Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Charma Jaurasi Lakhatigaon Agreement signed
Project: UDRP-RB UID: 2311 Sanction Cost: 1312.29  lakh Length: 18.851 KM.
District: Pithoragarh Block: Didihat Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 139        Package Name:  UDRP/PWD/07/RD/123        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/RD/123      Contractor Name: Panchghati Construction (JV)
Start Date:  21-11-2017      Intended Completion Date:  22-02-2019     
Total Bond Cost: 114682000.5 (1146.82 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 24599289 for 429 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence10.40 KM82.8621-11-201731-12-201818.85 KM16.00 KM6.1370.33
2.R/Wall, B/ Wall Type Protection works2000.00 m192.2001-12-201715-01-20192000.00 m1941.00 m16.26186.53
3.G-27.23 KM106.9415-12-201828-02-20197.23 KM0.70 KM0.910.35
4.G-37.48 KM60.1215-12-201828-02-20197.48 KM0.70 KM0.495.63
5.PC/CC i/c Prime Coat, Tack Coat18.85 KM282.6901-03-201930-04-201918.85 KM0.00 KM00.00
6.Cause Way9.00 No44.1101-05-201831-12-20189.00 No6.00 No2.5629.41
7.Culverts/Scupper 65.00 No248.8401-12-201731-12-201865.00 No57.00 No19.03218.21
8.longitudinal Drain18425.00 m47.8601-04-201815-01-201918425.00 m3000.00 m0.687.79
9.Crash Barrier195.00 m5.8501-02-201920-02-2019195.00 m0.00 m00.00
10.Parapet1238.00 No37.1601-10-201831-01-20191238.00 No308.00 No0.819.25
11.Road Furniture1082.00 No16.2001-02-201930-03-20191082.00 No0.00 No00.00
12.Other Allied Works & Finishing Work 4.00 Job21.9701-02-201930-04-20194.00 Job0.00 Job00.00
Total Amount: 1146.8 46.87   537.5
Remarks: No Remarks       Work Program Made On: 07-01-2018        Updation of work program on: 12-11-2018       
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.30-December-201722.10  lakh
2.16-February-201847.19  lakh
3.27-February-201883.14  lakh
4.27-March-201839.12  lakh
5.23-May-201837.44  lakh
6.31-August-201847.70  lakh
7.29-October-201840.72  lakh
8.27-December-201855.95  lakh
Total 373.36  lakh
% Payment 32.55 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill should be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 64   No. of Test Done : 64    No. of Test Passed : 64   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
Number of Notice(s) issued: 12

Mobile Pic Upload

Number of Pics Available on Web Repository: 66
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-01-20192+400G3 patch rolling workShoyab AliJEUDRP R&B Munsyari See Pic
2.05-01-20195+500 lab siteAIV test for g3 materialDeepak Kumar 3JEUDRP R&B Munsyari See Pic
3.20-12-20186+700Abutment masonary work in progressShoyab AliJEUDRP R&B Munsyari See Pic
4.20-12-20185+600Causeway R/W work in progressShoyab AliJEUDRP R&B Munsyari See Pic
5.20-12-20185+700Parapet curing work in progressShoyab AliJEUDRP R&B Munsyari See Pic
6.20-12-20185+300Drain excavation work in progressShoyab AliJEUDRP R&B Munsyari See Pic
7.20-12-20182+500Cooli wall work in progressShoyab AliJEUDRP R&B Munsyari See Pic
8.20-12-20182+600Scrapping work in progressShoyab AliJEUDRP R&B Munsyari See Pic
9.14-11-20185+200World Bank mission visit at charma-jorasi motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
10.14-11-20180+010World Bank mission visit at charma-jorasi motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
11.14-11-20188+400Kachha drain work on process at charma-jorasi motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
12.10-11-201813+400Site visit by DPM sir.Neeraj Kumar TewariAEUDRP R&B Munsyari See Pic
13.31-10-2018Ch-8+300Kutcha drain work on process at charma-jorasi motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
14.31-10-201818+850SE sir,AE sir visit at charma-jorasi motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
15.12-10-2018Ch-7+710Kacha drain work on progress at charma-jorasi motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
16.06-04-201814+450Site visit Se sir EE sir Re sirAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
17.05-04-201818+450Checking of information boardDinesh KumarREDSC4 R&B WB Munsyari See Pic
18.05-04-2018LabChecking of labDinesh KumarREDSC4 R&B WB Munsyari See Pic
19.05-04-20180+00Site visit by SE Sir EE Sir and AE SirDinesh KumarREDSC4 R&B WB Munsyari See Pic
20.29-03-201816+420Slab casting work in progressAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic