Didihat Aadichura
Work Completed
|
Project: |
UDRP-RB |
UID: |
2315 |
Sanction Cost: |
332.12 lakh |
Length:
|
8.500 KM. |
District: |
Pithoragarh |
Block: |
Didihat |
Constituency: |
Didihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 24
Package Name: 
UDRP/PWD/07/16/RD/024
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 03-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/16/RD/024
Contractor Name: Dwarika Projects Limited
|
Start Date: 11-07-2014
Intended Completion Date: 30-04-2018
Original End Date: 10-10-2015 |
Total Bond Cost: 100030227.5 (1000.3 lakh)
Variation Cost: 28359199.65 (283.59 lakh) Hence Total Bond Cost is 128389427.15 (1283.89 lakh)
|
Sub Project Cost: 320.98 lakh
Variation Cost of Sub Project: 13213799.38 (132.14 lakh)
Total Sub Project Cost:
453.12 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 600.00 m | 116.65 | 01-08-2014 | 30-09-2015 | 1614.00 m | 1614.00 m | 26.76 | 116.65 | 2. | G-3 | 1.48 KM | 8.72 | 01-01-2015 | 10-10-2015 | 1.88 KM | 1.88 KM | 2 | 8.72 | 3. | PC/CC i/c Prime Coat, Tack Coat | 6.00 KM | 107.62 | 15-09-2015 | 15-11-2015 | 6.50 KM | 6.50 KM | 24.69 | 107.62 | 4. | Cause Way | 4.00 No | 7.53 | 01-10-2014 | 15-03-2016 | 4.00 No | 4.00 No | 1.73 | 7.53 | 5. | Culverts/Scupper | 25.00 No | 115.21 | 01-10-2014 | 15-03-2016 | 24.00 No | 24.00 No | 26.43 | 115.21 | 6. | longitudinal Drain | 6000.00 m | 11.15 | 01-08-2014 | 08-03-2016 | 4250.00 m | 4250.00 m | 2.56 | 11.15 | 7. | Parapet | 1598.00 No | 65.73 | 01-09-2014 | 25-02-2016 | 1300.00 No | 1300.00 No | 15.08 | 65.73 | 8. | Road Furniture | 124.00 No | 3.28 | 10-02-2016 | 15-03-2016 | 123.00 No | 123.00 No | 0.75 | 3.28 |
Total Amount: |
435.89 |
|
100 |
435.89 |
|
Remarks:
No Remarks
Work Program Made On:
29-09-2014 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2014 | 16.06 lakh | 2. | 31-December-2014 | 61.88 lakh | 3. | 31-March-2015 | 77.97 lakh | 4. | 06-June-2015 | 44.81 lakh | 5. | 24-July-2015 | 9.06 lakh | 6. | 29-September-2015 | 100.55 lakh | 7. | 30-October-2015 | 19.79 lakh | 8. | 26-December-2015 | 7.26 lakh | 9. | 18-March-2016 | 14.85 lakh | 10. | 30-March-2016 | 2.41 lakh | 11. | 11-May-2016 | 7.26 lakh | 12. | 27-July-2016 | 1.67 lakh | 13. | 31-March-2017 | 18.39 lakh | 14. | 05-February-2018 | 16.99 lakh | 15. | 06-June-2018 | 30.48 lakh | 16. | 21-January-2019 | 3.68 lakh | 17. | 30-March-2019 | 4.46 lakh |
Total |
437.57 lakh |
% Payment | 96.57 % |
|
Advance Amount: 106.76 lakh
Recovered Amount: 106.76 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 130 No. of Test Done : 148 No. of Test Passed : 130 No. of Test Failed : 18 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.77 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 77 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 17-12-2016 | Ch-4+550 | Wire creat in progress | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
2. | 15-12-2016 | Ch-2+625 | Wire create in progress | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
3. | 29-11-2016 | Ch-3+050 | Site visit Chief sir SE sir EE Sir AE sir RE Sir JE sir | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
4. | 29-07-2016 | Ch-0+720 | Road opening communication by jcb | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
5. | 10-07-2016 | Ch-5+600 | Road block site visit AE sir and RE sir | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
6. | 10-07-2016 | Ch-6+950 | Site visit Ae sir and Re sir | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
7. | 10-07-2016 | Ch-6+950 | Road damage | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
8. | 10-07-2016 | Ch 0. 850 | Slip clearance | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
9. | 05-07-2016 | Ch-0+400 | Slip clearance | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
10. | 05-07-2016 | Ch-0+125 | Slip clearance | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
11. | 30-04-2016 | 7+00 | Checking of PC by EE Sir CME | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
12. | 30-04-2016 | 7+875 | Site visit by EE sir PIU | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
13. | 30-04-2016 | 7.875 | Site visit EE sir PIU | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
14. | 30-04-2016 | 7.900 | Site visit EE sir PIU | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
15. | 11-03-2016 | Ch-0+200 | White washing of parapet | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
16. | 11-03-2016 | 0.200 | Parapet white washing | Baldev Arya | Site Supervisor | DSC4 R&B WB Pithoragarh | See Pic |
17. | 06-03-2016 | 2+125 | Causeway | Girjesh Kumar Dubey | QC | DSC4 R&B WB Munsyari | See Pic |
18. | 06-03-2016 | 2+125 | Causeway under progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
19. | 24-02-2016 | Ch-0+000 | Slab casting | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
20. | 23-02-2016 | Ch-18+130 | White washing in parapet | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
|
|