Didihat Dunakot
Work Completed
|
Project: |
UDRP-RB |
UID: |
2301 |
Sanction Cost: |
706.55 lakh |
Length:
|
19.060 KM. |
District: |
Pithoragarh |
Block: |
Didihat |
Constituency: |
Didihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 24
Package Name: 
UDRP/PWD/07/16/RD/024
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 03-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/16/RD/024
Contractor Name: Dwarika Projects Limited
|
Start Date: 11-07-2014
Intended Completion Date: 30-04-2018
Original End Date: 10-10-2015 |
Total Bond Cost: 100030227.5 (1000.3 lakh)
Variation Cost: 28359199.65 (283.59 lakh) Hence Total Bond Cost is 128389427.15 (1283.89 lakh)
|
Sub Project Cost: 679.32 lakh
Variation Cost of Sub Project: 15145400.27 (151.45 lakh)
Total Sub Project Cost:
830.77 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 650.00 m | 116.22 | 01-09-2014 | 30-09-2015 | 1891.00 m | 1891.00 m | 17.28 | 116.22 | 2. | GSB/RBI/G-1 | 0.87 KM | 7.04 | 01-11-2014 | 01-03-2016 | 0.25 KM | 0.25 KM | 1.05 | 7.04 | 3. | G-2 | 1.05 KM | 5.90 | 01-11-2014 | 05-03-2016 | 0.36 KM | 0.36 KM | 0.88 | 5.90 | 4. | G-3 | 1.80 KM | 10.63 | 01-11-2014 | 10-03-2016 | 0.32 KM | 0.32 KM | 1.58 | 10.63 | 5. | PC/CC i/c Prime Coat, Tack Coat | 16.08 KM | 199.83 | 01-03-2015 | 15-05-2016 | 17.08 KM | 17.08 KM | 29.71 | 199.83 | 6. | Cause Way | 11.00 No | 29.22 | 01-10-2014 | 25-02-2016 | 9.00 No | 9.00 No | 4.35 | 29.22 | 7. | Culverts/Scupper | 42.00 No | 88.30 | 01-10-2014 | 25-02-2016 | 36.00 No | 36.00 No | 13.13 | 88.30 | 8. | longitudinal Drain | 18050.00 m | 66.42 | 01-09-2014 | 15-04-2016 | 14442.00 m | 14442.00 m | 9.88 | 66.42 | 9. | Parapet | 3648.00 No | 141.05 | 01-09-2014 | 05-03-2016 | 2800.00 No | 2800.00 No | 20.97 | 141.05 | 10. | Road Furniture | 295.00 No | 7.91 | 01-01-2016 | 15-05-2016 | 281.00 No | 281.00 No | 1.18 | 7.91 |
Total Amount: |
672.52 |
|
100 |
672.52 |
|
Remarks:
No Remarks
Work Program Made On:
01-10-2014 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2014 | 87.90 lakh | 2. | 31-December-2014 | 67.31 lakh | 3. | 31-March-2015 | 198.07 lakh | 4. | 06-June-2015 | 86.39 lakh | 5. | 24-July-2015 | 61.31 lakh | 6. | 29-September-2015 | 102.50 lakh | 7. | 30-October-2015 | 35.52 lakh | 8. | 26-December-2015 | 11.34 lakh | 9. | 18-March-2016 | 2.39 lakh | 10. | 30-March-2016 | 23.11 lakh | 11. | 11-May-2016 | 72.01 lakh | 12. | 27-July-2016 | 39.85 lakh | 13. | 31-March-2017 | 19.86 lakh | 14. | 10-November-2017 | 5.90 lakh | 15. | 06-June-2018 | 2.43 lakh | 16. | 21-January-2019 | 11.56 lakh |
Total |
827.45 lakh |
% Payment | 99.6 % |
|
Advance Amount: 106.76 lakh
Recovered Amount: 106.76 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 130 No. of Test Done : 148 No. of Test Passed : 130 No. of Test Failed : 18 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.10 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 170 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 16-12-2016 | Ch-9+900 | Excavation of wire create | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
2. | 03-12-2016 | 9+300 | Site visit by CE sir pithoragarh | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
3. | 03-09-2016 | Ch5+000 | Site visit AE sir RE Sir | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
4. | 03-09-2016 | Ch 4+990 | Site visit AE sir RE Sir | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
5. | 01-09-2016 | Ch 5.050 | Slip clearance | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
6. | 02-08-2016 | Ch-9+900 | Site visit RE Sir | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
7. | 21-07-2016 | Ch7+950 | Road opening communication by Jcb | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
8. | 21-07-2016 | Ch-5+050 | Slip clearance in progress | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
9. | 15-07-2016 | Ch7+850 | Slip clearance in progress | Anmol Madan | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
10. | 11-07-2016 | Ch 5.875 | Slip clearance for opening communication | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
11. | 11-07-2016 | Ch 5.425 | Slip clearance | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
12. | 11-07-2016 | Ch 7.900 | Slip | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
13. | 11-07-2016 | Ch 7.700 | Slip | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
14. | 11-07-2016 | Ch 7.475 | Slip | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
15. | 11-07-2016 | Ch 7.475 | Slip | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
16. | 11-07-2016 | Ch 5.325 | Slip | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
17. | 11-07-2016 | Ch 5.325 | Slip | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
18. | 11-07-2016 | Ch 5.000 | Openings communication | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
19. | 11-07-2016 | Ch 5.000 | Opening communication | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
20. | 10-07-2016 | Ch 5.100 | Slip clearance for opening communication | Laxman Ram | JE | UDRP R&B Munsyari | See Pic |
|
|