Ganai Bankot motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
2322 |
Sanction Cost: |
575.81 lakh |
Length:
|
13.000 KM. |
District: |
Pithoragarh |
Block: |
Gangolihat |
Constituency: |
Gangolihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 12
Package Name: 
UDRP/PWD/07/20/RD/012
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 06-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/20/RD/012
Contractor Name: ESPAN Infrastructure Ltd
|
Start Date: 20-08-2014
Intended Completion Date: 28-07-2016
Original End Date: 19-11-2015 |
Total Bond Cost: 48862983.5 (488.63 lakh)
Variation Cost: 5673825.41 (56.74 lakh) Hence Total Bond Cost is 54536808.91 (545.37 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 781792 for 32 days
LD Analysis for Milestone2: calculated LD is Rs 171017 for 7 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 1511.00 m | 108.97 | 20-08-2014 | 25-12-2015 | 1985.00 m | 1985.00 m | 22.37 | 108.97 | 2. | GSB/RBI/G-1 | 0.25 KM | 14.66 | 25-02-2016 | 15-03-2016 | 0.20 KM | 0.20 KM | 3.01 | 14.66 | 3. | G-3 | 0.35 KM | 2.76 | 25-09-2015 | 20-03-2016 | 0.35 KM | 0.35 KM | 0.57 | 2.76 | 4. | PC/CC i/c Prime Coat, Tack Coat | 13.00 KM | 135.46 | 15-04-2015 | 15-04-2016 | 13.00 KM | 13.00 KM | 27.81 | 135.46 | 5. | Cause Way | 17.00 No | 52.37 | 25-11-2015 | 25-03-2016 | 17.00 No | 17.00 No | 10.75 | 52.37 | 6. | Culverts/Scupper | 35.00 No | 60.49 | 20-08-2014 | 15-03-2016 | 27.00 No | 27.00 No | 12.42 | 60.49 | 7. | longitudinal Drain | 10850.00 m | 31.56 | 01-05-2015 | 15-03-2016 | 9350.00 m | 9350.00 m | 6.48 | 31.56 | 8. | Parapet | 1950.00 No | 77.63 | 11-12-2015 | 11-04-2016 | 1140.00 No | 1140.00 No | 15.94 | 77.63 | 9. | Road Furniture | 116.00 No | 3.26 | 15-02-2016 | 15-04-2016 | 118.00 No | 118.00 No | 0.67 | 3.26 |
Total Amount: |
487.16 |
|
100 |
487.16 |
|
Remarks:
No Remarks
Work Program Made On:
25-09-2015 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 06-June-2015 | 120.43 lakh | 2. | 27-August-2015 | 45.61 lakh | 3. | 30-September-2015 | 69.00 lakh | 4. | 30-October-2015 | 44.19 lakh | 5. | 21-December-2015 | 39.17 lakh | 6. | 30-January-2016 | 40.21 lakh | 7. | 09-March-2016 | 28.77 lakh | 8. | 30-March-2016 | 14.97 lakh | 9. | 30-April-2016 | 24.13 lakh | 10. | 25-May-2016 | 47.99 lakh | 11. | 26-October-2016 | 34.00 lakh | 12. | 24-February-2017 | 21.74 lakh |
Total |
530.21 lakh |
% Payment |
97.2 % |
|
Advance Amount: 48.86 lakh
Recovered Amount: 48.86 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 190 No. of Test Done : 212 No. of Test Passed : 190 No. of Test Failed : 22 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.00 |
Number of Notice(s) issued: 72 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 134 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 13-06-2016 | 11.425 | Seal coat work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
2. | 18-05-2016 | 8.325 | Rolling of premix carpet | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
3. | 18-05-2016 | 8.200 | Seal coat work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
4. | 30-04-2016 | 8.325 | P Q C work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
5. | 27-04-2016 | Chainage 0.400 | Laying of PC | Prem Prakash | AE | UDRP R&B Munsyari | See Pic |
6. | 26-04-2016 | 0.400 | Rolling of sealcoat | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
7. | 26-04-2016 | 0.400 | Seal coat work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
8. | 22-04-2016 | Lab | Bitumen extraction test of pc | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
9. | 22-04-2016 | 8+325 | Causeway khranja in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
10. | 22-04-2016 | 0+400 | Seal coat work in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
11. | 22-04-2016 | Lab | Bitumen extraction test of p c | Girjesh Kumar Dubey | QC | DSC4 R&B WB Munsyari | See Pic |
12. | 22-04-2016 | Lab | Bitumen extraction test | Girjesh Kumar Dubey | QC | DSC4 R&B WB Munsyari | See Pic |
13. | 22-04-2016 | 0+400 | Rolling of sealcoat | Girjesh Kumar Dubey | QC | DSC4 R&B WB Munsyari | See Pic |
14. | 21-04-2016 | 0.250 | Seal coat work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
15. | 19-04-2016 | 13.000 | Information board | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
16. | 14-04-2016 | 0.000 | Seal coat work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
17. | 14-04-2016 | 0.125 | P C work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
18. | 14-04-2016 | 0.025 | P C work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
19. | 14-04-2016 | 0.000 | P C work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
20. | 14-04-2016 | 0.650 | Seal coat in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
|
|