Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Charma Jaurasi Lakhatigaon Work Completed
Project: UDRP-RB UID: 2311 Sanction Cost: 1312.29  lakh Length: 18.851 KM.
District: Pithoragarh Block: Didihat Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 139        Package Name:  UDRP/PWD/07/RD/123        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/RD/123      Contractor Name: Panchghati Construction (JV)
Start Date:  21-11-2017      Intended Completion Date:  15-06-2019      Original End Date:  22-02-2019
Total Bond Cost: 114682000.5 (1146.82 lakh)        Variation Cost: 16547030.24 (165.47 lakh)    Hence Total Bond Cost is   131229030.74 (1312.29 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 27064952 for 472 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence18.85 KM104.8621-11-201731-12-201818.85 KM18.85 KM7.99104.86
2.R/Wall, B/ Wall Type Protection works2000.00 m267.1101-12-201715-01-20192000.00 m2000.00 m20.36267.11
3.GSB/RBI/G-10.40 KM12.2401-05-201910-05-20190.40 KM0.40 KM0.9312.24
4.G-27.23 KM35.5615-12-201815-05-20197.23 KM7.23 KM2.7135.56
5.G-37.48 KM80.9815-12-201825-05-20197.48 KM7.48 KM6.1780.98
6.PC/CC i/c Prime Coat, Tack Coat18.85 KM301.7801-03-201915-06-201918.85 KM18.85 KM23301.78
7.Cause Way9.00 No61.8201-05-201831-12-20189.00 No9.00 No4.7161.82
8.Culverts/Scupper 67.00 No268.4501-12-201715-05-201967.00 No67.00 No20.46268.45
9.longitudinal Drain18425.00 m90.5001-04-201831-05-201918425.00 m18425.00 m6.990.50
10.Crash Barrier0.00 m0.0001-02-201901-02-20190.00 m0.00 m00.00
11.Parapet1238.00 No42.8701-10-201815-04-20191238.00 No1238.00 No3.2742.87
12.Road Furniture1082.00 No16.2001-02-201910-06-20191082.00 No1082.00 No1.2416.20
13.Other Allied Works & Finishing Work 4.00 Job29.9401-02-201915-06-20194.00 Job4.00 Job2.2829.94
Total Amount: 1312.31 100   1312.31
Remarks: No Remarks       Work Program Made On: 07-01-2018        Updation of work program on: 13-05-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-December-201722.10  lakh
2.16-February-201847.19  lakh
3.27-February-201883.14  lakh
4.27-March-201839.12  lakh
5.23-May-201837.44  lakh
6.31-August-201847.70  lakh
7.29-October-201840.72  lakh
8.27-December-201855.95  lakh
9.15-February-2019117.72  lakh
10.28-February-201973.98  lakh
11.30-March-2019170.03  lakh
12.30-April-2019142.07  lakh
13.17-May-201975.62  lakh
14.31-May-2019104.60  lakh
15.22-June-201992.55  lakh
16.30-June-2019136.10  lakh
Total 1286.03  lakh
% Payment 97.99 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 64   No. of Test Done : 64    No. of Test Passed : 64   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.00
Number of Notice(s) issued: 12

Mobile Pic Upload

Number of Pics Available on Web Repository: 98
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-05-201916+100PC WORK IN PROGRESS AT CHARMA-JAURASI-LAKHATIGAON MOTOR ROADDeepak Kumar 3JEUDRP R&B Munsyari See Pic
2.17-05-201914+400Culvert slab casting work in progressShoyab AliJEUDRP R&B Munsyari See Pic
3.17-05-201914+400Culvert slab casting work in progressShoyab AliJEUDRP R&B Munsyari See Pic
4.17-05-20199+020K.C. drain excavation work in progressShoyab AliJEUDRP R&B Munsyari See Pic
5.17-05-201914+500Parapet casting work in progressShoyab AliJEUDRP R&B Munsyari See Pic
6.15-05-201913+700Rolling over PC surfaceNeeraj Kumar TewariAEUDRP R&B Munsyari See Pic
7.10-05-201911+210PC work in progress at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
8.07-05-201913+000Rolling over seal coatNeeraj Kumar TewariAEUDRP R&B Munsyari See Pic
9.27-04-20199+800PC work in progress at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
10.22-04-20190+400PC work in progress at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
11.21-04-20192+700PC work in progress at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
12.20-04-20192+400Rolling over PC surface.Neeraj Kumar TewariAEUDRP R&B Munsyari See Pic
13.19-04-20191+400Seal coat laying work in progress at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
14.12-04-20190+900PC RollingNeeraj Kumar TewariAEUDRP R&B Munsyari See Pic
15.11-04-20190+300Seal coat at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
16.08-04-201917+250Ambient air quality monitoring test at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
17.08-04-201918+851Ambient noise level test at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
18.08-04-20197+100Air noise test at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
19.08-04-20195+100Air quality monitoring test monitoring test at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
20.03-04-20193+800Seal coat laying work in process at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic