 | 31-10-2018 | 10.18 KM | 10.18 KM | 8.06 | 97.75 | 5. | PC/CC i/c Prime Coat, Tack Coat | 10.18 KM | 133.35 | 01-04-2019 | 15-06-2019 | 10.18 KM | 10.18 KM | 11 | 133.35 | 6. | Cause Way | 16.00 No | 75.90 | 01-07-2018 | 31-10-2018 | 16.00 No | 16.00 No | 6.26 | 75.90 | 7. | Culverts/Scupper | 52.00 No | 201.26 | 15-12-2017 | 30-10-2018 | 52.00 No | 52.00 No | 16.6 | 201.26 | 8. | longitudinal Drain | 10500.00 m | 23.58 | 15-05-2018 | 15-05-2019 | 10180.00 m | 10180.00 m | 1.95 | 23.58 | 9. | Crash Barrier | 0.00 m | 0.00 | 01-12-2018 | 01-12-2018 | 0.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 681.00 No | 25.12 | 01-10-2018 | 20-02-2019 | 681.00 No | 681.00 No | 2.07 | 25.12 | 11. | Road Furniture | 750.00 No | 12.83 | 01-01-2019 | 15-04-2019 | 750.00 No | 750.00 No | 1.06 | 12.83 | 12. | Other Allied Works & Finishing Work | 4.00 Job | 48.78 | 01-01-2019 | 15-06-2019 | 4.00 Job | 4.00 Job | 4.02 | 48.78 |
Total Amount: |
1212.18 |
|
100 |
1212.18 |
|
Remarks:
No Remarks
Work Program Made On:
06-01-2018 } ?>
Updation of work program on:
13-05-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-December-2017 | 40.43 lakh | 2. | 16-February-2018 | 106.33 lakh | 3. | 01-March-2018 | 91.66 lakh | 4. | 27-March-2018 | 97.83 lakh | 5. | 23-May-2018 | 77.93 lakh | 6. | 30-May-2018 | 86.18 lakh | 7. | 07-August-2018 | 59.94 lakh | 8. | 29-September-2018 | 87.85 lakh | 9. | 29-October-2018 | 64.74 lakh | 10. | 30-November-2018 | 55.07 lakh | 11. | 27-December-2018 | 79.27 lakh | 12. | 21-January-2019 | 87.73 lakh | 13. | 15-February-2019 | 29.74 lakh | 14. | 30-March-2019 | 28.17 lakh | 15. | 17-May-2019 | 85.65 lakh | 16. | 12-June-2019 | 52.67 lakh | 17. | 30-June-2019 | 36.99 lakh |
Total |
1168.18 lakh |
% Payment |
96.37 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 99 No. of Test Done : 101 No. of Test Passed : 99 No. of Test Failed : 2 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
Number of Notice(s) issued: 12 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 27 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 18-05-2019 | At plant site | Bitumin extraction at plant site | Prem Prakash | AE | UDRP R&B Munsyari | See Pic |
2. | 18-05-2019 | At plant site | Bitumin extraction test at plant | Prem Prakash | AE | UDRP R&B Munsyari | See Pic |
3. | 18-05-2019 | Ch 0.850 | PC laying work in progress | Prem Prakash | AE | UDRP R&B Munsyari | See Pic |
4. | 17-05-2019 | 1+800 | P.C. laying work in progress | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
5. | 08-05-2019 | 6+350 | P.C. laying work in progress | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
6. | 12-11-2018 | Chainage 2.700 | Water sprinkling in progress | Prem Prakash | AE | UDRP R&B Munsyari | See Pic |
7. | 12-10-2018 | Chainage 6.550 | G3 laying in progress | Prem Prakash | AE | UDRP R&B Munsyari | See Pic |
8. | 04-04-2018 | 2+100 | Thickness checking of G2 material | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
9. | 04-04-2018 | 0+00 | Site visit by SE Sir EE Sir and AE sir. | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
10. | 22-03-2018 | 2+375 | Thickness checking of G2 layer found 150 mm | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
11. | 22-03-2018 | 1+985 | Loose thickness checking of G2 material found120 mm. | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
12. | 22-03-2018 | Lab | Lab checking by CME Sir | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
13. | 23-02-2018 | In lab | Grading of G2 material | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
14. | 06-02-2018 | Aiv testing in lab | Aiv testing for G2 material result found 12.68 ,20.0, and 27.78. | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
15. | 06-02-2018 | Lab | Aiv testing in lab for G2 material | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
16. | 20-01-2018 | 8.450 | Hillside cutting work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
17. | 09-01-2018 | 8.100 | Hillside cutting work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
18. | 05-01-2018 | 7+900 | Hill cutting in progress cutting with rock breaker | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
19. | 31-12-2017 | 7.725 | Hillside cutting work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
20. | 26-12-2017 | 0+785 | Construction of culvert Abutment in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
|
|