Kqitee Sain Rathi Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2330 |
Sanction Cost: |
658.61 lakh |
Length:
|
6.500 KM. |
District: |
Pithoragarh |
Block: |
Munsiari |
Constituency: |
Dharchula |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 35
Package Name: 
UDRP/PWD/07/16/RD/035
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 27-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/16/RD/035
Contractor Name: Dwarika Projects Limited
|
Start Date: 03-11-2014
Intended Completion Date: 15-04-2019
Original End Date: 02-02-2016 |
Total Bond Cost: 78211526 (782.12 lakh)
Variation Cost: 21090687.36 (210.91 lakh) Hence Total Bond Cost is 99302213.36 (993.02 lakh)
|
Sub Project Cost: 471.58 lakh
Variation Cost of Sub Project: 17946946.40 (179.47 lakh)
Total Sub Project Cost:
651.05 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2111724 for 54 days
LD Analysis for Milestone2: calculated LD is Rs 1290498 for 33 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.00 KM | 12.07 | 16-09-2015 | 15-01-2016 | 2.00 KM | 2.00 KM | 1.99 | 12.07 | 2. | R/Wall, B/ Wall Type Protection works | 2025.00 m | 203.07 | 03-11-2014 | 31-10-2017 | 2025.00 m | 2025.00 m | 33.43 | 203.07 | 3. | GSB/RBI/G-1 | 6.05 KM | 56.91 | 25-09-2015 | 15-10-2017 | 6.05 KM | 6.05 KM | 9.37 | 56.91 | 4. | G-2 | 6.05 KM | 33.70 | 25-11-2015 | 25-10-2017 | 6.05 KM | 6.05 KM | 5.55 | 33.70 | 5. | G-3 | 6.05 KM | 37.44 | 11-10-2016 | 31-10-2017 | 6.05 KM | 6.05 KM | 6.16 | 37.44 | 6. | PC/CC i/c Prime Coat, Tack Coat | 6.05 KM | 117.29 | 15-03-2017 | 30-04-2018 | 6.05 KM | 6.05 KM | 19.31 | 117.29 | 7. | Cause Way | 5.00 No | 13.28 | 25-11-2015 | 31-10-2017 | 3.00 No | 3.00 No | 2.19 | 13.28 | 8. | Culverts/Scupper | 27.00 No | 82.95 | 03-11-2014 | 10-11-2017 | 27.00 No | 27.00 No | 13.66 | 82.95 | 9. | longitudinal Drain | 4300.00 m | 35.23 | 01-05-2015 | 15-06-2017 | 5905.00 m | 5905.00 m | 5.8 | 35.23 | 10. | Parapet | 600.00 No | 6.23 | 15-02-2016 | 31-01-2018 | 600.00 No | 600.00 No | 1.03 | 6.23 | 11. | Road Furniture | 93.00 No | 3.07 | 01-03-2018 | 31-03-2018 | 90.00 No | 90.00 No | 0.51 | 3.07 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 6.21 | 01-03-2018 | 31-03-2018 | 1.00 Job | 1.00 Job | 1.02 | 6.21 |
Total Amount: |
607.45 |
|
100 |
607.45 |
|
Remarks:
No Remarks
Work Program Made On:
25-09-2015 } ?>
Updation of work program on:
29-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2015 | 43.84 lakh | 2. | 06-June-2015 | 35.37 lakh | 3. | 22-August-2015 | 135.06 lakh | 4. | 29-September-2015 | 23.43 lakh | 5. | 08-January-2016 | 69.65 lakh | 6. | 18-March-2016 | 46.79 lakh | 7. | 30-June-2016 | 4.07 lakh | 8. | 27-July-2016 | 20.27 lakh | 9. | 31-March-2017 | 50.12 lakh | 10. | 31-May-2017 | 95.05 lakh | 11. | 26-November-2017 | 23.52 lakh | 12. | 16-February-2018 | 28.41 lakh | 13. | 27-February-2018 | 12.87 lakh | 14. | 27-March-2018 | 3.32 lakh | 15. | 30-May-2018 | 4.18 lakh | 16. | 07-August-2018 | 11.78 lakh | 17. | 29-October-2018 | 7.35 lakh | 18. | 20-November-2018 | 1.73 lakh | 19. | 26-December-2018 | 7.00 lakh | 20. | 27-December-2018 | 0.70 lakh | 21. | 15-February-2019 | 1.85 lakh | 22. | 12-March-2019 | 11.67 lakh | 23. | 31-May-2019 | 8.53 lakh | 24. | 22-June-2019 | 15.45 lakh |
Total |
662.01 lakh |
% Payment | 101.68 % |
|
Advance Amount: 88.43 lakh
Recovered Amount: 88.43 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 438 No. of Test Done : 443 No. of Test Passed : 438 No. of Test Failed : 5 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.98 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 165 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-02-2018 | 1+525 | Dry R/W wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
2. | 31-12-2017 | 4+450 | Construction of Retaining wall in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
3. | 02-09-2017 | 2+685 | Retaining wall damaged due to heavy rain | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
4. | 02-09-2017 | 4+ 650 | Land slide due to heavy rain | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
5. | 02-09-2017 | 4+320 and 4+475 | Both Retaining wall damaged due to heavy rain | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
6. | 02-09-2017 | 1+520 | Road damaged due to heavy rain | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
7. | 12-10-2016 | 0+050 | T l sir site visit checking of G3 stone | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
8. | 24-09-2016 | 0+175 | Site Visit for C.M.E. sir | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
9. | 24-09-2016 | 0+000 | Visit for C.M.E. sir | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
10. | 27-08-2016 | 2+600 | Site visit with AE Sir RE Sir | Girjesh Kumar Dubey | QC | DSC4 R&B WB Munsyari | See Pic |
11. | 18-07-2016 | 1+000 | Sleap clearance | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
12. | 18-07-2016 | 1+000 | Site visit exen sir | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
13. | 11-07-2016 | 0+010 | G2 layer damaged. By heavy. Rainfall. Or g2 layer. Washed out. Due to heavy rain | Ravindra Singh Dafouti | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
14. | 11-07-2016 | 0+080 | Dismantling. Of R/wall. By heavy rain | Ravindra Singh Dafouti | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
15. | 11-07-2016 | 0+500 | Dismantling. Of R/Wall. By heavy. Rain | Ravindra Singh Dafouti | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
16. | 11-07-2016 | 0+250 | Washing. G1&g2 | Ravindra Singh Dafouti | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
17. | 13-06-2016 | 5+100 | Box culvert casting | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
18. | 10-06-2016 | Chainage 5.100 | Construction of RCC Box Culvert | Prem Prakash | AE | UDRP R&B Munsyari | See Pic |
19. | 07-06-2016 | 5+100 | Visit of TL sir & RE sir | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
20. | 09-04-2016 | 1+100 | Hill cutting in progress | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
|
|