Charma Jaurasi Lakhatigaon
Work Completed
|
Project: |
UDRP-RB |
UID: |
2311 |
Sanction Cost: |
1312.29 lakh |
Length:
|
18.851 KM. |
District: |
Pithoragarh |
Block: |
Didihat |
Constituency: |
Didihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 139
Package Name: 
UDRP/PWD/07/RD/123
Tender Date: 07-04-2017
Current Status: Agreement signed
Achieved on Date: 14-11-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/RD/123
Contractor Name: Panchghati Construction (JV)
|
Start Date: 21-11-2017
Intended Completion Date: 15-06-2019
Original End Date: 22-02-2019 |
Total Bond Cost: 114682000.5 (1146.82 lakh)
Variation Cost: 16547030.24 (165.47 lakh) Hence Total Bond Cost is 131229030.74 (1312.29 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 27064952 for 472 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 18.85 KM | 104.86 | 21-11-2017 | 31-12-2018 | 18.85 KM | 18.85 KM | 7.99 | 104.86 | 2. | R/Wall, B/ Wall Type Protection works | 2000.00 m | 267.11 | 01-12-2017 | 15-01-2019 | 2000.00 m | 2000.00 m | 20.36 | 267.11 | 3. | GSB/RBI/G-1 | 0.40 KM | 12.24 | 01-05-2019 | 10-05-2019 | 0.40 KM | 0.40 KM | 0.93 | 12.24 | 4. | G-2 | 7.23 KM | 35.56 | 15-12-2018 | 15-05-2019 | 7.23 KM | 7.23 KM | 2.71 | 35.56 | 5. | G-3 | 7.48 KM | 80.98 | 15-12-2018 | 25-05-2019 | 7.48 KM | 7.48 KM | 6.17 | 80.98 | 6. | PC/CC i/c Prime Coat, Tack Coat | 18.85 KM | 301.78 | 01-03-2019 | 15-06-2019 | 18.85 KM | 18.85 KM | 23 | 301.78 | 7. | Cause Way | 9.00 No | 61.82 | 01-05-2018 | 31-12-2018 | 9.00 No | 9.00 No | 4.71 | 61.82 | 8. | Culverts/Scupper | 67.00 No | 268.45 | 01-12-2017 | 15-05-2019 | 67.00 No | 67.00 No | 20.46 | 268.45 | 9. | longitudinal Drain | 18425.00 m | 90.50 | 01-04-2018 | 31-05-2019 | 18425.00 m | 18425.00 m | 6.9 | 90.50 | 10. | Crash Barrier | 0.00 m | 0.00 | 01-02-2019 | 01-02-2019 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 1238.00 No | 42.87 | 01-10-2018 | 15-04-2019 | 1238.00 No | 1238.00 No | 3.27 | 42.87 | 12. | Road Furniture | 1082.00 No | 16.20 | 01-02-2019 | 10-06-2019 | 1082.00 No | 1082.00 No | 1.24 | 16.20 | 13. | Other Allied Works & Finishing Work | 4.00 Job | 29.94 | 01-02-2019 | 15-06-2019 | 4.00 Job | 4.00 Job | 2.28 | 29.94 |
Total Amount: |
1312.31 |
|
100 |
1312.31 |
|
Remarks:
No Remarks
Work Program Made On:
07-01-2018 } ?>
Updation of work program on:
13-05-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-December-2017 | 22.10 lakh | 2. | 16-February-2018 | 47.19 lakh | 3. | 27-February-2018 | 83.14 lakh | 4. | 27-March-2018 | 39.12 lakh | 5. | 23-May-2018 | 37.44 lakh | 6. | 31-August-2018 | 47.70 lakh | 7. | 29-October-2018 | 40.72 lakh | 8. | 27-December-2018 | 55.95 lakh | 9. | 15-February-2019 | 117.72 lakh | 10. | 28-February-2019 | 73.98 lakh | 11. | 30-March-2019 | 170.03 lakh | 12. | 30-April-2019 | 142.07 lakh | 13. | 17-May-2019 | 75.62 lakh | 14. | 31-May-2019 | 104.60 lakh | 15. | 22-June-2019 | 92.55 lakh | 16. | 30-June-2019 | 136.10 lakh |
Total |
1286.03 lakh |
% Payment |
97.99 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 64 No. of Test Done : 64 No. of Test Passed : 64 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
Number of Notice(s) issued: 12 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 98 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 25-05-2019 | 16+100 | PC WORK IN PROGRESS AT CHARMA-JAURASI-LAKHATIGAON MOTOR ROAD | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
2. | 17-05-2019 | 14+400 | Culvert slab casting work in progress | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
3. | 17-05-2019 | 14+400 | Culvert slab casting work in progress | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
4. | 17-05-2019 | 9+020 | K.C. drain excavation work in progress | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
5. | 17-05-2019 | 14+500 | Parapet casting work in progress | Shoyab Ali | JE | UDRP R&B Munsyari | See Pic |
6. | 15-05-2019 | 13+700 | Rolling over PC surface | Neeraj Kumar Tewari | AE | UDRP R&B Munsyari | See Pic |
7. | 10-05-2019 | 11+210 | PC work in progress at charma-jaurasi-lakhatigaon motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
8. | 07-05-2019 | 13+000 | Rolling over seal coat | Neeraj Kumar Tewari | AE | UDRP R&B Munsyari | See Pic |
9. | 27-04-2019 | 9+800 | PC work in progress at charma-jaurasi-lakhatigaon motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
10. | 22-04-2019 | 0+400 | PC work in progress at charma-jaurasi-lakhatigaon motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
11. | 21-04-2019 | 2+700 | PC work in progress at charma-jaurasi-lakhatigaon motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
12. | 20-04-2019 | 2+400 | Rolling over PC surface. | Neeraj Kumar Tewari | AE | UDRP R&B Munsyari | See Pic |
13. | 19-04-2019 | 1+400 | Seal coat laying work in progress at charma-jaurasi-lakhatigaon motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
14. | 12-04-2019 | 0+900 | PC Rolling | Neeraj Kumar Tewari | AE | UDRP R&B Munsyari | See Pic |
15. | 11-04-2019 | 0+300 | Seal coat at charma-jaurasi-lakhatigaon motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
16. | 08-04-2019 | 17+250 | Ambient air quality monitoring test at charma-jaurasi-lakhatigaon motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
17. | 08-04-2019 | 18+851 | Ambient noise level test at charma-jaurasi-lakhatigaon motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
18. | 08-04-2019 | 7+100 | Air noise test at charma-jaurasi-lakhatigaon motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
19. | 08-04-2019 | 5+100 | Air quality monitoring test monitoring test at charma-jaurasi-lakhatigaon motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
20. | 03-04-2019 | 3+800 | Seal coat laying work in process at charma-jaurasi-lakhatigaon motor road | Deepak Kumar 3 | JE | UDRP R&B Munsyari | See Pic |
|
|