Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ganai Bankot motor road Work Completed
Project: UDRP-RB UID: 2322 Sanction Cost: 575.81  lakh Length: 13.000 KM.
District: Pithoragarh Block: Gangolihat Constituency: Gangolihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 12        Package Name:  UDRP/PWD/07/20/RD/012        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 06-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/20/RD/012      Contractor Name: ESPAN Infrastructure Ltd
Start Date:  20-08-2014      Intended Completion Date:  28-07-2016      Original End Date:  19-11-2015
Total Bond Cost: 48862983.5 (488.63 lakh)        Variation Cost: 5673825.41 (56.74 lakh)    Hence Total Bond Cost is   54536808.91 (545.37 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 781792 for 32 days        LD Analysis for Milestone2: calculated LD is Rs 171017 for 7 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works1511.00 m108.9720-08-201425-12-20151985.00 m1985.00 m22.37108.97
2.GSB/RBI/G-10.25 KM14.6625-02-201615-03-20160.20 KM0.20 KM3.0114.66
3.G-30.35 KM2.7625-09-201520-03-20160.35 KM0.35 KM0.572.76
4.PC/CC i/c Prime Coat, Tack Coat13.00 KM135.4615-04-201515-04-201613.00 KM13.00 KM27.81135.46
5.Cause Way17.00 No52.3725-11-201525-03-201617.00 No17.00 No10.7552.37
6.Culverts/Scupper 35.00 No60.4920-08-201415-03-201627.00 No27.00 No12.4260.49
7.longitudinal Drain10850.00 m31.5601-05-201515-03-20169350.00 m9350.00 m6.4831.56
8.Parapet1950.00 No77.6311-12-201511-04-20161140.00 No1140.00 No15.9477.63
9.Road Furniture116.00 No3.2615-02-201615-04-2016118.00 No118.00 No0.673.26
Total Amount: 487.16 100   487.16
Remarks: No Remarks       Work Program Made On: 25-09-2015        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.06-June-2015120.43  lakh
2.27-August-201545.61  lakh
3.30-September-201569.00  lakh
4.30-October-201544.19  lakh
5.21-December-201539.17  lakh
6.30-January-201640.21  lakh
7.09-March-201628.77  lakh
8.30-March-201614.97  lakh
9.30-April-201624.13  lakh
10.25-May-201647.99  lakh
11.26-October-201634.00  lakh
12.24-February-201721.74  lakh
Total 530.21  lakh
% Payment 97.2 %
Advance Amount:  48.86  lakh        Recovered Amount:  48.86  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 190   No. of Test Done : 212    No. of Test Passed : 190   No. of Test Failed : 22   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.00
Number of Notice(s) issued: 72

Mobile Pic Upload

Number of Pics Available on Web Repository: 134
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-06-201611.425Seal coat work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
2.18-05-20168.325Rolling of premix carpetPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
3.18-05-20168.200Seal coat work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
4.30-04-20168.325P Q C work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
5.27-04-2016Chainage 0.400Laying of PCPrem PrakashAEUDRP R&B Munsyari See Pic
6.26-04-20160.400Rolling of sealcoatPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
7.26-04-20160.400Seal coat work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
8.22-04-2016LabBitumen extraction test of pcDinesh KumarREDSC4 R&B WB Munsyari See Pic
9.22-04-20168+325Causeway khranja in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
10.22-04-20160+400Seal coat work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
11.22-04-2016LabBitumen extraction test of p cGirjesh Kumar DubeyQCDSC4 R&B WB Munsyari See Pic
12.22-04-2016LabBitumen extraction testGirjesh Kumar DubeyQCDSC4 R&B WB Munsyari See Pic
13.22-04-20160+400Rolling of sealcoatGirjesh Kumar DubeyQCDSC4 R&B WB Munsyari See Pic
14.21-04-20160.250Seal coat work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
15.19-04-201613.000Information boardPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
16.14-04-20160.000Seal coat work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
17.14-04-20160.125P C work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
18.14-04-20160.025P C work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
19.14-04-20160.000P C work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
20.14-04-20160.650Seal coat in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic