Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Didihat Dunakot Work Completed
Project: UDRP-RB UID: 2301 Sanction Cost: 706.55  lakh Length: 19.060 KM.
District: Pithoragarh Block: Didihat Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: ODR
Procurement:
Package No.: 24        Package Name:  UDRP/PWD/07/16/RD/024        Tender Date: 22-02-2014        Current Status: Agreement signed        Achieved on Date: 03-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/16/RD/024      Contractor Name: Dwarika Projects Limited
Start Date:  11-07-2014      Intended Completion Date:  30-04-2018      Original End Date:  10-10-2015
Total Bond Cost: 100030227.5 (1000.3 lakh)        Variation Cost: 28359199.65 (283.59 lakh)    Hence Total Bond Cost is   128389427.15 (1283.89 lakh) 
Sub Project Cost: 679.32  lakh        Variation Cost of Sub Project: 15145400.27  (151.45 lakh)       Total Sub Project Cost:   830.77 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works650.00 m116.2201-09-201430-09-20151891.00 m1891.00 m17.28116.22
2.GSB/RBI/G-10.87 KM7.0401-11-201401-03-20160.25 KM0.25 KM1.057.04
3.G-21.05 KM5.9001-11-201405-03-20160.36 KM0.36 KM0.885.90
4.G-31.80 KM10.6301-11-201410-03-20160.32 KM0.32 KM1.5810.63
5.PC/CC i/c Prime Coat, Tack Coat16.08 KM199.8301-03-201515-05-201617.08 KM17.08 KM29.71199.83
6.Cause Way11.00 No29.2201-10-201425-02-20169.00 No9.00 No4.3529.22
7.Culverts/Scupper 42.00 No88.3001-10-201425-02-201636.00 No36.00 No13.1388.30
8.longitudinal Drain18050.00 m66.4201-09-201415-04-201614442.00 m14442.00 m9.8866.42
9.Parapet3648.00 No141.0501-09-201405-03-20162800.00 No2800.00 No20.97141.05
10.Road Furniture295.00 No7.9101-01-201615-05-2016281.00 No281.00 No1.187.91
Total Amount: 672.52 100   672.52
Remarks: No Remarks       Work Program Made On: 01-10-2014        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-201487.90  lakh
2.31-December-201467.31  lakh
3.31-March-2015198.07  lakh
4.06-June-201586.39  lakh
5.24-July-201561.31  lakh
6.29-September-2015102.50  lakh
7.30-October-201535.52  lakh
8.26-December-201511.34  lakh
9.18-March-20162.39  lakh
10.30-March-201623.11  lakh
11.11-May-201672.01  lakh
12.27-July-201639.85  lakh
13.31-March-201719.86  lakh
14.10-November-20175.90  lakh
15.06-June-20182.43  lakh
16.21-January-201911.56  lakh
Total 827.45  lakh
% Payment99.6 %
Advance Amount:  106.76  lakh        Recovered Amount:  106.76  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 130   No. of Test Done : 148    No. of Test Passed : 130   No. of Test Failed : 18   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.10
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 170
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.16-12-2016Ch-9+900Excavation of wire createAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
2.03-12-20169+300Site visit by CE sir pithoragarhDinesh KumarREDSC4 R&B WB Munsyari See Pic
3.03-09-2016Ch5+000Site visit AE sir RE SirAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
4.03-09-2016Ch 4+990Site visit AE sir RE SirAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
5.01-09-2016Ch 5.050Slip clearanceLaxman RamJEUDRP R&B Munsyari See Pic
6.02-08-2016Ch-9+900Site visit RE SirAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
7.21-07-2016Ch7+950Road opening communication by JcbAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
8.21-07-2016Ch-5+050Slip clearance in progressAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
9.15-07-2016Ch7+850Slip clearance in progressAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
10.11-07-2016Ch 5.875Slip clearance for opening communicationLaxman RamJEUDRP R&B Munsyari See Pic
11.11-07-2016Ch 5.425Slip clearanceLaxman RamJEUDRP R&B Munsyari See Pic
12.11-07-2016Ch 7.900SlipLaxman RamJEUDRP R&B Munsyari See Pic
13.11-07-2016Ch 7.700SlipLaxman RamJEUDRP R&B Munsyari See Pic
14.11-07-2016Ch 7.475SlipLaxman RamJEUDRP R&B Munsyari See Pic
15.11-07-2016Ch 7.475SlipLaxman RamJEUDRP R&B Munsyari See Pic
16.11-07-2016Ch 5.325SlipLaxman RamJEUDRP R&B Munsyari See Pic
17.11-07-2016Ch 5.325SlipLaxman RamJEUDRP R&B Munsyari See Pic
18.11-07-2016Ch 5.000Openings communicationLaxman RamJEUDRP R&B Munsyari See Pic
19.11-07-2016Ch 5.000Opening communicationLaxman RamJEUDRP R&B Munsyari See Pic
20.10-07-2016Ch 5.100Slip clearance for opening communicationLaxman RamJEUDRP R&B Munsyari See Pic