Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kunalta motor road Work Completed
Project: UDRP-RB UID: 2331 Sanction Cost: 1220.10  lakh Length: 10.500 KM.
District: Pithoragarh Block: Gangolihat Constituency: Gangolihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 136        Package Name:  UDRP/PWD/07/RD/120        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/RD/120      Contractor Name: Dinesh Chandra Patni
Start Date:  21-11-2017      Intended Completion Date:  15-06-2019      Original End Date:  20-02-2019
Total Bond Cost: 103717243.78 (1037.17 lakh)        Variation Cost: 17501106.75 (175.01 lakh)    Hence Total Bond Cost is   121218350.53 (1212.18 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 11305262 for 218 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence10.18 KM92.5221-11-201731-03-201810.18 KM10.18 KM7.6392.52
2.R/Wall, B/ Wall Type Protection works2749.00 m327.6701-01-201831-12-20182749.00 m2749.00 m27.03327.67
3.G-220.36 KM173.4201-03-201830-09-201820.36 KM20.36 KM14.31173.42
4.G-310.18 KM97.7501-06-201831-10-201810.18 KM10.18 KM8.0697.75
5.PC/CC i/c Prime Coat, Tack Coat10.18 KM133.3501-04-201915-06-201910.18 KM10.18 KM11133.35
6.Cause Way16.00 No75.9001-07-201831-10-201816.00 No16.00 No6.2675.90
7.Culverts/Scupper 52.00 No201.2615-12-201730-10-201852.00 No52.00 No16.6201.26
8.longitudinal Drain10500.00 m23.5815-05-201815-05-201910180.00 m10180.00 m1.9523.58
9.Crash Barrier0.00 m0.0001-12-201801-12-20180.00 m0.00 m00.00
10.Parapet681.00 No25.1201-10-201820-02-2019681.00 No681.00 No2.0725.12
11.Road Furniture750.00 No12.8301-01-201915-04-2019750.00 No750.00 No1.0612.83
12.Other Allied Works & Finishing Work 4.00 Job48.7801-01-201915-06-20194.00 Job4.00 Job4.0248.78
Total Amount: 1212.18 100   1212.18
Remarks: No Remarks       Work Program Made On: 06-01-2018        Updation of work program on: 13-05-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-December-201740.43  lakh
2.16-February-2018106.33  lakh
3.01-March-201891.66  lakh
4.27-March-201897.83  lakh
5.23-May-201877.93  lakh
6.30-May-201886.18  lakh
7.07-August-201859.94  lakh
8.29-September-201887.85  lakh
9.29-October-201864.74  lakh
10.30-November-201855.07  lakh
11.27-December-201879.27  lakh
12.21-January-201987.73  lakh
13.15-February-201929.74  lakh
14.30-March-201928.17  lakh
15.17-May-201985.65  lakh
16.12-June-201952.67  lakh
17.30-June-201936.99  lakh
Total 1168.18  lakh
% Payment 96.37 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 99   No. of Test Done : 101    No. of Test Passed : 99   No. of Test Failed : 2   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.00
Number of Notice(s) issued: 12

Mobile Pic Upload

Number of Pics Available on Web Repository: 27
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-05-2019At plant siteBitumin extraction at plant sitePrem PrakashAEUDRP R&B Munsyari See Pic
2.18-05-2019At plant siteBitumin extraction test at plantPrem PrakashAEUDRP R&B Munsyari See Pic
3.18-05-2019Ch 0.850PC laying work in progressPrem PrakashAEUDRP R&B Munsyari See Pic
4.17-05-20191+800P.C. laying work in progressShoyab AliJEUDRP R&B Munsyari See Pic
5.08-05-20196+350P.C. laying work in progressShoyab AliJEUDRP R&B Munsyari See Pic
6.12-11-2018Chainage 2.700Water sprinkling in progressPrem PrakashAEUDRP R&B Munsyari See Pic
7.12-10-2018Chainage 6.550G3 laying in progressPrem PrakashAEUDRP R&B Munsyari See Pic
8.04-04-20182+100Thickness checking of G2 materialDinesh KumarREDSC4 R&B WB Munsyari See Pic
9.04-04-20180+00Site visit by SE Sir EE Sir and AE sir.Dinesh KumarREDSC4 R&B WB Munsyari See Pic
10.22-03-20182+375Thickness checking of G2 layer found 150 mmDinesh KumarREDSC4 R&B WB Munsyari See Pic
11.22-03-20181+985Loose thickness checking of G2 material found120 mm.Dinesh KumarREDSC4 R&B WB Munsyari See Pic
12.22-03-2018LabLab checking by CME SirDinesh KumarREDSC4 R&B WB Munsyari See Pic
13.23-02-2018In labGrading of G2 materialDinesh KumarREDSC4 R&B WB Munsyari See Pic
14.06-02-2018Aiv testing in labAiv testing for G2 material result found 12.68 ,20.0, and 27.78.Dinesh KumarREDSC4 R&B WB Munsyari See Pic
15.06-02-2018LabAiv testing in lab for G2 materialDinesh KumarREDSC4 R&B WB Munsyari See Pic
16.20-01-20188.450Hillside cutting work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
17.09-01-20188.100Hillside cutting work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
18.05-01-20187+900Hill cutting in progress cutting with rock breakerDinesh KumarREDSC4 R&B WB Munsyari See Pic
19.31-12-20177.725Hillside cutting work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
20.26-12-20170+785Construction of culvert Abutment in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic